General Assembly

 

Committee Bill No. 1

January Session, 2011

 

LCO No. 4531

 

*04531SB00001ET_*

Referred to Committee on Energy and Technology

 

Introduced by:

 

(ET )

 

AN ACT CONCERNING CONNECTICUT'S ENERGY FUTURE.

Be it enacted by the Senate and House of Representatives in General Assembly convened:

Section 1. (NEW) (Effective July 1, 2011) (a) There is established a Department of Energy and Environmental Protection, which shall, for the purposes of energy policy and regulation, have the following goals: (1) Reducing rates and decreasing costs for Connecticut's ratepayers, (2) ensuring the reliability and safety of our state's energy supply, (3) increasing the state's use of clean energy, and (4) creating jobs and developing the state's energy related economy. The department head shall be the Commissioner of Energy and Environmental Protection who shall be appointed by the Governor in accordance with the provisions of sections 4-5 to 4-8, inclusive, of the general statutes, with the powers and duties therein prescribed.

(b) The Department of Energy and Environmental Protection shall constitute a successor department to the Department of Environmental Protection and the Department of Public Utility Control in accordance with the provisions of sections 4-38d, 4-38e and 4-39 of the general statutes. The Department of Energy and Environmental Protection shall be divided into three bureaus, which shall include the Bureau of Energy, the Bureau of Environmental Protection and the Bureau of Public Utility Control. The bureaus shall further be divided into units or divisions, as the commissioner deems appropriate, which shall include, but not be limited to, the following units or divisions: (1) Energy research, (2) telecommunications and technology policy, and (3) conservation and renewable energy. The Bureau of Energy head shall be the energy bureau chief who shall have a background in energy conservation, generation and renewable energy and shall have no industry conflicts. The Bureau of Public Utility Control shall include a procurement manager whose duties shall include, but not be limited to, overseeing the procurement of electricity for standard service. There shall also be, within the department, an Office of the Ombudsman for the purpose of programmatic oversight. Said ombudsman shall communicate with policymakers, stakeholders and individuals affected by the department's implementation of energy policy. The ombudsman shall make findings and recommendations to the Commissioner of Energy and Environmental Protection who may implement such recommendations as appropriate. Annually, the ombudsman shall report in accordance with the provisions of section 11-4a of the general statutes to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

(c) Wherever the words "Commissioner of Environmental Protection" are used or referenced to in the following sections of the general statutes, the words "Commissioner of Energy and Environmental Protection" shall be substituted in lieu thereof: 3-7, 3-100, 4-5, 4-168, 4a-57, 4a-67d, 4b-15, 4b-15a, 4b-21, 5-238a, 7-121d, 7-131, 7-131a, 7-131d, 7-131e, 7-131f, 7-131g, 7-131i, 7-131l, 7-131t, 7-131u, 7-136h, 7-137c, 7-147, 7-151a, 7-151b, 7-245, 7-246, 7-246f, 7-247, 7-249a, 7-323o, 7-374, 7-487, 8-336f, 10-231b, 10-231c, 10-231d, 10-231g, 10-382, 10-388, 10-389, 10-391, 12-81, 12-81r, 12-107d, 12-217mm, 12-263m, 12-407, 12-412, 13a-80i, 13a-94, 13a-142a, 13a-142b, 13a-142e, 13a-175j, 13b-11a, 13b-31c, 13b-31e, 13b-38x, 13b-51, 13b-56, 13b-57, 13b-329, 14-21e, 14-21i, 14-21s, 14-65a, 14-67l, 14-80a, 14-100b, 14-164c, 14-164h, 14-164i, 14-164k, 14-164o, 15-11a, 15-121, 15-125, 15-127, 15-130, 15-133a, 15-133c, 15-140a, 15-140c, 15-140d, 15-140e, 15-140f, 15-140j, 15-140o, 15-140u, 15-140v, 15-141, 15-142, 15-143, 15-144, 15-145, 15-149a, 15-149b, 15-150a, 15-151, 15-154, 15-154a, 15-155, 15-155d, 15-156, 15-174, 16-2, 16-11a, 16-19e, 16-19g, 16-50c, 16-50d, 16-50j, 16-245, 16-261a, 16a-21a, 16a-27, 16a-35h, 16a-38k, 16a-103, 16a-106, 19a-35a, 19a-47, 19a-102a, 19a-330, 19a-341, 21-84b, 22-6c, 22-11h, 22-26cc, 22-81a, 22-91c, 22-350a, 22-358, 22a-1g, 22a-2a, 22a-5b, 22a-5c, 22a-6, 22a-6a, 22a-6b, 22a-6e, 22a-6f, 22a-6g, 22a-6h, 22a-6i, 22a-6j, 22a-6k, 22a-6l, 22a-6m, 22a-6n, 22a-6p, 22a-6s, 22a-6u, 22a-6v, 22a-6w, 22a-6y, 22a-6z, 22a-6aa, 22a-6bb, 22a-6cc, 22a-7a, 22a-7b, 22a-8a, 22a-10, 22a-13, 22a-16a, 22a-21, 22a-21b, 22a-21c, 22a-21d, 22a-21h, 22a-21j, 22a-22, 22a-25, 22a-26, 22a-27, 22a-27f, 22a-27l, 22a-27p, 22a-27r, 22a-27s, 22a-27t, 22a-27u, 22a-27v, 22a-27w, 22a-29, 22a-35a, 22a-38, 22a-42a, 22a-44, 22a-45a, 22a-45b, 22a-45c, 22a-45d, 22a-47, 22a-54, 22a-54a, 22a-56a, 22a-66a, 22a-66c, 22a-66j, 22a-66k, 22a-66l, 22a-66y, 22a-66z, 22a-68, 22a-93, 22a-106a, 22a-109, 22a-113m, 22a-113n, 22a-113t, 22a-114, 22a-115, 22a-118, 22a-122, 22a-133a, 22a-133b, 22a-133k, 22a-133l, 22a-133m, 22a-133n, 22a-133u, 22a-133v, 22a-133w, 22a-133y, 22a-133z, 22a-133aa, 22a-133bb, 22a-133ee, 22a-134, 22a-134e, 22a-134f, 22a-134g, 22a-134h, 22a-134i, 22a-134k, 22a-134l, 22a-134m, 22a-134n, 22a-134p, 22a-134q, 22a-134s, 22a-135, 22a-136, 22a-137, 22a-148, 22a-149, 22a-150, 22a-151, 22a-153, 22a-154, 22a-155, 22a-156, 22a-158, 22a-160, 22a-162, 22a-170, 22a-171, 22a-173, 22a-174c, 22a-174d, 22a-174e, 22a-174f, 22a-174g, 22a-174h, 22a-174i, 22a-174j, 22a-174k, 22a-174l, 22a-174m, 22a-180, 22a-182a, 22a-183, 22a-186, 22a-188, 22a-188a, 22a-191, 22a-191a, 22a-192, 22a-193, 22a-194a, 22a-194c, 22a-194f, 22a-198, 22a-199, 22a-200, 22a-200a, 22a-200b, 22a-200c, 22a-201a, 22a-201b, 22a-207, 22a-208a, 22a-208b, 22a-208d, 22a-208e, 22a-208f, 22a-208g, 22a-208h, 22a-208j, 22a-208o, 22a-208p, 22a-208q, 22a-208v, 22a-208w, 22a-208x, 22a-208y, 22a-208aa, 22a-208bb, 22a-209a, 22a-209b, 22a-209d, 22a-209f, 22a-209g, 22a-209h, 22a-209i, 22a-213a, 22a-214, 22a-219b, 22a-219c, 22a-219e, 22a-220, 22a-220a, 22a-220d, 22a-222, 22a-223, 22a-225, 22a-227, 22a-228, 22a-230, 22a-231, 22a-233a, 22a-235, 22a-235a, 22a-237, 22a-238, 22a-239, 22a-240, 22a-240a, 22a-241, 22a-241a, 22a-241b, 22a-241g, 22a-241h, 22a-241j, 22a-245, 22a-245a, 22a-245b, 22a-245d, 22a-248, 22a-250, 22a-250a, 22a-250b, 22a-250c, 22a-252, 22a-255b, 22a-255c, 22a-255d, 22a-255f, 22a-255h, 22a-256b, 22a-256c, 22a-256i, 22a-256m, 22a-256o, 22a-256q, 22a-256r, 22a-256v, 22a-256y, 22a-256aa, 22a-260, 22a-264, 22a-283, 22a-285a, 22a-285d, 22a-285e, 22a-285g, 22a-285h, 22a-285j, 22a-295, 22a-300, 22a-308, 22a-309, 22a-314, 22a-315, 22a-316, 22a-317, 22a-318, 22a-319, 22a-320, 22a-321, 22a-322, 22a-324, 22a-326, 22a-328, 22a-336, 22a-337, 22a-339a, 22a-339b, 22a-339c, 22a-339d, 22a-339f, 22a-339g, 22a-339h, 22a-342a, 22a-349, 22a-349a, 22a-351, 22a-352, 22a-354b, 22a-354c, 22a-354d, 22a-354e, 22a-354f, 22a-354h, 22a-354i, 22a-354j, 22a-354k, 22a-354l, 22a-354m, 22a-354p, 22a-354q, 22a-354t, 22a-354u, 22a-354v, 22a-354w, 22a-354x, 22a-354z, 22a-354aa, 22a-354bb, 22a-354cc, 22a-355, 22a-357, 22a-359, 22a-361, 22a-361a, 22a-363b, 22a-364, 22a-367, 22a-368a, 22a-378a, 22a-381, 22a-401, 22a-402, 22a-406, 22a-409, 22a-416, 22a-423, 22a-426, 22a-430b, 22a-430c, 22a-434a, 22a-439, 22a-439a, 22a-444, 22a-445, 22a-449, 22a-449d, 22a-449e, 22a-449f, 22a-449g, 22a-449h, 22a-449i, 22a-449j, 22a-449k, 22a-449l, 22a-449n, 22a-449p, 22a-449q, 22a-450a, 22a-452a, 22a-452e, 22a-453a, 22a-454c, 22a-457a, 22a-457b, 22a-458, 22a-459, 22a-461, 22a-462, 22a-463, 22a-471, 22a-472, 22a-474, 22a-475, 22a-482, 22a-485, 22a-497, 22a-500, 22a-501, 22a-517, 22a-521, 22a-522, 22a-523, 22a-524, 22a-525, 22a-526, 22a-527, 22a-601, 22a-602, 22a-604, 22a-605, 22a-613, 22a-616, 22a-626, 22a-627, 22a-629, 22a-630, 22a-634, 22a-637, 22a-638, 22a-902, 23-4, 23-5, 23-5b, 23-6, 23-7, 23-8, 23-8b, 23-9a, 23-9b, 23-10, 23-10b, 23-10c, 23-10e, 23-10i, 23-11, 23-12, 23-13, 23-14, 23-15a, 23-15b, 23-16, 23-16a, 23-17, 23-18, 23-20, 23-21, 23-22, 23-23, 23-24, 23-24a, 23-25, 23-26b, 23-26c, 23-26d, 23-26f, 23-26g, 23-30, 23-31, 23-32, 23-32a, 23-33, 23-37a, 23-37b, 23-41, 23-61a, 23-61b, 23-61f, 23-65, 23-65f, 23-65g, 23-65h, 23-65i, 23-65j, 23-65l, 23-65m, 23-65n, 23-65o, 23-65p, 23-65q, 23-73, 23-75, 23-77, 23-101, 23-102, 24-2, 25-32b, 25-32d, 25-32i, 25-33e, 25-33g, 25-33h, 25-33k, 25-33m, 25-33o, 25-34, 25-68b, 25-68i, 25-68k, 25-68l, 25-68m, 25-68n, 25-71, 25-72, 25-74, 25-76, 25-80, 25-83a, 25-94, 25-95, 25-97, 25-102a, 25-102d, 25-102e, 25-102f, 25-102m, 25-102t, 25-102ii, 25-102qq, 25-102xx, 25-109e, 25-109q, 25-131, 25-139, 25-155, 25-157, 25-178, 25-199, 25-199a, 25-201, 25-231, 26-1, 26-3, 26-3a, 26-3b, 26-3c, 26-5, 26-6, 26-6a, 26-7, 26-15, 26-17a, 26-18, 26-25a, 26-25b, 26-27, 26-27b, 26-27c, 26-27d, 26-28b, 26-29c, 26-30, 26-31, 26-31a, 26-40a, 26-40c, 26-46, 26-55, 26-65, 26-65a, 26-67b, 26-67c, 26-67e, 26-74, 26-80a, 26-86a, 26-86c, 26-86e, 26-91, 26-103, 26-107f, 26-107h, 26-107i, 26-115, 26-119, 26-141a, 26-141b, 26-141c, 26-142a, 26-142b, 26-157c, 26-157d, 26-157e, 26-157f, 26-157h, 26-157i, 26-159a, 26-186a, 26-192j, 26-297, 26-313, 26-314, 26-315, 26-316, 28-1b, 28-31, 29-32b, 32-1e, 32-1o, 32-9cc, 32-9dd, 32-9kk, 32-9ll, 32-11a, 32-23x, 32-242, 32-242a, 32-664, 38a-684, 47-46a, 47-59b, 47-65, 47-65a, 47-66, 47-66d, 47-66g, 51-164n, 52-192, 52-473a, 53-190, 53a-44a, 53a-54b and 53a-217e.

(d) Wherever the words "Department of Environmental Protection" are used or referred to in the following sections of the general statutes, the words "Department of Energy and Environmental Protection" shall be substituted in lieu thereof: 1-84, 1-206, 1-217, 2-20a, 4-38c, 4-66c, 4-66aa, 4-89, 4a-53, 4b-15, 5-142, 7-131e, 7-151a, 7-151b, 7-252, 8-387, 10-282, 10-291, 10-413, 10a-119e, 12-63e, 12-263m, 13a-142b, 13a-142c, 13a-142d, 13b-38a, 14-386, 15-129, 15-130a, 15-140e, 15-140f, 15-140j, 15-154, 15-155, 16-19h, 16-19o, 16-50j, 16-50k, 16-50p, 16-243q, 16-244d, 16-244j, 16-245l, 16-245y, 16-262m, 16-262n, 19a-197b, 19a-320, 20-420, 21-84b, 22-11f, 22-11g, 22-11h, 22-26cc, 22-81, 22-91e, 22-455, 22a-1d, 22a-2, 22a-2a, 22a-2c, 22a-5b, 22a-6, 22a-6f, 22a-6g, 22a-6l, 22a-6p, 22a-6r, 22a-6u, 22a-6x, 22a-6cc, 22a-10, 22a-11, 22a-20a, 22a-21, 22a-21a, 22a-21b, 22a-21c, 22a-21i, 22a-21j, 22a-21k, 22a-22, 22a-25, 22a-26, 22a-26a, 22a-27j, 22a-27l, 22a-27s, 22a-29, 22a-33, 22a-40, 22a-47a, 22a-58, 22a-61, 22a-66z, 22a-68, 22a-115, 22a-118, 22a-119, 22a-122, 22a-123, 22a-126, 22a-132, 22a-133v, 22a-133w, 22a-134i, 22a-135, 22a-170, 22a-174, 22a-174l, 22a-186, 22a-188a, 22a-196, 22a-198, 22a-200b, 22a-200c, 22a-200d, 22a-207, 22a-208a, 22a-209f, 22a-223, 22a-233a, 22a-239a, 22a-244, 22a-245a, 22a-247, 22a-248, 22a-250, 22a-255h, 22a-256m, 22a-256y, 22a-259, 22a-260, 22a-264, 22a-275, 22a-314, 22a-315, 22a-336, 22a-352, 22a-355, 22a-361, 22a-363b, 22a-416, 22a-426, 22a-446, 22a-449f, 22a-449l, 22a-449n, 22a-454a, 22a-475, 22a-477, 22a-509, 22a-521, 22a-601, 22a-629, 22a-630, 22a-635, 23-5c, 23-8, 23-8b, 23-10b, 23-10d, 23-15, 23-15b, 23-19, 23-20, 23-24a, 23-32a, 23-61a, 23-65f, 23-65h, 23-65i, 23-65k, 23-67, 23-68, 23-72, 23-73, 23-101, 23-102, 23-103, 25-32d, 25-33o, 25-33p, 25-37d, 25-37e, 25-37i, 25-43c, 25-102e, 25-102f, 25-128, 25-131, 25-157, 25-157a, 25-157b, 25-157n, 25-175, 25-201, 25-203, 25-206, 25-231, 26-6a, 26-15, 26-15a, 26-15b, 26-17a, 26-27b, 26-31, 26-40a, 26-55, 26-55a, 26-59, 26-66a, 26-66b, 26-72, 26-86f, 26-105, 26-142a, 26-157d, 26-192k, 26-300, 26-304, 26-314, 28-31, 29-28, 29-36f, 30-55a, 32-1e, 32-9t, 32-9cc, 32-9dd, 32-9kk, 32-9ll, 32-11a, 32-23d, 32-23x, 32-242, 32-242a, 32-726, 46b-220, 47-46a, 47-64, 52-557b, 53-204, 53-205, 53-206d, 53a-44a, 53a-217e, 54-56g and 54-143.

(e) Wherever the words "Department of Public Utility Control" are used or referred to in the following sections of the general statutes, the words "Department of Energy and Environmental Protection" shall be substituted in lieu thereof: 1-84, 1-84b, 2-20a, 2-71p, 4-38c, 4a-57, 4a-74, 4d-2, 4d-80, 7-223, 7-233t, 7-233ii, 8-387, 12-81q, 12-94d, 12-264, 12-265, 12-408b, 12-412, 12-491, 13a-82, 13a-126, 13a-126a, 13b-10a, 13b-37, 13b-43, 13b-44, 13b-387a, 15-96, 16-1, 16-1b, 16-2, 16-2a, 16-4, 16-6, 16-6a, 16-6b, 16-7, 16-8, 16-8a, 16-8b, 16-8c, 16-8d, 16-9, 16-9a, 16-10, 16-10a, 16-11, 16-12, 16-13, 16-14, 16-15, 16-16, 16-17, 16-18, 16-18a, 16-19, 16-19a, 16-19b, 16-19d, 16-19e, 16-19f, 16-19h, 16-19k, 16-19n, 16-19o, 16-19u, 16-19w, 16-19x, 16-19z, 16-19aa, 16-19bb, 16-19cc, 16-19dd, 16-19ee, 16-19ff, 16-19gg, 16-19jj, 16-19kk, 16-19mm, 16-19nn, 16-19oo, 16-19pp, 16-19qq, 16-19ss, 16-19tt, 16-19uu, 16-19vv, 16-20, 16-21, 16-23, 16-24, 16-25, 16-25a, 16-26, 16-27, 16-28, 16-29, 16-32, 16-32a, 16-32b, 16-32c, 16-32e, 16-32g, 16-33, 16-35, 16-41, 16-42, 16-43, 16-43a, 16-43d, 16-44, 16-44a, 16-45, 16-46, 16-47, 16-47a, 16-48, 16-49, 16-49e, 16-50c, 16-50d, 16-50f, 16-50k, 16-50aa, 16-216, 16-227, 16-231, 16-233, 16-234, 16-235, 16-238, 16-243, 16-243a, 16-243b, 16-243c, 16-243f, 16-243j, 16-243k, 16-243m, 16-243n, 16-243p, 16-243q, 16-243r, 16-243s, 16-243t, 16-243u, 16-243w, 16-244a, 16-244b, 16-244c, 16-244d, 16-244e, 16-244f, 16-244g, 16-244h, 16-244i, 16-244k, 16-244l, 16-245, 16-245a, 16-245b, 16-245c, 16-245d, 16-245e, 16-245g, 16-245l, 16-245o, 16-245p, 16-245q, 16-245s, 16-245t, 16-245u, 16-245v, 16-245w, 16-245x, 16-245y, 16-246, 16-246e, 16-246g, 16-247c, 16-247j, 16-247l, 16-247m, 16-247o, 16-247p, 16-247q, 16-247t, 16-249, 16-250, 16-250a, 16-250b, 16-256b, 16-256c, 16-256g, 16-256h, 16-256k, 16-258a, 16-258b, 16-258c, 16-259, 16-261, 16-261a, 16-262a, 16-262c, 16-262d, 16-262i, 16-262j, 16-262k, 16-262l, 16-262m, 16-262n, 16-262o, 16-262q, 16-262r, 16-262s, 16-262v, 16-262w, 16-262x, 16-265, 16-269, 16-271, 16-272, 16-273, 16-274, 16-275, 16-276, 16-278, 16-280a, 16-280b, 16-280d, 16-280e, 16-280f, 16-280h, 16-281a, 16-331, 16-331c, 16-331e, 16-331f, 16-331g, 16-331h, 16-331i, 16-331j, 16-331k, 16-331n, 16-331o, 16-331p, 16-331q, 16-331r, 16-331t, 16-331u, 16-331v, 16-331y, 16-331z, 16-331aa, 16-331cc, 16-331dd, 16-331ff, 16-331gg, 16-332, 16-333, 16-333a, 16-333b, 16-333e, 16-333f, 16-333g, 16-333h, 16-333i, 16-333l, 16-333n, 16-333o, 16-333p, 16-347, 16-348, 16-356, 16-357, 16-358, 16-359, 16a-3, 16a-3a, 16a-3b, 16a-3c, 16a-7b, 16a-7c, 16a-13b, 16a-37c, 16a-38n, 16a-38o, 16a-40b, 16a-40k, 16a-41, 16a-46, 16a-46b, 16a-46c, 16a-47a, 16a-47b, 16a-47c, 16a-47d, 16a-47e, 16a-49, 16a-103, 20-298, 20-309, 20-340, 20-340a, 20-341k, 20-341z, 20-357, 20-541, 22a-174j, 22a-174l, 22a-200c, 22a-256dd, 22a-266, 22a-358, 22a-475, 22a-478, 22a-479, 23-8b, 23-65, 25-32d, 25-33a, 25-33e, 25-33g, 25-33h, 25-33k, 25-33l, 25-33p, 25-37d, 25-37e, 26-141b, 28-1b, 28-24, 28-26, 28-27, 28-31, 29-282, 29-415, 32-80a, 32-222, 33-219, 33-221, 33-241, 33-951, 42-287, 43-44, 49-4c and 52-259a.

(f) Wherever the words "Secretary of the Office of Policy and Management" are used or referred to in the following sections of title 16a of the general statutes, the words "Commissioner of Energy and Environmental Protection" shall be substituted in lieu thereof: 16a-3, 16a-4d, 16a-6, 16a-14, 16a-22, 16a-22c, 16a-22h, 16a-22i, 16a-22j, 16a-23t, 16a-35c, 16a-35d, 16a-35h, 16a-37c, 16a-37f, 16a-37u, 16a-38, 16a-38a, 16a-38b, 16a-38i, 16a-38j, 16a-38k, 16a-38m, 16a-38o, 16a-39b, 16a-40b, 16a-41a, 16a-44b, 16a-46a, 16a-46c, 16a-46e, 16a-46f, 16a-102 and 16a-106.

(g) Wherever the words "Office of Policy and Management" are used or referred to in the following sections of title 16a of the general statutes, the words "Department of Energy and Environmental Protection" shall be substituted in lieu thereof: 16a-2, 16a-3, 16a-4d, 16a-6, 16a-7b, 16a-14, 16a-14e, 16a-20, 16a-22, 16a-22c, 16a-22h, 16a-22i, 16a-22j, 16a-23t, 16a-35c, 16a-35d, 16a-35g, 16a-35h, 16a-37c, 16a-37f, 16a-37u, 16a-37v, 16a-37w, 16a-38, 16a-38a, 16a-38b, 16a-38i, 16a-38j, 16a-38k, 16a-38l, 16a-38m, 16a-38n, 16a-38o, 16a-39b, 16a-40b, 16a-40f, 16a-41a, 16a-44b, 16a-46a, 16a-46c, 16a-46e, 16a-46f, 16a-46g, 16a-102 and 16a-106.

(h) Wherever the word "secretary" is used or referred to in the following sections of title 16a of the general statutes, the word "commissioner" shall be substituted in lieu thereof: 16a-2, 16a-3, 16a-4d, 16a-6, 16a-9, 16a-11, 16a-12, 16a-13, 16a-13a, 16a-13b, 16a-14, 16a-14a, 16a-14b, 16a-22, 16a-22c, 16a-22d, 16a-22e, 16a-22f, 16a-22h, 16a-22i, 16a-22j, 16a-23t, 16a-35c, 16a-35d, 16a-35h, 16a-37c, 16a-37f, 16a-37u, 16a-38, 16a-38a, 16a-38b, 16a-38i, 16a-38j, 16a-38k, 16a-38m, 16a-38o, 16a-39b, 16a-40b, 16a-41a, 16a-44b, 16a-45a, 16a-46a, 16a-46b, 16a-46c, 16a-46e, 16a-46f, 16a-102, 16a-106 and 16a-111.

(i) If the term "Department of Environmental Protection" or "Department of Public Utility Control" is used or referred to in any public or special act of 2011, or in any section of the general statutes which is amended in 2011, it shall be deemed to refer to the Department of Energy and Environmental Protection.

(j) If the term "Commissioner of Environmental Protection" is used or referred to in any public or special act of 2011, or in any section of the general statutes which is amended in 2011, it shall be deemed to refer to the Commissioner of Energy and Environmental Protection.

Sec. 2. Section 4-5 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

As used in sections 4-6, 4-7 and 4-8, the term "department head" means Secretary of the Office of Policy and Management, Commissioner of Administrative Services, Commissioner of Revenue Services, Banking Commissioner, Commissioner of Children and Families, Commissioner of Consumer Protection, Commissioner of Correction, Commissioner of Economic and Community Development, State Board of Education, Commissioner of Emergency Management and Homeland Security, Commissioner of Energy and Environmental Protection, Commissioner of Agriculture, Commissioner of Public Health, Insurance Commissioner, Labor Commissioner, Liquor Control Commission, Commissioner of Mental Health and Addiction Services, Commissioner of Public Safety, Commissioner of Social Services, Commissioner of Developmental Services, Commissioner of Motor Vehicles, Commissioner of Transportation, Commissioner of Public Works, Commissioner of Veterans' Affairs, Chief Information Officer, [the chairperson of the Public Utilities Control Authority,] the executive director of the Board of Education and Services for the Blind, the executive director of the Connecticut Commission on Culture and Tourism, and the executive director of the Office of Military Affairs. As used in sections 4-6 and 4-7, "department head" also means the Commissioner of Education.

Sec. 3. Section 4-38c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

There shall be within the executive branch of state government the following departments: Office of Policy and Management, Department of Administrative Services, Department of Revenue Services, Department of Banking, Department of Agriculture, Department of Children and Families, Department of Consumer Protection, Department of Correction, Department of Economic and Community Development, State Board of Education, Department of Emergency Management and Homeland Security, Department of Energy and Environmental Protection, Department of Public Health, Board of Governors of Higher Education, Insurance Department, Labor Department, Department of Mental Health and Addiction Services, Department of Developmental Services, Department of Public Safety, Department of Social Services, Department of Transportation, Department of Motor Vehicles, Department of Veterans' Affairs [,] and Department of Public Works. [and Department of Public Utility Control.]

Sec. 4. Section 4-67e of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The Secretary of the Office of Policy and Management shall coordinate the activity of the Commissioners of Public Health and Energy and Environmental Protection [and the chairperson of the Public Utilities Control Authority] in the following: (1) The review of the authority of each agency for consistency with the policies established by section 22a-380, (2) the preparation of a memorandum of understanding, not more than six months after October 1, 1991, intended to avoid inconsistency, overlap and redundancy in requirements and authority of each agency in water conservation issues, emergency contingency plans and regulatory authority under chapters 283, 446i, 446j and 474, (3) the review of exercise of regulatory authority over water companies, as defined in section 25-32a, to determine whether inconsistency, overlap or redundancy exist in the statutory requirements or regulatory authority of such agencies under chapters 283, 446i, 446j, and 474, (4) the assessment of the necessity of a memorandum of understanding to avoid such inconsistency, overlap or redundancy, and, if determined to be necessary, the preparation of such a memorandum by July 1, 1995, and (5) the development of recommendations for legislation and amendments to regulations to implement the provisions of a memorandum of understanding prepared pursuant to this section, or for consistency with the policies established by section 22a-380. There shall be a period of public review and comment on a memorandum of understanding prior to final agreement. On or before January 1, 1995, the [secretary] commissioner shall submit to the joint standing committees of the General Assembly having cognizance of matters relating to public health, energy and public utilities and the environment, written findings, and any recommendations, concerning the review and assessment conducted pursuant to subdivisions (3) and (4) of this section.

Sec. 5. Subsections (a) and (b) of section 4b-47 of the general statutes are repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) Prior to the sale or transfer of state land or any interest in state land by a state agency, department or institution, such agency, department or institution shall provide notice of such sale or transfer to the Council on Environmental Quality, the Secretary of the Office of Policy and Management and the Commissioner of Energy and Environmental Protection on a form approved by the [Council on Environmental Quality] Commissioner of Energy and Environmental Protection. Such notice shall be published in the Environmental Monitor and shall provide for a written public comment period of thirty days following publication of such notice, during which the public and state agencies may submit comments to the Secretary of the Office of Policy and Management. Such comments may include, but shall not be limited to, significant natural and recreational resources on such land and recommend means to preserve such natural or recreational resources. The Secretary of the Office of Policy and Management, in consultation with the Commissioner of Energy and Environmental Protection, shall (1) respond to any written comments received during such thirty-day comment period, and (2) publish such written comments along with the Office of Policy and Management's response to such written comments in the Environmental Monitor for a period of not less than fifteen days prior to the sale or transfer of the land.

(b) The Commissioner of Energy and Environmental Protection shall develop a policy for reviewing notices received from a state agency, department or institution, as described in subsection (a) of this section, and making a draft recommendation to the Secretary of the Office of Policy and Management as to whether all or a portion of the land or land interest referenced in such notice should be preserved by (1) transferring the land or land interest or granting a conservation easement therein to the Department of Energy and Environmental Protection, (2) imposing restrictions or conditions upon the transfer of the land or land interest, or (3) transferring all or a portion of the land or land interest, or granting a conservation easement interest therein, to an appropriate third party. Any such recommendations shall be accompanied by a report explaining the basis of the recommendations and shall include, where appropriate, a natural resource inventory. Such recommendations and report shall be published in the Environmental Monitor and shall provide for a written public comment period of thirty days following publication of such notice. The Commissioner of Energy and Environmental Protection shall (A) respond to any written comments received during such thirty-day comment period, (B) make a final recommendation to the Secretary of the Office of Policy and Management, and (C) publish such written comments along with the Department of Energy and Environmental Protection's response to such written comments including the department's final recommendation to the [secretary] commissioner in the Environmental Monitor. Following receipt of the final recommendation of the Commissioner of Energy and Environmental Protection, the Secretary of the Office of Policy and Management shall make the final determination as to the ultimate disposition of the land or interest. Such determination shall be published in the Environmental Monitor for a period of not less than fifteen days prior to the sale or transfer of such land or interest.

Sec. 6. Subsection (a) of section 4d-90 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There is established a Geospatial Information Systems Council consisting of the following members, or their designees: (1) The Secretary of the Office of Policy and Management; (2) the Commissioners of Energy and Environmental Protection, Economic and Community Development, Transportation, Public Safety, Public Health, Public Works, Agriculture, Emergency Management and Homeland Security and Social Services; (3) the Chief Information Officer of the Department of Information Technology; (4) the Chancellor of the Connecticut State University System; (5) the president of The University of Connecticut; (6) [the Executive Director of the Connecticut Siting Council; (7)] one member who is a user of geospatial information systems appointed by the president pro tempore of the Senate representing a municipality with a population of more than sixty thousand; [(8)] (7) one member who is a user of geospatial information systems appointed by the minority leader of the Senate representing a regional planning agency; [(9)] (8) one member who is a user of geospatial information systems appointed by the Governor representing a municipality with a population of less than sixty thousand but more than thirty thousand; [(10)] (9) one member who is a user of geospatial information systems appointed by the speaker of the House of Representatives representing a municipality with a population of less than thirty thousand; [(11)] (10) one member appointed by the minority leader of the House of Representatives who is a user of geospatial information systems; [(12) the chairperson of the Public Utilities Control Authority; (13)] (11) the Adjutant General of the Military Department; and [(14)] (12) any other persons the council deems necessary appointed by the council. The Governor shall select the chairperson from among the members. The chairperson shall administer the affairs of the council. Vacancies shall be filled by appointment by the authority making the appointment. Members shall receive no compensation for their services on said council, but shall be reimbursed for necessary expenses incurred in the performance of their duties. Said council shall hold one meeting each calendar quarter and such additional meetings as may be prescribed by council rules. In addition, special meetings may be called by the chairperson or by any three members upon delivery of forty-eight hours written notice to each member.

Sec. 7. Subsection (a) of section 4d-100 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There shall be a Broadband Internet Coordinating Council, which shall include representatives from both the private and public sectors. The council shall consist of ten members, two of whom shall be appointed by the Governor, two of whom shall be appointed by the president pro tempore of the Senate, two of whom shall be appointed by the speaker of the House of Representatives, one of whom shall be appointed by the majority leader of the Senate, one of whom shall be appointed by the majority leader of the House of Representatives, one of whom shall be appointed by the minority leader of the Senate and one of whom shall be appointed by the minority leader of the House of Representatives. One of each of the two members appointed by the Governor, the president pro tempore of the Senate and the speaker of the House of Representatives shall have specific expertise in the area of telecommunications. Members of the council shall serve without compensation, except for necessary expenses incurred in the performance of their duties. Members shall serve on the council for terms of two years each and no member shall serve for more than two consecutive terms. The [chairperson of the Public Utilities Control Authority, or the chairperson's designee, and the] Commissioner of Energy and Environmental Protection, or the commissioner's designee, Secretary of the Office of Policy and Management, or the secretary's designee, shall be an ex-officio [members] member of the council without vote and shall attend its meetings. Any member who fails to attend three consecutive meetings or fifty per cent of all meetings during any calendar year shall be deemed to have resigned. The president pro tempore of the Senate and the speaker of the House of Representatives shall jointly choose a chairperson and a vice-chairperson to act in the chairperson's absence.

Sec. 8. Section 16-1 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) Terms used in this title and in chapters 244, 244a, 244b, 245, 245a and 245b shall be construed as follows, unless another meaning is expressed or is clearly apparent from the language or context:

(1) "Authority" means the Public Utilities Control Authority and "department" means the Department of [Public Utility Control] Energy and Environmental Protection;

(2) "Commissioner" means a member of said authority;

(3) "Commissioner of Transportation" means the Commissioner of Transportation appointed under section 13b-3;

(4) "Public service company" includes electric, electric distribution, gas, telephone, telegraph, pipeline, sewage, water and community antenna television companies and holders of a certificate of cable franchise authority, owning, leasing, maintaining, operating, managing or controlling plants or parts of plants or equipment, and all express companies having special privileges on railroads within this state, but shall not include telegraph company functions concerning intrastate money order service, towns, cities, boroughs, any municipal corporation or department thereof, whether separately incorporated or not, a private power producer, as defined in section 16-243b, or an exempt wholesale generator, as defined in 15 USC 79z-5a;

(5) "Plant" includes all real estate, buildings, tracks, pipes, mains, poles, wires and other fixed or stationary construction and equipment, wherever located, used in the conduct of the business of the company;

(6) "Railroad company" includes every person owning, leasing, maintaining, operating, managing or controlling any railroad, or any cars or other equipment employed thereon or in connection therewith, for public or general use within this state;

(7) "Street railway company" includes every person owning, leasing, maintaining, operating, managing or controlling any street railway, or any cars or other equipment employed thereon or in connection therewith, for public or general use within this state;

(8) "Electric company" includes, until an electric company has been unbundled in accordance with the provisions of section 16-244e, every person owning, leasing, maintaining, operating, managing or controlling poles, wires, conduits or other fixtures, along public highways or streets, for the transmission or distribution of electric current for sale for light, heat or power within this state, or, engaged in generating electricity to be so transmitted or distributed for such purpose, but shall not include (A) a private power producer, as defined in section 16-243b, (B) an exempt wholesale generator, as defined in 15 USC 79z-5a, (C) a municipal electric utility established under chapter 101, (D) a municipal electric energy cooperative established under chapter 101a, (E) an electric cooperative established under chapter 597, or (F) any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act;

(9) "Gas company" includes every person owning, leasing, maintaining, operating, managing or controlling mains, pipes or other fixtures, in public highways or streets, for the transmission or distribution of gas for sale for heat or power within this state, or engaged in the manufacture of gas to be so transmitted or distributed for such purpose, but shall not include a person manufacturing gas through the use of a biomass gasification plant provided such person does not own, lease, maintain, operate, manage or control mains, pipes or other fixtures in public highways or streets, a municipal gas utility established under chapter 101 or any other gas utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act;

(10) "Water company" includes every person owning, leasing, maintaining, operating, managing or controlling any pond, lake, reservoir, stream, well or distributing plant or system employed for the purpose of supplying water to fifty or more consumers. A water company does not include homeowners, condominium associations providing water only to their members, homeowners associations providing water to customers at least eighty per cent of whom are members of such associations, a municipal waterworks system established under chapter 102, a district, metropolitan district, municipal district or special services district established under chapter 105, chapter 105a or any other general statute or any public or special act which is authorized to supply water, or any other waterworks system owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act;

(11) "Consumer" means any private dwelling, boardinghouse, apartment, store, office building, institution, mechanical or manufacturing establishment or other place of business or industry to which water is supplied by a water company;

(12) "Sewage company" includes every person owning, leasing, maintaining, operating, managing or controlling, for general use in any town, city or borough, or portion thereof, in this state, sewage disposal facilities which discharge treated effluent into any waterway of this state;

(13) "Pipeline company" includes every person owning, leasing, maintaining, operating, managing or controlling mains, pipes or other fixtures through, over, across or under any public land, water, parkways, highways, parks or public grounds for the transportation, transmission or distribution of petroleum products for hire within this state;

(14) "Community antenna television company" includes every person owning, leasing, maintaining, operating, managing or controlling a community antenna television system, in, under or over any public street or highway, for the purpose of providing community antenna television service for hire and shall include any municipality which owns or operates one or more plants for the manufacture or distribution of electricity pursuant to section 7-213 or any special act and seeks to obtain or obtains a certificate of public convenience and necessity to construct or operate a community antenna television system pursuant to section 16-331 or a certificate of cable franchise authority pursuant to section 16-331q. "Community antenna television company" does not include a certified competitive video service provider;

(15) "Community antenna television service" means (A) the one-way transmission to subscribers of video programming or information that a community antenna television company makes available to all subscribers generally, and subscriber interaction, if any, which is required for the selection of such video programming or information, and (B) noncable communications service. "Community antenna television service" does not include video service provided by a certified competitive video service provider;

(16) "Community antenna television system" means a facility, consisting of a set of closed transmission paths and associated signal generation, reception and control equipment that is designed to provide community antenna television service which includes video programming and which is provided in, under or over any public street or highway, for hire, to multiple subscribers within a franchise, but such term does not include (A) a facility that serves only to retransmit the television signals of one or more television broadcast stations; (B) a facility that serves only subscribers in one or more multiple unit dwellings under common ownership, control or management, unless such facility is located in, under or over a public street or highway; (C) a facility of a common carrier which is subject, in whole or in part, to the provisions of Subchapter II of Chapter 5 of the Communications Act of 1934, 47 USC 201 et seq., as amended, except that such facility shall be considered a community antenna television system and the carrier shall be considered a public service company to the extent such facility is used in the transmission of video programming directly to subscribers; or (D) a facility of an electric company which is used solely for operating its electric company systems. "Community antenna television system" does not include a facility used by a certified competitive video service provider to provide video service;

(17) "Video programming" means programming provided by, or generally considered comparable to programming provided by, a television broadcast station;

(18) "Noncable communications service" means any telecommunications service, as defined in section 16-247a, and which is not included in the definition of "cable service" in the Communications Act of 1934, 47 USC 522, as amended. Nothing in this definition shall be construed to affect service which is both authorized and preempted pursuant to federal law;

(19) "Public service motor vehicle" includes all motor vehicles used for the transportation of passengers for hire;

(20) "Motor bus" includes any public service motor vehicle operated in whole or in part upon any street or highway, by indiscriminately receiving or discharging passengers, or operated on a regular route or over any portion thereof, or operated between fixed termini, and any public service motor vehicle operated over highways within this state between points outside this state or between points within this state and points outside this state;

(21) "Cogeneration technology" means the use for the generation of electricity of exhaust steam, waste steam, heat or resultant energy from an industrial, commercial or manufacturing plant or process, or the use of exhaust steam, waste steam or heat from a thermal power plant for an industrial, commercial or manufacturing plant or process, but shall not include steam or heat developed solely for electrical power generation;

(22) "Renewable fuel resources" means energy sources described in subdivisions (26) and (27) of this subsection;

(23) "Telephone company" means a telecommunications company that provides one or more noncompetitive or emerging competitive services, as defined in section 16-247a;

(24) "Domestic telephone company" includes any telephone company which has been chartered by or organized or constituted within or under the laws of this state;

(25) "Telecommunications company" means a person that provides telecommunications service, as defined in section 16-247a, within the state, but shall not mean a person that provides only (A) private telecommunications service, as defined in section 16-247a, (B) the one-way transmission of video programming or other programming services to subscribers, (C) subscriber interaction, if any, which is required for the selection of such video programming or other programming services, (D) the two-way transmission of educational or instructional programming to a public or private elementary or secondary school, or a public or independent institution of higher education, as required by the department pursuant to a community antenna television company franchise agreement, or provided pursuant to a contract with such a school or institution which contract has been filed with the department, or (E) a combination of the services set forth in subparagraphs (B) to (D), inclusive, of this subdivision;

(26) "Class I renewable energy source" means (A) energy derived from solar power, wind power, a fuel cell, methane gas from landfills, ocean thermal power, wave or tidal power, low emission advanced renewable energy conversion technologies, a [run-of-the-river] hydropower facility [provided such facility has a generating capacity of not more than five megawatts, does not cause an appreciable change in the river flow, and began operation after July 1, 2003,] or a sustainable biomass facility with an average emission rate of equal to or less than .075 pounds of nitrogen oxides per million BTU of heat input for the previous calendar quarter, except that energy derived from a sustainable biomass facility with a capacity of less than five hundred kilowatts that began construction before July 1, 2003, may be considered a Class I renewable energy source, [or] (B) any electrical generation, including distributed generation, generated from a Class I renewable energy source;

(27) "Class II renewable energy source" means energy derived from a trash-to-energy facility, a biomass facility that began operation before July 1, 1998, provided the average emission rate for such facility is equal to or less than .2 pounds of nitrogen oxides per million BTU of heat input for the previous calendar quarter, or a run-of-the-river hydropower facility provided such facility has a generating capacity of not more than five megawatts, does not cause an appreciable change in the riverflow, and began operation prior to July 1, 2003;

(28) "Electric distribution services" means the owning, leasing, maintaining, operating, managing or controlling of poles, wires, conduits or other fixtures along public highways or streets for the distribution of electricity, or electric distribution-related services;

(29) "Electric distribution company" or "distribution company" means any person providing electric transmission or distribution services within the state, including an electric company, subject to subparagraph (F) of this subdivision, but does not include: (A) A private power producer, as defined in section 16-243b; (B) a municipal electric utility established under chapter 101, other than a participating municipal electric utility; (C) a municipal electric energy cooperative established under chapter 101a; (D) an electric cooperative established under chapter 597; (E) any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or special act; (F) after an electric company has been unbundled in accordance with the provisions of section 16-244e, a generation entity or affiliate of the former electric company; or (G) an electric supplier;

(30) "Electric supplier" means any person [, including an electric aggregator] or participating municipal electric utility that is licensed by the Department of [Public Utility Control] Energy and Environmental Protection in accordance with section 16-245, [that] as amended by this act, and provides electric generation services to end use customers in the state using the transmission or distribution facilities of an electric distribution company, regardless of whether or not such person takes title to such generation services, but does not include: (A) A municipal electric utility established under chapter 101, other than a participating municipal electric utility; (B) a municipal electric energy cooperative established under chapter 101a; (C) an electric cooperative established under chapter 597; (D) any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or special act; or (E) an electric distribution company in its provision of electric generation services in accordance with subsection (a) or, prior to January 1, 2004, subsection (c) of section 16-244c, as amended by this act;

(31) "Electric aggregator" means [(A) a person, municipality or regional water authority that] any person, municipality or regional water authority or the Connecticut Resources Recovery Authority, if such entity gathers together electric customers for the purpose of negotiating the purchase of electric generation services from an electric supplier, [or (B) the Connecticut Resources Recovery Authority, if it gathers together electric customers for the purpose of negotiating the purchase of electric generation services from an electric supplier,] provided such [person, municipality or authority] entity is not engaged in the purchase or resale of electric generation services, and provided further such customers contract for electric generation services directly with an electric supplier, and may include an electric cooperative established pursuant to chapter 597;

(32) "Electric generation services" means electric energy, electric capacity or generation-related services;

(33) "Electric transmission services" means electric transmission or transmission-related services;

(34) "Generation entity or affiliate" means a corporate affiliate or, as provided in subdivision (3) of subsection (a) of section 16-244e, a separate division of an electric company after unbundling has occurred pursuant to section 16-244e, that provides electric generation services;

(35) "Participating municipal electric utility" means a municipal electric utility established under chapter 101 or any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act, that is authorized by the department in accordance with section 16-245c to provide electric generation services to end use customers outside its service area, as defined in section 16-245c;

(36) "Person" means an individual, business, firm, corporation, association, joint stock association, trust, partnership or limited liability company;

(37) "Regional independent system operator" means the "ISO - New England, Inc.", or its successor organization as approved by the Federal Energy Regulatory Commission;

(38) "Certified telecommunications provider" means a person certified by the department to provide intrastate telecommunications services, as defined in section 16-247a, pursuant to sections 16-247f to 16-247h, inclusive;

(39) "Gas registrant" means a person registered to sell natural gas pursuant to section 16-258a;

(40) "Customer-side distributed resources" means (A) the generation of electricity from a unit with a rating of not more than sixty-five megawatts on the premises of a retail end user within the transmission and distribution system including, but not limited to, fuel cells, photovoltaic systems or small wind turbines, or (B) a reduction in the demand for electricity on the premises of a retail end user in the distribution system through methods of conservation and load management, including, but not limited to, peak reduction systems and demand response systems;

(41) "Federally mandated congestion charges" means any cost approved by the Federal Energy Regulatory Commission as part of New England Standard Market Design including, but not limited to, locational marginal pricing, locational installed capacity payments, any cost approved by the Department of [Public Utility Control] Energy and Environmental Protection to reduce federally mandated congestion charges in accordance with section 7-233y, this section, sections 16-19ss, 16-32f, as amended by this act, 16-50i, 16-50k, 16-50x, 16-243i to 16-243q, inclusive, as amended by this act, 16-244c, 16-244e, 16-245m, as amended by this act, 16-245n, as amended by this act, and 16-245z, as amended by this act, and section 21 of public act 05-1 of the June special session and reliability must run contracts;

(42) "Combined heat and power system" means a system that produces, from a single source, both electric power and thermal energy used in any process that results in an aggregate reduction in electricity use;

(43) "Grid-side distributed resources" means the generation of electricity from a unit with a rating of not more than sixty-five megawatts that is connected to the transmission or distribution system, which units may include, but are not limited to, units used primarily to generate electricity to meet peak demand;

(44) "Class III source" means the electricity output from combined heat and power systems with an operating efficiency level of no less than fifty per cent, determined quarterly on a rolling annual average basis, that are part of customer-side distributed resources developed at commercial and industrial facilities in this state on or after January 1, 2006, a waste heat recovery system installed on or after April 1, 2007, that produces electrical or thermal energy by capturing preexisting waste heat or pressure from industrial or commercial processes, or the electricity savings created in this state from conservation and load management programs begun on or after January 1, 2006;

(45) "Sustainable biomass" means biomass that is cultivated and harvested in a sustainable manner. "Sustainable biomass" does not mean construction and demolition waste, as defined in section 22a-208x, finished biomass products from sawmills, paper mills or stud mills, organic refuse fuel derived separately from municipal solid waste, or biomass from old growth timber stands, except where (A) such biomass is used in a biomass gasification plant that received funding prior to May 1, 2006, from the Renewable Energy Investment Fund established pursuant to section 16-245n, as amended by this act, or (B) the energy derived from such biomass is subject to a long-term power purchase contract pursuant to subdivision (2) of subsection (j) of section 16-244c entered into prior to May 1, 2006, (C) such biomass is used in a renewable energy facility that is certified as a Class I renewable energy source by the department until such time as the department certifies that any biomass gasification plant, as defined in subparagraph (A) of this subdivision, is operational and accepting such biomass, in an amount not to exceed one hundred forty thousand tons annually, is used in a renewable energy facility that was certified as a Class I renewable energy source by the department prior to December 31, 2007, and uses biomass, including construction and demolition waste as defined in section 22a-208x, from a Connecticut-sited transfer station and volume-reduction facility that generated biomass during calendar year 2007 that was used during calendar year 2007 to generate Class I renewable energy certificates, or (D) in the event there is no facility as described in subparagraph (A) or (C) of this subdivision accepting such biomass, in an amount not to exceed one hundred forty thousand tons annually, is used in one or more other renewable energy facilities certified either as a Class I or Class II renewable energy source by the department, provided such facilities use biomass, including construction and demolition waste as defined in said section 22a-208x, from a Connecticut-sited transfer station and volume-reduction facility that generated biomass during calendar year 2007 that was used during calendar year 2007 to generate Class I renewable energy certificates. Notwithstanding the provisions of subparagraphs (C) and (D) of this subdivision, the amount of biomass specified in said subparagraphs shall not apply to a biomass gasification plant, as defined in subparagraph (A) of this subdivision;

(46) "Video service" means video programming services provided through wireline facilities, a portion of which are located in the public right-of-way, without regard to delivery technology, including Internet protocol technology. "Video service" does not include any video programming provided by a commercial mobile service provider, as defined in 47 USC 332(d), any video programming provided as part of community antenna television service in a franchise area as of October 1, 2007, any video programming provided as part of and via a service that enables users to access content, information, electronic mail or other services over the public Internet;

(47) "Certified competitive video service provider" means an entity providing video service pursuant to a certificate of video franchise authority issued by the department in accordance with section 16-331e. "Certified competitive video service provider" does not mean an entity issued a certificate of public convenience and necessity in accordance with section 16-331 or the affiliates, successors and assigns of such entity or an entity issued a certificate of cable franchise authority in accordance with section 16-331p or the affiliates, successors and assignees of such entity;

(48) "Certificate of video franchise authority" means an authorization issued by the Department of [Public Utility Control] Energy and Environmental Protection conferring the right to an entity or person to own, lease, maintain, operate, manage or control facilities in, under or over any public highway to offer video service to any subscribers in the state;

(49) "Certificate of cable franchise authority" means an authorization issued by the Department of [Public Utility Control] Energy and Environmental Protection pursuant to section 16-331q conferring the right to a community antenna television company to own, lease, maintain, operate, manage or control a community antenna television system in, under or over any public highway to (A) offer community antenna television service in a community antenna television company's designated franchise area, or (B) use the public rights-of-way to offer video service in a designated franchise area. The certificate of cable franchise authority shall be issued as an alternative to a certificate of public convenience and necessity pursuant to section 16-331 and shall only be available to a community antenna television company under the terms specified in sections 16-331q to 16-331aa, inclusive;

(50) "Thermal energy transportation company" means any person authorized under any provision of the general statutes or special act to furnish heat or air conditioning or both, by means of steam, heated or chilled water or other medium, to lay and maintain mains, pipes or other conduits, and to erect such other fixtures necessary or convenient in and on the streets, highways and public grounds of any municipality to carry steam, heated or chilled water or other medium from such plant to the location to be served and to return the same; [and]

(51) "The Connecticut Television Network" means the General Assembly's state-wide twenty-four-hour state public affairs programming service, separate and distinct from community access channels; and

(52) "Commissioner of Energy and Environmental Protection" means the Commissioner of Energy and Environmental Protection appointed pursuant to title 4.

(b) Notwithstanding any provision of the general statutes, the terms "utility", "public utility" and "public service company" shall be deemed to include a community antenna television company and a holder of a certificate of cable franchise authority, except (1) as otherwise provided in sections 16-8, 16-27, 16-28 and 16-43, (2) that no provision of the general statutes, including but not limited to, the provisions of sections 16-6b and 16-19, shall subject a community antenna television company to regulation as a common carrier or utility by reason of providing community antenna television service, other than noncable communications service, as provided in Subchapter V-A of Chapter 5 of the Communications Act of 1934, 47 USC 521 et seq., as amended, and (3) that no provision of the general statutes, including but not limited to, sections 16-6b and 16-19, shall apply to community antenna television companies to the extent any such provision is preempted pursuant to any other provision of the Communications Act of 1934, 47 USC 151 et seq., as amended, any other federal act or any regulation adopted thereunder.

Sec. 9. Section 16-2 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There shall continue to be a Public Utilities Control Authority within the Department of Energy and Environmental Protection, which shall consist of five electors of this state, appointed by the Governor with the advice and consent of both houses of the General Assembly. Not more than three members of said authority in office at any one time shall be members of any one political party. On or before July 1, 1983, and quadrennially thereafter, the Governor shall appoint three members to the authority and on or before July 1, 1985, and quadrennially thereafter, the Governor shall appoint two members. All such members shall serve for a term of four years. The procedure prescribed by section 4-7 shall apply to such appointments, except that the Governor shall submit each nomination on or before May first, and both houses shall confirm or reject it before adjournment sine die. The commissioners shall be sworn to the faithful performance of their duties.

(b) The authority shall elect a chairperson and vice-chairperson each June for one-year terms starting on July first of the same year. The vice-chairperson shall perform the duties of the chairperson in his absence.

(c) Any matter coming before the authority may be assigned by the chairperson to a panel of three commissioners, not more than two of whom shall be members of the same political party. Except as otherwise provided by statute or regulation, the panel shall determine whether a public hearing shall be held on the matter, and may designate one or two of its members to conduct such hearing or appoint an examiner to ascertain the facts and report thereon to the panel. The decision of the panel, if unanimous, shall be the decision of the authority. If the decision of the panel is not unanimous, the matter shall be referred to the entire authority for decision.

(d) The commissioners of the authority shall serve full time and shall make full public disclosure of their assets, liabilities and income at the time of their appointment, and thereafter each member of the authority shall make such disclosure on or before July thirtieth of each year of such member's term, and shall file such disclosure with the office of the Secretary of the State. Each commissioner shall receive annually a salary equal to that established for management pay plan salary group seventy-five by the Commissioner of Administrative Services, except that the chairperson shall receive annually a salary equal to that established for management pay plan salary group seventy-seven.

(e) To insure the highest standard of public utility regulation, on and after October 1, 2007, any newly appointed commissioner of the authority shall have education or training and three or more years of experience in one or more of the following fields: Economics, engineering, law, accounting, finance, utility regulation, public or government administration, consumer advocacy, business management, and environmental management. On and after July 1, 1997, at least three of these fields shall be represented on the authority by individual commissioners at all times. Any time a commissioner is newly appointed, at least one of the commissioners shall have experience in utility customer advocacy.

[(f) The chairperson of the authority, with the consent of two or more other members of the authority, shall appoint an executive director, who shall be the chief administrative officer of the Department of Public Utility Control. The executive director shall be supervised by the chairperson of the authority, serve for a term of four years and annually receive a salary equal to that established for management pay plan salary group seventy-two by the Commissioner of Administrative Services. The executive director (1) shall conduct comprehensive planning with respect to the functions of the department; (2) shall coordinate the activities of the department; (3) shall cause the administrative organization of the department to be examined with a view to promoting economy and efficiency; (4) shall, in concurrence with the chairperson of the authority, organize the department into such divisions, bureaus or other units as he deems necessary for the efficient conduct of the business of the department and may from time to time abolish, transfer or consolidate within the department, any division, bureau or other units as may be necessary for the efficient conduct of the business of the department, provided such organization shall include any division, bureau or other unit which is specifically required by the general statutes; (5) shall, for any proceeding on a proposed rate amendment in which staff of the department are to be made a party pursuant to section 16-19j, determine which staff shall appear and participate in the proceedings and which shall serve the members of the authority; (6) may enter into such contractual agreements, in accordance with established procedures, as may be necessary for the discharge of his duties; and (7) may, subject to the provisions of section 4-32, and unless otherwise provided by law, receive any money, revenue or services from the federal government, corporations, associations or individuals, including payments from the sale of printed matter or any other material or services. The executive director shall require the staff of the department to have expertise in public utility engineering and accounting, finance, economics, computers and rate design. Subject to the provisions of chapter 67 and within available funds in any fiscal year, the executive director may appoint a secretary, and may employ such accountants, clerical assistants, engineers, inspectors, experts, consultants and agents as the department may require.]

[(g)] (f) No member of the authority or employee of the department shall, while serving as such, have any interest, financial or otherwise, direct or indirect, or engage in any business, employment, transaction or professional activity, or incur any obligation of any nature, which is in substantial conflict with the proper discharge of his duties or employment in the public interest and of his responsibilities as prescribed in the laws of this state, as defined in section 1-85; provided, no such substantial conflict shall be deemed to exist solely by virtue of the fact that a member of the authority or employee of the department, or any business in which such a person has an interest, receives utility service from one or more Connecticut utilities under the normal rates and conditions of service.

[(h)] (g) No member of the authority or employee of the department shall accept other employment which will either impair his independence of judgment as to his official duties or employment or require him, or induce him, to disclose confidential information acquired by him in the course of and by reason of his official duties.

[(i)] (h) No member of the authority or employee of the department shall wilfully and knowingly disclose, for pecuniary gain, to any other person, confidential information acquired by him in the course of and by reason of his official duties or employment or use any such information for the purpose of pecuniary gain.

[(j)] (i) No member of the authority or employee of the department shall agree to accept, or be in partnership or association with any person, or a member of a professional corporation or in membership with any union or professional association which partnership, association, professional corporation, union or professional association agrees to accept any employment, fee or other thing of value, or portion thereof, in consideration of his appearing, agreeing to appear, or taking any other action on behalf of another person before the authority, the Connecticut Siting Council, the Office of Policy and Management or the Commissioner of Environmental Protection.

[(k)] (j) No commissioner of the authority shall, for a period of one year following the termination of his or her service as a commissioner, accept employment: (1) By a public service company or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of public service companies; (2) by a certified telecommunications provider or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of persons, firms or corporations so certified; or (3) by an electric supplier or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of electric suppliers. No such commissioner who is also an attorney shall in any capacity, appear or participate in any matter, or accept any compensation regarding a matter, before the authority, for a period of one year following the termination of his or her service as a commissioner.

Sec. 10. Section 16-2c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

There is established a Division of Adjudication within the Department of [Public Utility Control] Energy and Environmental Protection. The staff of the division shall include but not be limited to, hearing examiners appointed pursuant to subsection (c) of section 16-2. The responsibilities of the division shall include, but not be limited to, hearing matters assigned under said subsection and advising the [chairperson of the Public Utilities Control Authority] Commissioner of Energy and Environmental Protection concerning legal issues.

Sec. 11. Subsections (a) and (b) of section 16-8 of the general statutes are repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The Department of [Public Utility Control] Energy and Environmental Protection may, in its discretion, delegate its powers, in specific cases, to one or more of its commissioners or to a hearing examiner to ascertain the facts and report thereon to the department. The department, or any commissioner thereof, in the performance of its duties or in connection with any hearing, or at the request of any person, corporation, company, town, borough or association, may summon and examine, under oath, such witnesses, and may direct the production of, and examine or cause to be produced and examined, such books, records, vouchers, memoranda, documents, letters, contracts or other papers in relation to the affairs of any public service company as it may find advisable, and shall have the same powers in reference thereto as are vested in magistrates taking depositions. If any witness objects to testifying or to producing any book or paper on the ground that such testimony, book or paper may tend to incriminate him, and the department directs such witness to testify or to produce such book or paper, and he complies, or if he is compelled so to do by order of court, he shall not be prosecuted for any matter concerning which he has so testified. The fees of witnesses summoned by the department to appear before it under the provisions of this section, and the fees for summoning witnesses shall be the same as in the Superior Court. All such fees, together with any other expenses authorized by statute, the method of payment of which is not otherwise provided, shall, when taxed by the department, be paid by the state, through the business office of the department, in the same manner as court expenses. The department may designate in specific cases a hearing examiner who may be a member of its technical staff or a member of the Connecticut Bar engaged for that purpose under a contract approved by the Secretary of the Office of Policy and Management to hold a hearing and make report thereon to the department. A hearing examiner so designated shall have the same powers as the department, or any commissioner thereof, to conduct a hearing, except that only a commissioner of the department shall have the power to grant immunity from prosecution to any witness who objects to testifying or to producing any book or paper on the ground that such testimony, book or paper may tend to incriminate him.

(b) (1) [In the performance of its duties the Department of Public Utility Control may establish management audit teams as a regular and continuing component of its staff. The management audit teams shall be composed of personnel with a professional background in accounting, engineering or any other training as the department may deem necessary to assure a competent and thorough review and audit.] The department may, within available appropriations, employ professional personnel to perform management audits. The department shall promptly establish such procedures as it deems necessary or desirable to provide for management audits to be performed on a regular or irregular schedule on all or any portion of the operating procedures and any other internal workings of any public service company, including the relationship between any public service company and a related holding company or subsidiary, consistent with the provisions of section 16-8c, provided no such audit shall be performed on a community antenna television company, except with regard to any noncable communications services which the company may provide, or when (A) such an audit is necessary for the department to perform its regulatory functions under the Communications Act of 1934, 47 USC 151, et seq., as amended from time to time, other federal law or state law, (B) the cost of such an audit is warranted by a reasonably foreseeable financial, safety or service benefit to subscribers of the company which is the subject of such an audit, and (C) such an audit is restricted to examination of the operating procedures that affect operations within the state.

(2) In any case where the department determines that an audit is necessary or desirable, it may (A) order the audit to be performed by one of its management audit teams, (B) require the affected company to perform the audit utilizing the company's own internal management audit staff as supervised by designated members of the department's staff or (C) require that the audit be performed under the supervision of designated members of the department's staff by an independent management consulting firm selected by the department, in consultation with the affected company. If the affected company has more than seventy-five thousand customers, such independent management consulting firm shall be of nationally-recognized stature. All reasonable and proper expenses of the audits, including, but not limited to, the costs associated with the audit firm's testimony at a public hearing or other proceeding, shall be borne by the affected companies and shall be paid by such companies at such times and in such manner as the department directs.

(3) For purposes of this section, a complete audit shall consist of (A) a diagnostic review of all functions of the audited company, which shall include, but not be limited to, documentation of the operations of the company, assessment of the company's system of internal controls, and identification of any areas of the company which may require subsequent audits, and (B) the performance of subsequent focused audits identified in the diagnostic review and determined necessary by the department. All audits performed pursuant to this section shall be performed in accordance with generally accepted management audit standards. The department shall adopt regulations in accordance with the provisions of chapter 54 setting forth such generally accepted management audit standards. Each audit of a community antenna television company shall be consistent with the provisions of the Communications Act of 1934, 47 USC 151, et seq., as amended from time to time, and of any other applicable federal law. The department shall certify whether a portion of an audit conforms to the provisions of this section and constitutes a portion of a complete audit.

(4) A complete audit of each portion of each gas, electric or electric distribution company having more than seventy-five thousand customers shall begin no less frequently than every six years, so that a complete audit of such a company's operations shall be performed every six years. Such an audit of each such company having more than seventy-five thousand customers shall be updated as required by the department.

(5) The results of an audit performed pursuant to this section shall be filed with the department and shall be open to public inspection. Upon completion and review of the audit, if the person or firm performing or supervising the audit determines that any of the operating procedures or any other internal workings of the affected public service company are inefficient, improvident, unreasonable, negligent or in abuse of discretion, the department may, after notice and opportunity for a hearing, order the affected public service company to adopt such new or altered practices and procedures as the department shall find necessary to promote efficient and adequate service to meet the public convenience and necessity. The department shall annually submit a report of audits performed pursuant to this section to the joint standing committee of the General Assembly having cognizance of matters relating to public utilities which report shall include the status of audits begun but not yet completed and a summary of the results of audits completed.

(6) All reasonable and proper costs and expenses, as determined by the department, of complying with any order of the department pursuant to this subsection shall be recognized by the department for all purposes as proper business expenses of the affected company.

(7) After notice and hearing, the department may modify the scope and schedule of a management audit of a telephone company which is subject to an alternative form of regulation so that such audit is consistent with that alternative form of regulation.

Sec. 12. Section 16-50j of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There is established a "Connecticut Siting Council", hereinafter referred to as the "council", which shall be within the Department of [Public Utility Control] Energy and Environmental Protection.

(b) Except for proceedings under chapter 445, this subsection and subsection (c) of this section, the council shall consist of: (1) The Commissioner of Energy and Environmental Protection, or his designee; (2) [the chairman, or his designee, of the Public Utilities Control Authority; (3)] one designee of the speaker of the House and one designee of the president pro tempore of the Senate; and [(4)] (3) five members of the public, to be appointed by the Governor, at least two of whom shall be experienced in the field of ecology, and not more than one of whom shall have affiliation, past or present, with any utility or governmental utility regulatory agency, or with any person owning, operating, controlling, or presently contracting with respect to a facility, a hazardous waste facility, as defined in section 22a-115, or an ash residue disposal area.

(c) For proceedings under chapter 445, subsection (b) of this section and this subsection, the council shall consist of (1) the Commissioners of Public Health and Public Safety or their designated representatives; (2) the designees of the speaker of the House of Representatives and the president pro tempore of the Senate as provided in subsection (b) of this section; (3) the five members of the public as provided in subsection (b) of this section; and (4) four ad hoc members, three of whom shall be electors from the municipality in which the proposed facility is to be located and one of whom shall be an elector from a neighboring municipality likely to be most affected by the proposed facility. The municipality most affected by the proposed facility shall be determined by the permanent members of the council. If any one of the five members of the public or of the designees of the speaker of the House of Representatives or the president pro tempore of the Senate resides (A) in the municipality in which a hazardous waste facility is proposed to be located for a proceeding concerning a hazardous waste facility or in which a low-level radioactive waste facility is proposed to be located for a proceeding concerning a low-level radioactive waste facility, or (B) in the neighboring municipality likely to be most affected by the proposed facility, the appointing authority shall appoint a substitute member for the proceedings on such proposal. If any appointee is unable to perform his duties on the council due to illness, or has a substantial financial or employment interest which is in conflict with the proper discharge of his duties under this chapter, the appointing authority shall appoint a substitute member for proceedings on such proposal. An appointee shall report any substantial financial or employment interest which might conflict with the proper discharge of his duties under this chapter to the appointing authority who shall determine if such conflict exists. If any state agency is the applicant, an appointee shall not be deemed to have a substantial employment conflict of interest because of employment with the state unless such appointee is directly employed by the state agency making the application. Ad hoc members shall be appointed by the chief elected official of the municipality they represent and shall continue their membership until the council issues a letter of completion of the development and management plan to the applicant.

(d) For proceedings under sections 22a-285d to 22a-285h, inclusive, the council shall consist of (1) the Commissioners of Public Health and Public Safety or their designated representatives; (2) the designees of the speaker of the House of Representatives and the president pro tempore of the Senate as provided in subsection (b) of this section, and (3) five members of the public as provided in subsection (b) of this section. If any one of the five members of the public or of the designees of the speaker of the House of Representatives or the president pro tempore of the Senate resides in the municipality in which an ash residue disposal area is proposed to be located the appointing authority shall appoint a substitute member for the proceedings on such proposal. If any appointee is unable to perform his duties on the council due to illness, or has a substantial financial or employment interest which is in conflict with the proper discharge of his duties under sections 22a-285d to 22a-285h, inclusive, the appointing authority shall appoint a substitute member for proceedings on such proposal. An appointee shall report any substantial financial or employment interest which might conflict with the proper discharge of his duties under said sections to the appointing authority who shall determine if such conflict exists. If any state agency is the applicant, an appointee shall not be deemed to have a substantial employment conflict of interest because of employment with the state unless such appointee is directly employed by the state agency making the application.

(e) The chairman of the council shall be appointed by the Governor from among the five public members appointed by him, with the advice and consent of the House or Senate, and shall serve as chairman at the pleasure of the Governor.

(f) The public members of the council, including the chairman, the members appointed by the speaker of the House and president pro tempore of the Senate and the four ad hoc members specified in subsection (c) of this section, shall be compensated for their attendance at public hearings, executive sessions, or other council business as may require their attendance at the rate of two hundred dollars, provided in no case shall the daily compensation exceed two hundred dollars.

(g) The council shall, in addition to its other duties prescribed in this chapter, adopt, amend, or rescind suitable regulations to carry out the provisions of this chapter and the policies and practices of the council in connection therewith, and appoint and prescribe the duties of such staff as may be necessary to carry out the provisions of this chapter. The chairman of the council, with the consent of five or more other members of the council, may appoint an executive director, who shall be the chief administrative officer of the Connecticut Siting Council. The executive director shall be exempt from classified service.

(h) Prior to commencing any hearing pursuant to section 16-50m, the council shall consult with and solicit written comments from the Department of Energy and Environmental Protection, the Department of Public Health, the Council on Environmental Quality, the Department of Agriculture, [the Department of Public Utility Control,] the Office of Policy and Management, the Department of Economic and Community Development and the Department of Transportation. In addition, the Department of Energy and Environmental Protection shall have the continuing responsibility to investigate and report to the council on all applications which prior to October 1, 1973, were within the jurisdiction of said Department of Environmental Protection with respect to the granting of a permit. Copies of such comments shall be made available to all parties prior to the commencement of the hearing. Subsequent to the commencement of the hearing, said departments and council may file additional written comments with the council within such period of time as the council designates. All such written comments shall be made part of the record provided by section 16-50o. Said departments and council shall not enter any contract or agreement with any party to the proceedings or hearings described in this section or section 16-50p, that requires said departments or council to withhold or retract comments, refrain from participating in or withdraw from said proceedings or hearings.

Sec. 13. Section 16a-3 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There is established a Connecticut Energy Advisory Board consisting of [fifteen] nine members, including [the Commissioner of Environmental Protection, the chairperson of the Public Utilities Control Authority, the Commissioner of Transportation,] the Consumer Counsel, [the Commissioner of Agriculture] the Attorney General, or the Attorney General's designee, and [the Secretary of the Office of Policy and Management, or their respective designees] a representative of the Connecticut Municipal Electric Energy Cooperative. The [Governor] president pro tempore of the Senate shall appoint a representative of an environmental organization knowledgeable in energy efficiency programs, a representative of a consumer advocacy organization and a representative of a state-wide business association. [The president pro tempore of the Senate shall appoint a representative of a chamber of commerce, a representative of a state-wide manufacturing association and a member of the public considered to be an expert in electricity, generation, procurement or conservation programs.] The speaker of the House of Representatives shall appoint a representative of low-income ratepayers, [a representative of state residents, in general, with expertise in energy issues] a representative of a state-wide manufacturing association and a member of the public considered to be an expert in electricity, generation, procurement or conservation programs. All appointed members shall serve in accordance with section 4-1a. No appointee may be employed by, or a consultant of, a public service company, as defined in section 16-1, or an electric supplier, as defined in section 16-1, or an affiliate or subsidiary of such company or supplier.

(b) The board shall (1) represent the state in regional energy system planning processes conducted by the regional independent system operator, as defined in section 16-1; (2) encourage representatives from the municipalities that are affected by a proposed project of regional significance to participate in regional energy system planning processes conducted by the regional independent system operator; (3) participate in a forecast proceeding conducted pursuant to subsection (a) of section 16-50r; (4) participate in a life-cycle proceeding conducted pursuant to subsection (b) of section 16-50r; and (5) review the procurement plan [submitted by the electric distribution companies] developed by the Department of Energy and Environmental Protection's Bureau of Energy pursuant to section 16a-3a, as amended by this act, and submit recommendations on the execution of such plan to the joint standing committee of the General Assembly having cognizance of matters relating to energy. The board shall conduct programmatic reviews and receive complaints from the public and businesses pertaining to matters within the jurisdiction of the Bureau of Energy.

(c) The board shall elect a chairman and a vice-chairman from among its members and shall adopt such rules of procedure as are necessary to carry out its functions.

(d) The board shall convene its first meeting not later than September 1, [2003] 2011. A quorum of the board shall consist of two-thirds of the members currently serving on the board.

(e) The board shall employ such staff as is required for the proper discharge of its duties. The board may also retain any third-party consultants it deems necessary to accomplish the goals set forth in subsection (b) of this section. The board shall annually submit to the Department of [Public Utility Control] Energy and Environmental Protection a proposal regarding the level of funding required for the discharge of its duties, which proposal shall be approved by the department either as submitted or as modified by the department.

(f) The Connecticut Energy Advisory Board shall report in accordance with the provisions of section 11-4a to the joint standing committee of the General Assembly having cognizance of matters relating to energy on such board's activities upon request of such committee.

[(f)] (g) The Connecticut Energy Advisory Board shall be within the [Office of Policy and Management] Department of Energy and Environmental Protection for administrative purposes only.

Sec. 14. Section 16a-3c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) On and after July 1, [2009] 2011, if the Department of [Public Utility Control] Energy and Environmental Protection does not receive and approve proposals pursuant to the requests for proposals processes, pursuant to section 16a-3b, sufficient to reach the goal set by the plan approved pursuant to section 16a-3a, as amended by this act, the department may order an electric distribution company to submit for the department's review in a contested case proceeding, in accordance with chapter 54, a proposal to build and operate an electric generation facility in the state. An electric distribution company shall be eligible to recover its prudently incurred costs consistent with the principles set forth in section 16-19e for any generation project approved pursuant to this section.

(b) On or before January 1, 2008, the department shall initiate a contested case proceeding to determine the costs and benefits of the state serving as the builder of last resort for the shortfall of megawatts from said request for proposal process.

Sec. 15. Section 16a-4 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The Secretary of the Office of Policy and Management shall employ, subject to the provisions of chapter 67, such staff as is required for the proper discharge of duties of the office as set forth in this chapter and sections 4-5, 4-124l, [4-124p,] 8-3b, 8-32a, 8-33a, 8-35a, 8-189, subsection (b) of section 8-206, sections 16a-20, 16a-102, 22a-352 and 22a-353. The secretary may adopt, pursuant to chapter 54, such regulations as are necessary to carry out the purposes of this chapter.

Sec. 16. Subsection (b) of section 16a-7b of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(b) No municipality other than a municipality operating a plant pursuant to chapter 101 or any special act and acting for purposes thereto may take an action to condemn, in whole or in part, or restrict the operation of any existing and currently operating energy facility, if such facility is first determined by the Department of [Public Utility Control] Energy and Environmental Protection, following a contested case proceeding, held in accordance with the provisions of chapter 54, to comprise a critical, unique and unmovable component of the state's energy infrastructure, unless the municipality first receives written approval from the department, [the Office of Policy and Management,] the Connecticut Energy Advisory Board and the Connecticut Siting Council that such taking would not have a detrimental impact on the state's or region's ability to provide a particular energy resource to its citizens.

Sec. 17. Subsection (a) of section 16a-7c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) Not later than fifteen days after receiving information pursuant to subsection (e) of section 16-50l, the Connecticut Energy Advisory Board shall publish such information in one or more newspapers or periodicals, as selected by the [board] Department of Energy and Environmental Protection.

Sec. 18. Section 16a-22c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

For the purposes of sections 16a-15 and 16a-22c to 16a-22g, inclusive:

(1) "Company" means any corporation, partnership, proprietorship or any other business, firm or commercial entity;

(2) "Petroleum products" means middle distillate, residual fuel oil, liquefied petroleum gas, motor gasoline, aviation gasoline or aviation turbine fuel, as defined in regulations which the [secretary] commissioner shall adopt in accordance with the provisions of chapter 54. Notwithstanding any provision of this subdivision to the contrary, "petroleum products" shall not include gasoline other than aviation gasoline, which is sold at retail in accordance with the provisions of chapter 250;

(3) ["Secretary" means the Secretary of the Office of Policy and Management, or his designee.] "Commissioner" means the Commissioner of Energy and Environmental Protection, or the commissioner's designee.

Sec. 19. Subsection (f) of section 16a-23t of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(f) The [chairperson of the Public Utilities Control Authority, or the chairperson's designee, the] Commissioner of Energy and Environmental Protection, or the commissioner's designee, Commissioner of Social Services, or the commissioner's designee, the chairperson of the Connecticut Energy Advisory Board, and the Secretary of the Office of Policy and Management, or the secretary's designee, shall constitute a Home Heating Oil Planning Council to address issues involving the supply, delivery and costs of home heating oil and state policies regarding the future of the state's home heating oil supply. The Secretary of the Office of Policy and Management shall convene the first meeting of the council.

Sec. 20. Section 16a-37w of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection shall, within available appropriations and in consultation with each state department, each constituent unit of the state system of higher education, as defined in section 10-1, the Judicial Branch and the Joint Committee on Legislative Management, establish a program designed to encourage the use of biodiesel blended heating fuel mixed from not more than ninety per cent ultra low sulfur number 2 heating oil and not less than ten per cent of biodiesel in state buildings and facilities under the custody and control of such department, unit, branch or committee. On or before January 1, [2008] 2012, the [secretary] commissioner shall prepare a plan for implementation of such program which shall include, but not be limited to, (1) identification of state buildings and facilities suitable for biodiesel blended heating fuel, (2) evaluation of energy efficiency and reliability of biodiesel blended heating fuel in such buildings and facilities, and (3) the availability and feasibility of exclusively using such fuels or fuel products, including agricultural products or waste yellow grease, produced in Connecticut.

Sec. 21. Subsection (b) of section 16a-38k of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(b) Not later than January 1, 2007, the [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection, in consultation with the Commissioner of Public Works [, the Commissioner of Environmental Protection] and the Commissioner of Public Safety, shall adopt regulations, in accordance with the provisions of chapter 54, to adopt state building construction standards that are consistent with or exceed the silver building rating of the Leadership in Energy and Environmental Design's rating system for new commercial construction and major renovation projects, as established by the United States Green Building Council, including energy standards that exceed those set forth in the 2004 edition of the American Society of Heating, Ventilating and Air Conditioning Engineers (ASHRAE) Standard 90.1 by no less than twenty per cent, or an equivalent standard, including, but not limited to, a two-globe rating in the Green Globes USA design program, and thereafter update such regulations as the [secretary] commissioner deems necessary.

Sec. 22. Section 16a-39 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) As used in this section:

(1) "Public building" means any building or portion thereof, other than an "exempted building", which is open to the public during normal business hours, including (A) any building which provides facilities or shelter for public assembly, (B) any inn, hotel, motel, sports arena, supermarket, transportation terminal, retail store, restaurant, or other commercial establishment which provides services or retails merchandise, and (C) any building owned or leased by the state of Connecticut or any political subdivision thereof, or by another state or political subdivision thereof and located in Connecticut, including libraries, museums, schools, hospitals, auditoriums, sports arenas and university buildings;

(2) "Exempted building" means (A) any building whose peak design rate of energy usage for all purposes is less than one watt per square foot of floor area for all purposes, (B) any building with neither a heating nor cooling system, and (C) any building owned or leased in whole or in part by the United States;

(3) "Commissioner" means the Commissioner of Public Works or his designee; and

[(4) "Secretary" means the Secretary of the Office of Policy and Management or his designee; and]

[(5)] (4) "Eligible building" means a building owned by a municipality, located within the state and not used for public education purposes.

(b) The commissioner, after consultation with the [secretary] Commissioner of Energy and Environmental Protection and with such advisory board as [said secretary] the Commissioner of Energy and Environmental Protection may appoint, shall adopt, in accordance with chapter 54, regulations establishing lighting standards for all public buildings. The members of any such advisory board shall receive neither compensation nor expenses for the performance of their duties.

(c) The lighting standards adopted pursuant to subsection (b) of this section shall provide for the maximum feasible energy efficiency of lighting equipment commensurate with other factors relevant to lighting levels and equipment, including, but not limited to, the purposes of the lighting, reasonable economic considerations in terms both of initial capital costs and of operating costs including nonenergy operating costs, reasonable budgetary considerations in terms of the feasibility of implementing changes which require a significant capital expenditure in a given time period, any constraints imposed on lighting equipment by the nature of the activities being carried out in the facility involved, considerations involving historic preservation or unusual architectural features, the amount of remaining useful lifetime which a particular structure would be expected to enjoy and the size of the building or portion of the building involved.

(d) The commissioner shall, upon the adoption of the regulations required by subsection (b) of this section, make random inspections of public buildings to monitor compliance with the standards established by such regulations. The commissioner may also inspect any public buildings against which complaints alleging violation of such standards have been received. The operator of a public building or portion thereof shall provide access to such inspectors at any reasonable time, including all times during which the facility is open to the public. If an inspector is denied access to a public building for the purposes of making an inspection in accordance with the provisions of this section, the commissioner may apply to the superior court for the judicial district wherein such building is located for injunctive or other equitable relief. If upon inspection it is determined that the lighting levels in a public building do not conform to such standards, the inspector shall make available to the owner or operator of such building, information regarding such standards and the economic and energy savings expected to result from compliance therewith. The owner or operator of a public building may, after having taken appropriate measures to render such building in compliance with such standards request a reinspection of such building by the commissioner. The commissioner may, upon such request or at his own discretion, conduct such reinspection and determine whether or not such building has been brought into compliance with such standards.

(e) The commissioner shall maintain a listing of all public buildings found to be in compliance with the lighting standards adopted pursuant to subsection (c) of this section.

(f) The [secretary] Commissioner of Energy and Environmental Protection may award lighting grants to municipalities for the purpose of improving the energy efficiency of lighting equipment in eligible buildings. All lighting grants shall be awarded based on an application, submitted by a municipality, which sets forth the lighting conservation measures to be implemented. Such measures shall meet the standards established pursuant to subsection (b) of this section and be consistent with the state energy policy, as set forth in section 16a-35k. When evaluating the applications submitted pursuant to this section and determining the amount of a lighting grant, the [secretary] Commissioner of Energy and Environmental Protection shall consider the energy savings and the payback period for the measures to be implemented and any other information which the [secretary] commissioner deems relevant. The funds for lighting grants shall be provided from proceeds of bonds issued for such purpose. The amount of each grant shall be not less than five thousand dollars but not more than fifty thousand dollars, provided the [secretary] Commissioner of Energy and Environmental Protection may award grants of less than five thousand dollars or more than fifty thousand dollars if the [secretary] Commissioner of Energy and Environmental Protection finds good cause to do so. All public service company incentive payments contributed to any energy conservation project at an eligible building shall be applied to pay the principal cost of that project.

Sec. 23. Section 16a-40 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

For the purposes of sections 16a-40a to 16a-40c, inclusive, and this section:

[(a)] (1) "Commissioner" means the Commissioner of [Economic and Community Development] Energy and Environmental Protection;

[(b)] (2) "Alternative energy device" means a wood-burning stove for space heating and any system or mechanism which uses wood, solar radiation, wind, water or geothermal resources as a source for space heating, water heating, cooling or generation of electrical energy. Such alternative energy device may be a new source or system, a replacement of an existing source or system or a supplement to an existing source or system; and

[(c)] (3) "Residential structure" means any building in which at least two-thirds of the usable square footage is used for dwelling purposes.

Sec. 24. Section 16a-41b of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There shall be a Low-Income Energy Advisory Board which shall consist of the following members: The [Secretary of the Office of Policy and Management or the secretary's designee] Commissioner of Energy and Environmental Protection or the commissioner's designee; the Commissioner of Social Services or the commissioner's designee; the executive director of the Commission on Aging; a representative of each electric and gas public service company designated by each such company; [the chairperson of the Department of Public Utility Control or] a commissioner of the Department of Public Utility Control; [designated by the chairperson;] the Consumer Counsel or the counsel's designee; the executive director of Operation Fuel; the executive director of Infoline; the director of the Connecticut Local Administrators of Social Services; the executive director of Legal Assistance Resource Center of Connecticut; the Connecticut president of AARP; a designee of the Norwich Public Utility; a designee of the Connecticut Petroleum Dealers Association; and a representative of the community action agencies administering energy assistance programs under contract with the Department of Social Services, designated by the Connecticut Association for Community Action.

(b) The Low-Income Energy Advisory Board shall advise and assist the [Office of Policy and Management] Department of Energy and Environmental Protection and the Department of Social Services in the planning, development, implementation and coordination of energy-assistance-related programs and policies and low-income weatherization assistance programs and policies, shall advise the Department of [Public Utility Control] Energy and Environmental Protection regarding the impact of utility rates and policies, and shall make recommendations to the General Assembly regarding (1) legislation and plans subject to legislative approval, and (2) administration of the block grant program authorized under the Low-Income Energy Assistance Act, as described in section 16a-41a, to ensure affordable access to residential energy services to low-income state residents.

(c) The [Secretary of the Office of Policy and Management or the person designated by the secretary] Commissioner of Energy and Environmental Protection or the commissioner's designee appointed pursuant to subsection (a) of this section shall be the chairperson of the board.

(d) The [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection shall convene the first meeting of the board not later than August 1, 2005. The [secretary] commissioner shall provide notice of meetings to the members of Low-Income Energy Advisory Board, provide space for such meetings, maintain minutes and publish reports of the board.

Sec. 25. Section 16a-46 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection shall be responsible for the development and implementation of a residential energy conservation service program in accordance with the provisions of this section, sections 16a-46a, 16a-46b and 16a-46c and applicable federal law. Participants in the program shall provide or arrange for low cost energy audits. No participant under subdivision (1) or (3) of section 16a-45a may be required to provide such services outside its authorized service area or area of normal operation. The residential energy conservation service program shall terminate on July 1, 2010.

(b) The [secretary, in consultation with the Department of Public Utility Control] commissioner, may adopt regulations, in accordance with chapter 54, with regard to the conduct and administration of such program. Not later than January first in 1996 and 1997, each participant shall submit a report to the [secretary] commissioner concerning the energy audits the participant provided or arranged for pursuant to this section. Not later than February first in 1996 and 1997, the [secretary] commissioner shall submit a report to the joint standing committee of the General Assembly having cognizance of matters relating to energy and technology concerning all energy audits provided or arranged for pursuant to this section.

Sec. 26. Section 16a-46c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The [Department of] Public Utility Control Authority shall exercise its regulatory responsibilities as they relate to the residential energy conservation service program within any program guidelines established by the [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection in regulations adopted under section 16a-46 and in the plan authorized under section 16a-46a. The [secretary] commissioner shall consult with the department in the development of the program. The department, in consultation with the [secretary] commissioner, may adopt regulations in accordance with chapter 54 concerning the conduct and administration of the program as it relates to the department's regulatory responsibilities.

Sec. 27. Section 21a-86a of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) On or before October 1, 1990, the Commissioner of Consumer Protection, in consultation with [the Secretary of the Office of Policy and Management, the chairperson of the Public Utilities Control Authority,] the State Building Inspector and the Commissioners of Public Health and Energy and Environmental Protection, shall adopt regulations in accordance with the provisions of chapter 54 establishing minimum efficiency standards for plumbing fixtures and other water-using devices, as appropriate.

(b) The maximum water use allowed in the regulations adopted under subsection (a) of this section for showerheads, urinals, faucets and replacement aerators manufactured or sold on or after October 1, 1990, shall be as follows: For showerheads, 2.5 gallons per minute; for urinals, 1.0 gallons per flush; for bathroom sinks, lavatory and kitchen faucets and replacement aerators, 2.5 gallons per minute, except that lavatories in restrooms of public facilities shall be equipped with outlet devices which limit the flow rate to a maximum of 0.5 gallons per minute. The maximum water use allowed in the regulations adopted under subsection (a) of this section for tank-type toilets, flushometer-valve toilets, flushometer-tank toilets and electromechanical hydraulic toilets manufactured or sold on or after January 1, 1992, shall be 1.6 gallons per flush, unless and until equivalent standards for similar types of toilets are adopted by the American National Standards Institute, Inc.

(c) Notwithstanding the provisions of subsection (b) of this section, the Commissioner of Consumer Protection, after consultation with [the Secretary of the Office of Policy and Management, the chairperson of the Public Utilities Control Authority,] the State Building Inspector and the Commissioners of Public Health and Energy and Environmental Protection, may increase the level of efficiency for plumbing fixtures upon determination that such increase would promote the conservation of water and energy and be cost-effective for consumers who purchase and use such fixtures. Any increased efficiency standard shall be effective one year after its adoption.

(d) The Commissioner of Consumer Protection, in consultation with the Secretary of the Office of Policy and Management, [the chairperson of the Public Utilities Control Authority,] the State Building Inspector and the Commissioners of Public Health and Energy and Environmental Protection, shall adopt regulations in accordance with the provisions of chapter 54 necessary to implement the provisions of sections 21a-86 to 21a-86g, inclusive. Such regulations shall provide for (1) the sale of plumbing fixtures which do not meet the standards if the commissioner determines that compliance is not feasible or an unnecessary hardship exists and (2) the sale of plumbing fixtures, including, but not limited to, antique reproduction plumbing fixtures, which do not meet the standards, provided such plumbing fixtures were in stock in a store located in the state before October 1, 1990, if a showerhead, urinal, faucet or replacement aerator or before January 1, 1992, if a tank-type toilet, flushometer-valve toilet, flushometer-tank toilet or electromechanical hydraulic toilet.

Sec. 28. Subsection (a) of section 21a-86c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The Commissioner of Consumer Protection, in consultation with [the Secretary of the Office of Policy and Management, the chairperson of the Public Utilities Control Authority,] the State Building Inspector and the Commissioners of Public Health and Energy and Environmental Protection, shall establish procedures for testing the efficiency of plumbing fixtures offered for retail sale if such procedures are not established in the State Building Code adopted pursuant to section 29-252.

Sec. 29. Section 22a-174l of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) Not later than sixty days after June 4, 2007, the Commissioner of Energy and Environmental Protection shall issue notice of intent to issue a general permit regarding the construction and operation of new or existing emergency engines and distributed generation resources that (1) generate no more than two megawatts of electricity; and (2) are approved by the Department of [Public Utility Control] Energy and Environmental Protection to participate in the markets administered by the regional independent system operator in accordance with subsection (b) of section 16-246g. Before issuing such permit, the sources to be covered by such permit shall provide the Commissioner of Energy and Environmental Protection with any information said commissioner deems necessary for the issuance of such permit. Any such general permit shall be issued in accordance with the provisions of subsection (k) of section 22a-174 and the general permit, and any authorization to operate under such permit, shall expire on the later of December 31, 2010, or ninety days after the energizing of the Middletown-Norwalk 345 kv transmission line approved by the Connecticut Siting Council. Notwithstanding this section, the Commissioner of Energy and Environmental Protection may [, in consultation with the chairperson of the Public Utilities Control Authority,] renew such general permit in accordance with the provisions of subsection (k) of section 22a-174 provided the Commissioner of Energy and Environmental Protection determines that renewal of such general permit is consistent with the requirements of subsection (b) of this section. The provisions of the general permit shall include, but not be limited to: Minimum setback provisions, limitations on hours of operation, requirements for air pollution controls certified to achieve a minimum reduction in emissions of nitrogen oxides of ninety per cent, directionally correct offsets at a ratio to be determined by the Commissioner of Energy and Environmental Protection, required control equipment, requirements for monitoring, reporting and recordkeeping, and any other requirement that said commissioner deems necessary. The provisions of this section are in addition to any other authority provided by law to said commissioner.

(b) When issuing or renewing the general permit pursuant to this section, the Commissioner of Energy and Environmental Protection shall [, in consultation with the chairperson of the Public Utilities Control Authority,] consider energy generation that will maximize the savings to the state's electric ratepayers and benefit the state's economy as a whole, but shall ensure that any emission increases resulting from the operation of sources covered by the general permit are offset by emission decreases from sources in Connecticut consistent with Connecticut's air quality attainment planning needs and requirements. The sources of decreases in emissions may include, but not be limited to, electric generation sources and demand response.

(c) On or before February 1, 2008, the Department of Energy and Environmental Protection [, in consultation with the Department of Public Utility Control,] shall report to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment regarding the economic and environmental benefits of the general permit issued pursuant to this section and the actions and measures taken pursuant to section 16-246g.

Sec. 30. Section 22a-1b of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The General Assembly directs that, to the fullest extent possible:

(a) Each state department, institution or agency shall review its policies and practices to insure that they are consistent with the state's environmental policy as set forth in sections 22a-1 and 22a-1a.

(b) (1) Each sponsoring agency shall, prior to a decision to prepare an environmental impact evaluation pursuant to subsection (c) of this section for an action which may significantly affect the environment, conduct an early public scoping process.

(2) To initiate an early public scoping process, the sponsoring agency shall provide notice on a form that has been approved by the [Council on Environmental Quality] Department of Energy and Environmental Protection, which shall include, but not be limited to, the date, time and location of any proposed public scoping meeting and the duration of the public comment period pursuant to subdivision (3) of this subsection, to the council, the Office of Policy and Management and any other state agency whose activities may reasonably be expected to affect or be affected by the proposed action.

(3) Members of the public and any interested state agency representatives may submit comments on the nature and extent of any environmental impacts of the proposed action during the thirty days following the publication of the notice of the early public scoping process pursuant to this section.

(4) A public scoping meeting shall be held at the discretion of the sponsoring agency or if twenty-five persons or an association having not less than twenty-five persons requests such a meeting within ten days of the publication of the notice in the Environmental Monitor. A public scoping meeting shall be held not less than ten days following the notice of the proposed action in the Environmental Monitor. The public comment period shall remain open for at least five days following the meeting.

(5) A sponsoring agency shall provide the following at a public scoping meeting: (A) A description of the proposed action; (B) a description of the purpose and need of the proposed action; (C) a list of the criteria for a site for the proposed action; (D) a list of potential sites for the proposed action; (E) the resources of any proposed site for the proposed action; (F) the environmental limitations of such sites; (G) potential alternatives to the proposed action; and (H) any information the sponsoring agency deems necessary.

(6) Any agency submitting comments or participating in the public scoping meeting pursuant to this section shall include, to the extent practicable, but not be limited to, information about (A) the resources of any proposed site for the proposed action, (B) any plans of the commenting agency that may affect or be affected by the proposed action, (C) any permits or approvals that may be necessary for the proposed action, and (D) any appropriate measures that would mitigate the impact of the proposed action, including, but not limited to, recommendations as to preferred sites for the proposed action or alternatives for the proposed action that have not been identified by the sponsoring agency.

(7) The sponsoring agency shall consider any comments received pursuant to this section or any information obtained during the public scoping meeting in selecting the proposed actions to be addressed in the environmental impact evaluation and shall evaluate in its environmental impact evaluation any substantive issues raised during the early public scoping process that pertain to a proposed action or site or alternative actions or sites.

(c) Each state department, institution or agency responsible for the primary recommendation or initiation of actions which may significantly affect the environment shall in the case of each such proposed action make a detailed written evaluation of its environmental impact before deciding whether to undertake or approve such action. All such environmental impact evaluations shall be detailed statements setting forth the following: (1) A description of the proposed action which shall include, but not be limited to, a description of the purpose and need of the proposed action, and, in the case of a proposed facility, a description of the infrastructure needs of such facility, including, but not limited to, parking, water supply, wastewater treatment and the square footage of the facility; (2) the environmental consequences of the proposed action, including cumulative, direct and indirect effects which might result during and subsequent to the proposed action; (3) any adverse environmental effects which cannot be avoided and irreversible and irretrievable commitments of resources should the proposal be implemented; (4) alternatives to the proposed action, including the alternative of not proceeding with the proposed action and, in the case of a proposed facility, a list of all the sites controlled by or reasonably available to the sponsoring agency that would meet the stated purpose of such facility; (5) an evaluation of the proposed action's consistency and each alternative's consistency with the state plan of conservation and development, an evaluation of each alternative including, to the extent practicable, whether it avoids, minimizes or mitigates environmental impacts, and, where appropriate, a description of detailed mitigation measures proposed to minimize environmental impacts, including, but not limited to, where appropriate, a site plan; (6) an analysis of the short term and long term economic, social and environmental costs and benefits of the proposed action; (7) the effect of the proposed action on the use and conservation of energy resources; and (8) a description of the effects of the proposed action on sacred sites or archaeological sites of state or national importance. In the case of an action which affects existing housing, the evaluation shall also contain a detailed statement analyzing (A) housing consequences of the proposed action, including direct and indirect effects which might result during and subsequent to the proposed action by income group as defined in section 8-37aa and by race, and (B) the consistency of the housing consequences with the long-range state housing plan adopted under section 8-37t. As used in this section, "sacred sites" and "archaeological sites" shall have the same meaning as in section 10-381.

(d) (1) The [Council on Environmental Quality] Department of Energy and Environmental Protection shall publish a document at least once a month to be called the Environmental Monitor which shall include any notices the council receives pursuant to sections 22a-1b to 22a-1i, inclusive, and shall include notice of the opportunity to request a public scoping meeting. Filings of such notices received by five o'clock p.m. on the first day of each month shall be published in the Environmental Monitor that is issued not later than ten days thereafter.

(2) The [Council on Environmental Quality] Department of Energy and Environmental Protection shall post the Environmental Monitor on its Internet site and distribute a subscription or a copy of the Environmental Monitor by electronic mail to any state agency, municipality or person upon request. The council shall also provide the Environmental Monitor to the clerk of each municipality for posting in its town hall.

(e) Any state department, institution or agency that conducts an environmental impact evaluation pursuant to subsection (c) of this section may enter into a contract with a person for the preparation of such evaluation, provided such department, institution or agency: (1) Guides such person in the preparation of such evaluation, (2) participates in the preparation of such evaluation, (3) independently reviews such evaluation prior to submitting such evaluation for comment pursuant to section 22a-1d, and (4) assures that any third party responsible for conducting any activity that is the subject of such evaluation is not a party to such contract. Such department, institution or agency may require any such third party responsible for conducting any activity that is the subject of such evaluation to remit a fee to such department, institution or agency in an amount sufficient to pay for the cost of hiring a person to prepare such evaluation in accordance with the provisions of this subsection.

Sec. 31. Section 22a-2 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) [There shall be a] The Department of Energy and Environmental Protection [which] shall have jurisdiction over all matters relating to the preservation and protection of the air, water and other natural resources of the state, the equitable distribution and conservation of energy, the regulation of public utilities and the development and administration of a state-wide energy policy. [Said department shall be under the direction of a Commissioner of Environmental Protection who shall be appointed in accordance with the provisions of sections 4-5 to 4-8, inclusive.]

(b) As used in this title and chapters 263, 268, 348, 360, 447, 448, 449, 452, 462, 474, 476, 477, 478, 479, 490 and 495, except where otherwise provided, "commissioner" means the Commissioner of Energy and Environmental Protection or his designated agent. The Commissioner of Energy and Environmental Protection shall have the authority to designate as his agent (1) any deputy commissioner to exercise all or part of the authority, powers and duties of said commissioner in his absence, (2) any deputy commissioner or any employee, assistant or agent employed pursuant to section 22a-4 to exercise such authority of the Commissioner of Energy and Environmental Protection as he delegates for the administration or enforcement of any applicable statute, regulation, permit or order, (3) the Commissioner of Public Safety and any local air pollution control official or agency to exercise such authority as the Commissioner of Energy and Environmental Protection delegates for the enforcement of any applicable statute, regulation, order or permit pertaining to air pollution, except the authority to render a final decision, after a hearing, assessing a civil penalty under said section 22a-6b, and (4) any municipal police department the authority to enforce the provisions of chapters 268 and 490.

(c) As used in this chapter, and chapters 263, 268, 348, 360, 440, 446d, 446i, 446k, 447, 448, 449, 452, 462, 474, 476, 477, 478, 479, 490 and 495, except where otherwise provided, "person" means any individual, firm, partnership, association, syndicate, company, trust, corporation, limited liability company, municipality, agency or political or administrative subdivision of the state, or other legal entity of any kind.

Sec. 32. Section 22a-5 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The commissioner shall carry out the energy and environmental policies of the state and shall have all powers necessary and convenient to faithfully discharge this duty. In addition to, and consistent with the environment policy of the state, the commissioner shall [(a)] (1) promote and coordinate management of water, land and air resources to assure their protection, enhancement and proper allocation and utilization; [(b)] (2) provide for the protection and management of plants, trees, fish, shellfish, wildlife and other animal life of all types, including the preservation of endangered species; [(c)] (3) provide for the protection, enhancement and management of the public forests, parks, open spaces and natural area preserves; [(d)] (4) provide for the protection, enhancement and management of inland, marine and coastal water resources, including, but not limited to, wetlands, rivers, estuaries and shorelines; [(e)] (5) provide for the prevention and abatement of all water, land and air pollution including, but not limited to, that related to particulates, gases, dust, vapors, noise, radiation, odors, nutrients and cooled or heated liquids, gases and solids; [(f)] (6) provide for control of pests and regulate the use, storage and disposal of pesticides and other chemicals which may be harmful to man, sea life, animals, plant life or natural resources; [(g)] (7) regulate the disposal of solid waste and liquid waste, including but not limited to, domestic and industrial refuse, junk motor vehicles, litter and debris, which methods shall be consistent with sound health, scenic environmental quality and land use practices; [(h)] (8) regulate the storage, handling and transportation of solids, liquids and gases which may cause or contribute to pollution; [and (i)] (9) provide for minimum state-wide standards for the mining, extraction, excavation or removal of earth materials of all types; (10) provide for the highest standards of public utility regulation and the protection of consumers; (11) provide for the equitable distribution and conservation of energy; (12) provide for the conservation of energy resources by avoiding unnecessary and wasteful consumption; (13) provide for the consumption of energy resources in the most efficient manner feasible; (14) provide for the development and use of renewable energy resources, such as solar and wind energy, to the maximum practicable extent; (15) diversify the state's energy supply; (16) whenever practicable, replace energy resources vulnerable to interruption due to circumstances beyond the state's control with energy sources that are less vulnerable to such interruption; (17) assist citizens and businesses in implementing measures to reduce energy consumption and energy costs; (18) ensure that low-income households can meet essential energy needs; (19) maintain planning and preparedness capabilities necessary to deal effectively with future energy supply interruptions; and (20) whenever available energy alternatives are equivalent, give preference to capacity additions for conservation and load management.

Sec. 33. Section 22a-11 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

There shall be a Council on Environmental Quality which shall be within the Department of Energy and Environmental Protection. [for administrative purposes only.] Said council shall consist of nine members, five to be appointed by the Governor, two to be appointed by the speaker of the House of Representatives and two to be appointed by the president pro tempore of the Senate. No member shall be allowed to serve more than eight years of any twelve-year period. The Governor shall fill any vacancy by appointment for the unexpired portion of the term vacated. The chairman of said council shall be selected by the Governor. Members of said council shall receive no compensation for their services thereon, but shall be reimbursed for necessary expenses in the performance of their duties. Said council shall hold one meeting each month and such additional meetings as may be prescribed by council rules. In addition, special meetings may be called by the chairman or by any three members upon delivery of forty-eight hours' written notice to each member. Five members shall constitute a quorum and not fewer than three votes shall be required for any final determination of said council. [The council may employ an executive director, exclusive of the provisions of chapter 67 and such additional staff and consultants as may be necessary to carry out its duties, within available appropriations.]

Sec. 34. Subsection (e) of section 22a-119 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(e) Prior to commencing any hearing pursuant to this section the council shall consult with and solicit written comments from the Departments of Energy and Environmental Protection, Public Health, [Public Utility Control,] Economic and Community Development, Public Safety and Transportation, the Office of Policy and Management and the Council on Environmental Quality. Copies of comments submitted by such agencies shall be available to all parties prior to commencement of the public hearing. Agencies consulted may file additional comments within thirty days of the conclusion of the hearing and such additional comments shall be a part of the record.

Sec. 35. Section 22a-198 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) On and after January 1, 2005, the owner or operator of a Title IV source that is also an affected unit or units shall:

(1) Combust liquid fuel, gaseous fuel, solid fuel or a combination of each provided that each fuel possesses a fuel sulfur limit equal to or less than 0.3 per cent sulfur, by weight (dry basis); or

(2) Meet an average emission rate equal to or less than 0.33 pounds SO2 per MMBtu for each calendar quarter for an affected unit at the premises; or

(3) Meet an average emission rate equal to or less than 0.3 pounds SO2 per MMBtu calculated for each calendar quarter, if such owner or operator averages the emissions from two or more affected units at the premises.

(b) On and after January 1, 2005, no owner or operator of a Title IV source that is also an affected unit or units may use SO2 DERCs or SO2 allowances to comply with the requirements of subsection (a) of this section except if the Commissioner of Environmental Protection requires the owner or operator of an affected unit or units using a low-sulfur fuel to comply with subdivision (1) of subsection (a) of this section to offset excess SO2 emissions that were emitted during a suspension period, as described in subsection (c) of this section, through the purchase or retirement of such SO2 DERCs or SO2 allowances.

(c) The Commissioner of Energy and Environmental Protection may suspend the requirements of subdivision (1) of subsection (a) of this section for the owner or operator of any affected unit using a low-sulfur fuel, including a low-sulfur solid fuel. Such suspension shall be made only when the commissioner finds that the availability of fuel that complies with such requirements is inadequate to meet the needs of residential, commercial and industrial users in this state and that such inadequate supply constitutes an emergency, provided such suspension shall not exceed the period that the inadequate supply constitutes an emergency. Any such suspension by the commissioner shall not suspend or alter the sulfur dioxide average emission rate requirements that are in effect as of May 2, 2002. The Commissioner of Energy and Environmental Protection shall specify in writing the period of time that such suspension shall be in effect and shall provide notice of such suspension to the joint standing committees of the General Assembly having cognizance of matters relating to the environment and energy and technology. No later than thirty days after the termination of such suspension, the owner or operator of an affected unit or units shall report to the commissioner, in writing, the amount of SO2 emissions in excess of those that would have occurred if the use of compliant fuel at such affected unit or units had not been interrupted. If such excess SO2 emissions from any premises exceed fifty tons, the commissioner shall require that the owner or operator of such affected unit or units offset such SO2 emissions through the purchase or retirement of SO2 DERCs or SO2 allowances.

(d) The provisions of subsections (c) and (f) of this section, when implemented by the Commissioner of Energy and Environmental Protection, shall not suspend any underlying procedures or requirements in the Regulations of Connecticut State Agencies adopted by the Department of Energy and Environmental Protection pertaining to SO2 emissions.

(e) No provision of section 22a-197, this section or subsection (a) of section 16-245l shall be construed to prohibit the Commissioner of Energy and Environmental Protection from waiving or suspending any applicable sulfur dioxide emissions standard as may be allowed under current federal or state laws or regulations, or other permit limits of a must run Title IV source, as ordered by the Independent System Operator, as may be allowed under current federal or state laws or regulations. The commissioner may attach any conditions to such suspension or waiver, as the commissioner deems necessary to mitigate any adverse environmental or public health impacts.

(f) The Commissioner of Energy and Environmental Protection [, in consultation with the chairperson of the Public Utilities Control Authority,] may suspend the prohibition of subsection (b) of this section for a Title IV source if it is determined that the application of the prohibition established under subsection (b) of this section adversely affects the ability to meet the reliability standards, as defined by the New England Power Pool or its successor organization, and the suspension thereof is intended to mitigate such reliability problems. The Commissioner of Energy and Environmental Protection [, in consultation with the chairperson of the Public Utilities Control Authority,] shall specify in writing the reasons for such suspension and the period of time that such suspension shall be in effect and shall provide notice of such suspension at the time of issuance, or the next business day, to the joint standing committees of the General Assembly having cognizance of matters relating to the environment and energy and technology. No such waiver shall last more than thirty days. The commissioner may reissue additional waivers for such source after said initial waiver has expired. Within ten days of receipt of the commissioner's notice of suspension, the committees having cognizance of matters relating to the environment and energy and technology may hold a joint public hearing and meeting of the committees to either modify or reject the commissioner's suspension by a majority vote. If the committees do not meet, the commissioner's suspension shall be deemed approved.

Sec. 36. Section 22a-354i of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) On or before July 1, 1991, the Commissioner of Energy and Environmental Protection shall publish notice of intent to adopt regulations in accordance with chapter 54 for land use controls in aquifer protection areas. The regulations shall establish (1) best management practice standards for existing regulated activities located entirely or in part within aquifer protection areas and a schedule for compliance of nonconforming regulated activities with such standards, (2) best management practice standards for and prohibitions of regulated activities proposed to be located entirely or in part within aquifer protection areas, (3) procedures for exempting regulated activities in aquifer protection areas upon determination solely by the commissioner that such regulated activities do not pose a threat to any existing or potential drinking water supply, and (4) requirements for design and installation of groundwater monitoring within aquifer protection areas. In addition, the commissioner may adopt such other regulations as deemed necessary to carry out the purposes of sections 22a-354b, 22a-354c, 22a-354h, this section, sections 22a-354m, 22a-354n, subsection (e) of section 22a-354p and subsection (d) of section 22a-451, including, but not limited to, regulations which provide for the manner in which the boundaries of aquifer protection areas shall be established and amended; criteria and procedures for submission and review of applications to construct or begin regulated activities; procedures for granting, denying, limiting, revoking, suspending, transferring and modifying permits for regulated activities; controls regarding the expansion of nonconforming regulated activities, including procedures for offsetting impacts from the expansion or modification of nonconforming regulated activities or procedures for modifying permits of regulated activities by the removal of other potential pollution sources within the subject well field, procedures for the granting of permits for such expansion or modification based on the certification of a qualified person that such expansion meets criteria established by the commissioner; registration requirements for existing regulated activities and procedures for transferring registrations; procedures for landowners to notify a municipality or the commissioner of a change in use and other provisions for administration of the aquifer protection program.

(b) In adopting such regulations, the commissioner shall consider the guidelines for aquifer protection areas recommended in the report prepared pursuant to special act 87-63, as amended, and shall avoid duplication and inconsistency with other state or federal laws and regulations affecting aquifers. The regulations shall be developed in consultation with an advisory committee appointed by the commissioner. The advisory committee shall include the Commissioners of Public Works and Public Health, [and the chairperson of the Public Utilities Control Authority,] or their designees, members of the public, and representatives of businesses affected by the regulations, agriculture, environmental groups, municipal officers and water companies.

Sec. 37. Section 22a-354w of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The Commissioner of Energy and Environmental Protection, in consultation with the Commissioner of Public Health [and the chairperson of the Public Utilities Control Authority,] shall prepare guidelines for acquisition of lands surrounding existing or proposed public water supply well fields. In preparing such guidelines the commissioner shall consider economic implications for mandating land acquisition including, but not limited to, the effect on land values and the ability of small water companies to absorb the cost of acquisition.

Sec. 38. Subsection (d) of section 22a-371 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(d) Upon notifying the applicant in accordance with subsection (c) of this section that the application is complete, the commissioner shall immediately provide notice of the application and a concise description of the proposed diversion to the Governor, the Attorney General, the speaker of the House of Representatives, the president pro tempore of the Senate, the Secretary of the Office of Policy and Management, the Commissioners of Public Health and Economic and Community Development, [the chairperson of the Public Utilities Control Authority,] chief executive officer and chairmen of the conservation commission and wetlands agency of the municipality or municipalities in which the proposed diversion will take place or have effect, and to any person who has requested notice of such activities.

Sec. 39. Section 23-8 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The Commissioner of Energy and Environmental Protection shall have power, acting by himself or with local authorities, to acquire, maintain and make available to the public open spaces for recreation. Said commissioner may take, in the name of the state and for the benefit of the public, by purchase, gift or devise, lands and rights in land and personal estate for public open spaces, or take bonds for the conveyance thereof, or may lease the same for a period not exceeding five years, with an option to buy, and may preserve and care for such public reservations, and, in his discretion and upon such terms as he may approve, such other open spaces within this state as may be entrusted, given or devised to the state by the United States or by cities, towns, corporations or individuals for the purposes of public recreation, or for the preservation of natural beauty or historical association, provided said commissioner shall not take or contract to take by purchase or lease any land or other property for an amount or amounts beyond such sum or sums as have been appropriated or contributed therefor. No provision of this section shall be construed to set aside any terms or conditions under which gifts or bequests of land have been accepted by the commissioner.

(b) Twenty-one per cent of the state's land area shall be held as open space land. The goal of the state's open space acquisition program shall be to acquire land such that ten per cent of the state's land area is held by the state as open space land and not less than eleven per cent of the state's land area is held by municipalities, water companies or nonprofit land conservation organizations as open space land consistent with the provisions of sections 7-131d to 7-131g, inclusive. Such program shall not affect the ability of any water company to reclassify or sell any land, or interest in land, which was not acquired, in whole or in part, with funds made available under the program established under sections 7-131d to 7-131g, inclusive. The goal for state open space acquisition shall be three thousand acres acquired in 1999, four thousand acres acquired in 2000, four thousand acres acquired in 2001 and five thousand acres acquired in 2002 provided such acquisition program shall continue until the overall state goal of open space acquisition is achieved. The commissioner, in consultation with [the Council on Environmental Quality established under section 22a-11 and] private nonprofit land conservation organizations, shall prepare, and update as necessary, a comprehensive strategy for achieving the state goal and shall set an appropriate additional goal for increasing the amount of land held as open space by municipalities or by private nonprofit land conservation organizations and shall include in such strategy provisions for achieving such goal. Such strategy shall include, but not be limited to, recommendations regarding: (1) Timetables for acquisition of land by the state, (2) management of such land, (3) resources to be used for acquisition and management of such land, and (4) acquisition and maintenance of open space land by municipalities and by private entities. On or before January 1, 1998, and annually thereafter, the commissioner shall submit a report to the joint standing committee of the General Assembly having cognizance of matters relating to the environment regarding the strategy and the progress being made towards the goals.

(c) To further the efforts to preserve open space in the state and to help realize the goal established in subsection (b) of this section to have at least twenty-one per cent of the state's land held by the state, municipalities, land conservation organizations and water utilities as open space, the Department of Energy and Environmental Protection shall conduct an evaluation of lands of class A water companies, as defined in section 16-1, to determine the resource value and potential desirability of such lands for purchase for open space or public outdoor recreation or natural resource conservation or preservation. The water companies and land conservation organizations shall work cooperatively with the department and provide maps and other information to assist the Department of Energy and Environmental Protection in the evaluation of these properties and said department shall develop strategies for alternative methods of funding the preservation of water company lands in perpetuity as open space.

Sec. 40. Section 23-102 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There shall be a Connecticut Greenways Council which shall be within the Department of Energy and Environmental Protection for administrative purposes only. The council shall consist of eleven members, five to be appointed by the Governor, one to be appointed by the speaker of the House of Representatives, one to be appointed by the majority leader of the House of Representatives, one to be appointed by the president pro tempore of the Senate, one to be appointed by the majority leader of the Senate, one to be appointed by the minority leader of the House of Representatives and one to be appointed by the minority leader of the Senate. All appointments to the council shall be made on or before October 1, 1995. Three of the members initially appointed by the Governor shall serve a term of two years and two of the members appointed by the Governor shall serve a term of four years. All members appointed by the Governor thereafter shall serve a term of four years. The terms of all members appointed by members of the General Assembly shall be coterminous with the terms of members of the General Assembly. The appointing authority shall fill any vacancy by appointment for the unexpired portion of the term vacated. The chairman of said council shall be selected by the Governor. Members of said council shall receive no compensation for their services on the council. The council shall hold one meeting each quarter and such additional meetings as may be prescribed by council rules. Special meetings may be called by the chairman or by any three members upon delivery of forty-eight hours' written notice to each member. The council may employ an executive director, exclusive of the provisions of chapter 67, and such additional staff and contractors and consultants as may be necessary to carry out its duties. [and may share the personnel and resources of the council on environmental quality, within available appropriations.] The council may receive aid or contributions from any source, including grants-in-aid from any state agency.

(b) The duties of the council shall be: (1) To advise and assist in the coordination of state agencies, municipalities, regional planning organizations, as defined in section 4-124i, and private citizens in voluntarily planning and implementing a system of greenways; (2) to operate a greenways help center to advise state agencies, municipalities, regional planning organizations, as defined in section 4-124i, and private citizens in the technical aspects of planning, designing and implementing greenways, including advice on securing state, federal and nongovernmental grants; (3) to establish criteria for designation of greenways; (4) to maintain an inventory of greenways in the state which shall include the location of greenways transportation projects which have received grants under sections 23-101, 32-6a, 32-9qq and 32-328; (5) to advise the Commissioner of Economic and Community Development on the distribution of grants for greenways transportation projects pursuant to sections 32-6a, 32-9qq and 32-328; and (6) to advise the Commissioner of Energy and Environmental Protection on the distribution of grants pursuant to section 23-101.

Sec. 41. Section 25-32i of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

There is created a Residential Water-Saving Advisory Board to advise the Commissioner of Public Health on educational materials or information on water conservation. The board shall consist of eight members as follows: The Commissioners of Energy and Environmental Protection and Public Health, the Secretary of the Office of Policy and Management, [the chairperson of the Public Utilities Control Authority,] and the Consumer Counsel, or their respective designees; a representative of a small investor-owned water company, who shall be appointed by the minority leader of the Senate; a representative of a large investor-owned water company, who shall be appointed by the minority leader of the House of Representatives; and a representative of a municipal or regional water authority, who shall be jointly appointed by the president pro tempore of the Senate and the speaker of the House of Representatives. The Governor shall designate the chairman of the board.

Sec. 42. Section 25-33o of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The [chairperson of the Public Utilities Control Authority, or the chairperson's designee, the] Commissioner of Energy and Environmental Protection, or the commissioner's designee, the Secretary of the Office of Policy and Management, or the secretary's designee, and the Commissioner of Public Health, or the commissioner's designee, shall constitute a Water Planning Council to address issues involving the water companies, water resources and state policies regarding the future of the state's drinking water supply. On or after July 1, 2007, and each year thereafter, the chairperson of the Water Planning Council shall be elected by the members of the Water Planning Council.

(b) The Water Planning Council shall conduct a study, in consultation with representatives of water companies, municipalities, agricultural groups, environmental groups and other water users, that shall include the following issues: (1) The financial viability, market structure, reliability of customer service and managerial competence of water companies; (2) fair and reasonable water rates; (3) protection and appropriate allocation of the state's water resources while providing for public water supply needs; (4) the adequacy and quality of the state's drinking water supplies to meet current and future needs; (5) an inventory of land and land use by water companies; (6) the status of current withdrawals, projected withdrawals, river flows and the future needs of water users; (7) methods for measurement and estimations of natural flows in Connecticut waterways in order to determine standards for stream flows that will protect the ecology of the state's rivers and streams; (8) the status of river flows and available data for measuring river flows; (9) the streamlining of the water diversion permit process; (10) coordination between the Departments of Energy and Environmental Protection [,] and Public Health [and Public Utility Control] in review of applications for water diversion; and (11) the procedure for coordination of planning of public water supply systems established in sections 25-33c to 25-33j, inclusive. Such study shall be conducted on both a regional and state-wide level.

(c) The council may establish an advisory group that shall serve at the pleasure of the council. The advisory group shall be balanced between consumptive and nonconsumptive interests. The advisory group may include representatives of (1) regional and municipal water utilities, (2) investor-owned water utilities, (3) a wastewater system, (4) agricultural interests, (5) electric power generation interests, (6) business and industry interests, (7) environmental land protection interests, (8) environmental river protection interests, (9) boating interests, (10) fisheries interests, (11) recreational interests, (12) endangered species protection interests, and (13) members of academia with expertise in stream flow, public health and ecology.

(d) The council shall, not later than January 1, 2002, and annually thereafter, report its preliminary findings and any proposed legislative changes to the joint standing committees of the General Assembly having cognizance of matters relating to public health, the environment and public utilities in accordance with section 11-4a, except that not later than February 1, 2004, the council shall report its recommendations in accordance with this subsection with regard to (1) a water allocation plan based on water budgets for each watershed, (2) funding for water budget planning, giving priority to the most highly stressed watersheds, and (3) the feasibility of merging the data collection and regulatory functions of the Department of Energy and Environmental Protection's inland water resources program and the Department of Public Health's water supplies section.

Sec. 43. Section 25-157 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

Notwithstanding any other provision of the general statutes, no state agency, including, but not limited to, the Department of Energy and Environmental Protection and the Connecticut Siting Council within such department, shall consider or render a final decision for any applications relating to electric power line crossings, gas pipeline crossings or telecommunications crossings of Long Island Sound that have required or will require a certificate issued pursuant to section 16-50k or approval by the Federal Energy Regulatory Commission including, but not limited to, electrical power line, gas pipeline or telecommunications applications that are pending or received after June 3, 2002, for a period of three years after June 3, 2002. Such moratorium shall not apply to applications relating solely to the maintenance, repair or replacement necessary for repair of electrical power lines, gas pipelines or telecommunications facilities currently used to provide service to customers located on islands or peninsulas off the Connecticut coast or harbors, embayments, tidal rivers, streams or creeks. An applicant may seek a waiver of such moratorium by submitting a petition to the following: The chairpersons and ranking members of the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment, the chairman of the Connecticut Siting Council, [the chairperson of the Public Utilities Control Authority,] the Commissioner of Energy and Environmental Protection, and any other state agency head with jurisdiction over the subject of the petition. Such persons may grant a petition for a waiver by unanimous consent. Nothing in section 16-244j, this section or sections 25-157a to 25-157c, inclusive, shall be construed to affect the project in the corridor across Long Island Sound, from Norwalk to Northport, New York, to replace the existing electric cables that cross the sound.

Sec. 44. Section 28-24 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There is established an Office of State-Wide Emergency Telecommunications which shall be in the Division of Fire, Emergency and Building Services within the Department of Public Safety. The Office of State-Wide Emergency Telecommunications shall be responsible for developing and maintaining a state-wide emergency service telecommunications policy. In connection with said policy the office shall:

(1) Develop a state-wide emergency service telecommunications plan specifying emergency police, fire and medical service telecommunications systems needed to provide coordinated emergency service telecommunications to all state residents, including the physically disabled;

(2) Pursuant to the recommendations of the task force established by public act 95-318 to study enhanced 9-1-1 telecommunications services, and in accordance with regulations adopted by the Commissioner of Public Safety pursuant to subsection (b) of this section, develop and administer, by July 1, 1997, an enhanced emergency 9-1-1 program, which shall provide for: (A) The replacement of existing 9-1-1 terminal equipment for each public safety answering point; (B) the subsidization of regional public safety emergency telecommunications centers, with enhanced subsidization for municipalities with a population in excess of forty thousand; (C) the establishment of a transition grant program to encourage regionalization of public safety telecommunications centers; and (D) the establishment of a regional emergency telecommunications service credit in order to support regional dispatch services;

(3) Provide technical telecommunications assistance to state and local police, fire and emergency medical service agencies;

(4) Provide frequency coordination for such agencies;

(5) Coordinate and assist in state-wide planning for 9-1-1 and E 9-1-1 systems;

(6) Review and make recommendations concerning proposed legislation affecting emergency service telecommunications; and

(7) Review and make recommendations to the General Assembly concerning emergency service telecommunications funding.

(b) The Commissioner of Public Safety shall adopt regulations, in accordance with chapter 54, establishing eligibility standards for state financial assistance to local or regional police, fire and emergency medical service agencies providing emergency service telecommunications. Not later than April 1, 1997, the commissioner shall adopt regulations, in accordance with chapter 54, in order to carry out the provisions of subdivision (2) of subsection (a) of this section.

(c) Within a time period determined by the commissioner to ensure the availability of funds for the fiscal year beginning July 1, 1997, to the regional public safety emergency telecommunications centers within the state, and not later than April first of each year thereafter, the commissioner shall determine the amount of funding needed for the development and administration of the enhanced emergency 9-1-1 program. The commissioner shall specify the expenses associated with (1) the purchase, installation and maintenance of new public safety answering point terminal equipment, (2) the implementation of the subsidy program, as described in subdivision (2) of subsection (a) of this section, (3) the implementation of the transition grant program, described in subdivision (2) of subsection (a) of this section, (4) the implementation of the regional emergency telecommunications service credit, as described in subdivision (2) of subsection (a) of this section, provided, for the fiscal year ending June 30, 2001, and each fiscal year thereafter, such credit for coordinated medical emergency direction services as provided in regulations adopted under this section shall be based upon the factor of thirty cents per capita and shall not be reduced each year, (5) the training of personnel, as necessary, (6) recurring expenses and future capital costs associated with the telecommunications network used to provide emergency 9-1-1 service and the public safety services data networks, (7) for the fiscal year ending June 30, 2001, and each fiscal year thereafter, the collection, maintenance and reporting of emergency medical services data, as required under subparagraphs (A) and (B) of subdivision (8) of section 19a-177, provided the amount of expenses specified under this subdivision shall not exceed two hundred fifty thousand dollars in any fiscal year, (8) for the fiscal year ending June 30, 2001, and each fiscal year thereafter, the initial training of emergency medical dispatch personnel, the provision of an emergency medical dispatch priority reference card set and emergency medical dispatch training and continuing education pursuant to subdivisions (3) and (4) of subsection (g) of section 28-25b, and (9) the administration of the enhanced emergency 9-1-1 program by the Office of State-Wide Emergency Telecommunications, as the commissioner determines to be reasonably necessary. The commissioner shall communicate the commissioner's findings to the [chairperson of the Public Utilities Control Authority] Commissioner of Energy and Environmental Protection not later than April first of each year.

(d) The office may apply for, receive and distribute any federal funds available for emergency service telecommunications. The office shall deposit such federal funds in the Enhanced 9-1-1 Telecommunications Fund established by section 28-30a.

(e) The office shall work in cooperation with the Department of [Public Utility Control] Energy and Environmental Protection to carry out the purposes of this section.

Sec. 45. Section 16a-48 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) As used in this section:

(1) ["Office" means the Office of Policy and Management] "Department" means the Department of Energy and Environmental Protection;

(2) "Fluorescent lamp ballast" or "ballast" means a device designed to operate fluorescent lamps by providing a starting voltage and current and limiting the current during normal operation, but does not include such devices that have a dimming capability or are intended for use in ambient temperatures of zero degrees Fahrenheit or less or have a power factor of less than sixty-one hundredths for a single F40T12 lamp;

(3) "F40T12 lamp" means a tubular fluorescent lamp that is a nominal forty-watt lamp, with a forty-eight-inch tube length and one and one-half inches in diameter;

(4) "F96T12 lamp" means a tubular fluorescent lamp that is a nominal seventy-five-watt lamp with a ninety-six-inch tube length and one and one-half inches in diameter;

(5) "Luminaire" means a complete lighting unit consisting of a fluorescent lamp, or lamps, together with parts designed to distribute the light, to position and protect such lamps, and to connect such lamps to the power supply;

(6) "New product" means a product that is sold, offered for sale, or installed for the first time and specifically includes floor models and demonstration units;

(7) ["Secretary" means the Secretary of the Office of Policy and Management] "Commissioner" means the Commissioner of Energy and Environmental Protection;

(8) "State Building Code" means the building code adopted pursuant to section 29-252;

(9) "Torchiere lighting fixture" means a portable electric lighting fixture with a reflector bowl giving light directed upward so as to give indirect illumination;

(10) "Unit heater" means a self-contained, vented fan-type commercial space heater that uses natural gas or propane and that is designed to be installed without ducts within the heated space. "Unit heater" does not include a product regulated by federal standards pursuant to 42 USC 6291, as amended from time to time, a product that is a direct vent, forced flue heater with a sealed combustion burner, or any oil fired heating system;

(11) "Transformer" means a device consisting of two or more coils of insulated wire that transfers alternating current by electromagnetic induction from one coil to another in order to change the original voltage or current value;

(12) "Low-voltage dry-type transformer" means a transformer that: (A) Has an input voltage of six hundred volts or less; (B) is between fourteen kilovolt-amperes and two thousand five hundred one kilovolt-amperes in size; (C) is air-cooled; and (D) does not use oil as a coolant. "Low-voltage dry-type transformer" does not include such transformers excluded from the low-voltage dry-type distribution transformer definition contained in the California Code of Regulations, Title 20: Division 2, Chapter 4, Article 4: Appliance Efficiency Regulations;

(13) "Pass-through cabinet" means a refrigerator or freezer with hinged or sliding doors on both the front and rear of the refrigerator or freezer;

(14) "Reach-in cabinet" means a refrigerator, freezer, or combination thereof, with hinged or sliding doors or lids;

(15) "Roll-in" or "roll-through cabinet" means a refrigerator or freezer with hinged or sliding doors that allows wheeled racks of product to be rolled into or through the refrigerator or freezer;

(16) "Commercial refrigerators and freezers" means reach-in cabinets, pass-through cabinets, roll-in cabinets and roll-through cabinets that have less than eighty-five feet of capacity, which are designed for the refrigerated or frozen storage of food and food products;

(17) "Traffic signal module" means a standard eight-inch or twelve-inch round traffic signal indicator consisting of a light source, lens and all parts necessary for operation and communication of movement messages to drivers through red, amber and green colors;

(18) "Illuminated exit sign" means an internally illuminated sign that is designed to be permanently fixed in place and used to identify an exit by means of a light source that illuminates the sign or letters from within where the background of the exit sign is not transparent;

(19) "Packaged air-conditioning equipment" means air-conditioning equipment that is built as a package and shipped as a whole to end-user sites;

(20) "Large packaged air-conditioning equipment" means air-cooled packaged air-conditioning equipment having not less than two hundred forty thousand BTUs per hour of capacity;

(21) "Commercial clothes washer" means a soft mount front-loading or soft mount top-loading clothes washer that is designed for use in (A) applications where the occupants of more than one household will be using it, such as in multifamily housing common areas and coin laundries; or (B) other commercial applications, if the clothes container compartment is no greater than three and one-half cubic feet for horizontal-axis clothes washers or no greater than four cubic feet for vertical-axis clothes washers;

(22) "Energy efficiency ratio" means a measure of the relative efficiency of a heating or cooling appliance that is equal to the unit's output in BTUs per hour divided by its consumption of energy, measured in watts;

(23) "Electricity ratio" means the ratio of furnace electricity use to total furnace energy use;

(24) "Boiler" means a space heater that is a self-contained appliance for supplying steam or hot water primarily intended for space-heating. "Boiler" does not include hot water supply boilers;

(25) "Central furnace" means a self-contained space heater designed to supply heated air through ducts of more than ten inches in length;

(26) "Residential furnace or boiler" means a product that utilizes only single-phase electric current or single-phase electric current or DC current in conjunction with natural gas, propane or home heating oil and that (A) is designed to be the principal heating source for the living space of a residence; (B) is not contained within the same cabinet as a central air conditioner with a rated cooling capacity of not less than sixty-five thousand BTUs per hour; (C) is an electric central furnace, electric boiler, forced-air central furnace, gravity central furnace or low pressure steam or hot water boiler; and (D) has a heat input rate of less than three hundred thousand BTUs per hour for an electric boiler and low pressure steam or hot water boiler and less than two hundred twenty-five thousand BTUs per hour for a forced-air central furnace, gravity central furnace and electric central furnace;

(27) "Furnace air handler" means the section of the furnace that includes the fan, blower and housing, generally upstream of the burners and heat exchanger. The furnace air handler may include a filter and a cooling coil;

(28) "High-intensity discharge lamp" means a lamp in which light is produced by the passage of an electric current through a vapor or gas, the light-producing arc is stabilized by bulb wall temperature and the arc tube has a bulb wall loading in excess of three watts per square centimeter;

(29) "Metal halide lamp" means a high intensity discharge lamp in which the major portion of the light is produced by radiation of metal halides and their products of dissociation, possibly in combination with metallic vapors;

(30) "Metal halide lamp fixture" means a light fixture designed to be operated with a metal halide lamp and a ballast for a metal halide lamp;

(31) "Probe start metal halide ballast" means a ballast used to operate metal halide lamps that does not contain an ignitor and that instead starts lamps by using a third starting electrode probe in the arc tube;

(32) "Single voltage external AC to DC power supply" means a device that (A) is designed to convert line voltage AC input into lower voltage DC output; (B) is able to convert to only one DC output voltage at a time; (C) is sold with, or intended to be used with, a separate end-use product that constitutes the primary power load; (D) is contained within a separate physical enclosure from the end-use product; (E) is connected to the end-use product in a removable or hard-wired male and female electrical connection, cable, cord or other wiring; (F) does not have batteries or battery packs, including those that are removable or that physically attach directly to the power supply unit; (G) does not have a battery chemistry or type selector switch and indicator light or a battery chemistry or type selector switch and a state of charge meter; and (H) has a nameplate output power less than or equal to two hundred fifty watts;

(33) "State regulated incandescent reflector lamp" means a lamp that is not colored or designed for rough or vibration service applications, has an inner reflective coating on the outer bulb to direct the light, has an E26 medium screw base, a rated voltage or voltage range that lies at least partially within one hundred fifteen to one hundred thirty volts, and that falls into one of the following categories: (A) A bulged reflector or elliptical reflector or a blown PAR bulb shape and that has a diameter that equals or exceeds two and one-quarter inches, or (B) a reflector, parabolic aluminized reflector, bulged reflector or similar bulb shape and that has a diameter of two and one-quarter to two and three-quarters inches. "State regulated incandescent reflector lamp" does not include ER30, BR30, BR40 and ER40 lamps of not more than fifty watts, BR30, BR40 and ER40 lamps of sixty-five watts and R20 lamps of not more than forty-five watts;

(34) "Bottle-type water dispenser" means a water dispenser that uses a bottle or reservoir as the source of potable water;

(35) "Commercial hot food holding cabinet" means a heated, fully-enclosed compartment with one or more solid or partial glass doors that is designed to maintain the temperature of hot food that has been cooked in a separate appliance. "Commercial hot food holding cabinet" does not include heated glass merchandizing cabinets, drawer warmers or cook-and-hold appliances;

(36) "Pool heater" means an appliance designed for heating nonpotable water contained at atmospheric pressure for swimming pools, spas, hot tubs and similar applications, including natural gas, heat pump, oil and electric resistance pool heaters;

(37) "Portable electric spa" means a factory-built electric spa or hot tub supplied with equipment for heating and circulating water;

(38) "Residential pool pump" means a pump used to circulate and filter pool water to maintain clarity and sanitation;

(39) "Walk-in refrigerator" means a space refrigerated to temperatures at or above thirty-two degrees Fahrenheit that has a total chilled storage area of less than three thousand square feet, can be walked into and is designed for the refrigerated storage of food and food products. "Walk-in refrigerator" does not include refrigerated warehouses and products designed and marketed exclusively for medical, scientific or research purposes;

(40) "Walk-in freezer" means a space refrigerated to temperatures below thirty-two degrees Fahrenheit that has a total chilled storage area of less than three thousand square feet, can be walked into and is designed for the frozen storage of food and food products. "Walk-in freezer" does not include refrigerated warehouses and products designed and marketed exclusively for medical, scientific or research purposes;

(41) "Central air conditioner" means a central air conditioning model that consists of one or more factory-made assemblies, which normally include an evaporator or cooling coil, compressor and condenser. Central air conditioning models may provide the function of air cooling, air cleaning, dehumidifying or humidifying;

(42) "Combination television" means a system in which a television or television monitor and an additional device or devices, including, but not limited to, a digital versatile disk player or video cassette recorder, are combined into a single unit in which the additional devices are included in the television casing;

(43) "Compact audio player" means an integrated audio system encased in a single housing that includes an amplifier and radio tuner with attached or separable speakers and can reproduce audio from one or more of the following media: Magnetic tape, compact disk, digital versatile disk or flash memory. "Compact audio player" does not mean a product that can be independently powered by internal batteries, has a powered external satellite antenna or can provide a video output signal;

(44) "Component television" means a television composed of two or more separate components, such as a separate display device and tuner, marketed and sold as a television under one model or system designation, which may have more than one power cord;

(45) "Computer monitor" means an analog or digital device designed primarily for the display of computer generated signals and that is not marketed for use as a television;

(46) "Digital versatile disc" means a laser-encoded plastic medium capable of storing a large amount of digital audio, video and computer data;

(47) "Digital versatile disc player" means a commercially available electronic product encased in a single housing that includes an integral power supply and for which the sole purpose is the decoding of digitized video signals;

(48) "Digital versatile disc recorder" means a commercially available electronic product encased in a single housing that includes an integral power supply and for which the sole purpose is the production or recording of digitized audio, video and computer signals on a digital versatile disk. "Digital versatile disk recorder" does not include a model that has an electronic programming guide function;

(49) "Television" means an analog or digital device designed primarily for the display and reception of a terrestrial, satellite, cable, internet protocol television or other broadcast or recorded transmission of analog or digital video and audio signals. "Television" includes combination televisions, television monitors, component televisions and any unit that is marketed to consumers as a television but does not include a computer monitor;

(50) "Television monitor" means a television that does not have an internal tuner/receiver or playback device.

(b) The provisions of this section apply to the testing, certification and enforcement of efficiency standards for the following types of new products sold, offered for sale or installed in the state: (1) Commercial clothes washers; (2) commercial refrigerators and freezers; (3) illuminated exit signs; (4) large packaged air-conditioning equipment; (5) low voltage dry-type distribution transformers; (6) torchiere lighting fixtures; (7) traffic signal modules; (8) unit heaters; (9) residential furnaces and boilers; (10) residential pool pumps; (11) metal halide lamp fixtures; (12) single voltage external AC to DC power supplies; (13) state regulated incandescent reflector lamps; (14) bottle-type water dispensers; (15) commercial hot food holding cabinets; (16) portable electric spas; (17) walk-in refrigerators and walk-in freezers; (18) pool heaters; [and] (19) compact audio players; (20) televisions; (21) digital versatile disc players; (22) digital versatile disc recorders; and (23) any other products as may be designated by the office in accordance with subdivision (3) of subsection (d) of this section.

(c) The provisions of this section do not apply to (1) new products manufactured in the state and sold outside the state, (2) new products manufactured outside the state and sold at wholesale inside the state for final retail sale and installation outside the state, (3) products installed in mobile manufactured homes at the time of construction, or (4) products designed expressly for installation and use in recreational vehicles.

(d) (1) The [office, in consultation with the Department of Public Utility Control,] department shall adopt regulations, in accordance with the provisions of chapter 54, to implement the provisions of this section and to establish minimum energy efficiency standards for the types of new products set forth in subsection (b) of this section. The regulations shall provide for the following minimum energy efficiency standards:

(A) Commercial clothes washers shall meet the requirements shown in Table P-3 of section 1605.3 of the California Code of Regulations, Title 20: Division 2, Chapter 4, Article 4;

(B) Commercial refrigerators and freezers shall meet the August 1, 2004, requirements shown in Table A-6 of said California regulation;

(C) Illuminated exit signs shall meet the version 2.0 product specification of the "Energy Star Program Requirements for Exit Signs" developed by the United States Environmental Protection Agency;

(D) Large packaged air-conditioning equipment having not more than seven hundred sixty thousand BTUs per hour of capacity shall meet a minimum energy efficiency ratio of 10.0 for units using both electric heat and air conditioning or units solely using electric air conditioning, and 9.8 for units using both natural gas heat and electric air conditioning;

(E) Large packaged air-conditioning equipment having not less than seven hundred sixty-one thousand BTUs per hour of capacity shall meet a minimum energy efficiency ratio of 9.7 for units using both electric heat and air conditioning or units solely using electric air conditioning, and 9.5 for units using both natural gas heat and electric air conditioning;

(F) Low voltage dry-type distribution transformers shall meet or exceed the energy efficiency values shown in Table 4-2 of the National Electrical Manufacturers Association Standard TP-1-2002;

(G) Torchiere lighting fixtures shall not consume more than one hundred ninety watts and shall not be capable of operating with lamps that total more than one hundred ninety watts;

(H) Traffic signal modules shall meet the product specification of the "Energy Star Program Requirements for Traffic Signals" developed by the United States Environmental Protection Agency that took effect in February, 2001, except where the department, in consultation with the Commissioner of Transportation, determines that such specification would compromise safe signal operation;

(I) Unit heaters shall not have pilot lights and shall have either power venting or an automatic flue damper;

(J) On or after January 1, 2009, residential furnaces and boilers purchased by the state shall meet or exceed the following annual fuel utilization efficiency: (i) For gas and propane furnaces, ninety per cent annual fuel utilization efficiency, (ii) for oil furnaces, eighty-three per cent annual fuel utilization efficiency, (iii) for gas and propane hot water boilers, eighty-four per cent annual fuel utilization efficiency, (iv) for oil-fired hot water boilers, eighty-four per cent annual fuel utilization efficiency, (v) for gas and propane steam boilers, eighty-two per cent annual fuel utilization efficiency, (vi) for oil-fired steam boilers, eighty-two per cent annual fuel utilization efficiency, and (vii) for furnaces with furnace air handlers, an electricity ratio of not more than 2.0, except air handlers for oil furnaces with a capacity of less than ninety-four thousand BTUs per hour shall have an electricity ratio of 2.3 or less;

(K) On or after January 1, 2010, metal halide lamp fixtures designed to be operated with lamps rated greater than or equal to one hundred fifty watts but less than or equal to five hundred watts shall not contain a probe-start metal halide lamp ballast;

(L) Single-voltage external AC to DC power supplies manufactured on or after January 1, 2008, shall meet the energy efficiency standards of table U-1 of section 1605.3 of the January 2006 California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4: Appliance Efficiency Regulations. This standard applies to single voltage AC to DC power supplies that are sold individually and to those that are sold as a component of or in conjunction with another product. This standard shall not apply to single voltage external AC to DC power supplies sold with products subject to certification by the United States Food and Drug Administration. A single-voltage external AC to DC power supply that is made available by a manufacturer directly to a consumer or to a service or repair facility after and separate from the original sale of the product requiring the power supply as a service part or spare part shall not be required to meet the standards in said table U-1 until five years after the effective dates indicated in the table;

(M) On or after January 1, 2009, state regulated incandescent reflector lamps shall be manufactured to meet the minimum average lamp efficacy requirements for federally-regulated incandescent reflector lamps contained in 42 USC 6295(i)(1)(A). Each lamp shall indicate the date of manufacture;

(N) On or after January 1, 2009, bottle-type water dispensers, commercial hot food holding cabinets, portable electric spas, walk-in refrigerators and walk-in freezers shall meet the efficiency requirements of section 1605.3 of the January 2006 California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4: Appliance Efficiency Regulations. On or after January 1, 2010, residential pool pumps shall meet said efficiency requirements;

(O) On or after January 1, 2009, pool heaters shall meet the efficiency requirements of sections 1605.1 and 1605.3 of the January 2006 California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4: Appliance Efficiency Regulations;

(P) On or after January 1, 2014, compact audio players, digital versatile disc players and digital versatile disc recorders shall meet the requirements shown in Table V-1 of Section 1605.3 of the November 2009 amendments to the California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4;

(Q) On or after January 1, 2014, televisions manufactured on or after the effective date of this section shall meet the requirements shown in Table V-2 of Section 1605.3 of the November 2009 amendments to the California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4;

(R) In addition to the requirements of subparagraph (Q) of this subdivision, televisions manufactured on or after January 1, 2014, shall meet the efficiency requirements of Sections 1605.3(v)(3)(A), 1605.3(v)(3)(B) and 1605.3(v)(3)(C) of the November 2009 amendments to the California Code of Regulations, Title 20, Division 2, Chapter 4, Article 4.

(2) Such efficiency standards, where in conflict with the State Building Code, shall take precedence over the standards contained in the Building Code. Not later than July 1, 2007, and biennially thereafter, the [office, in consultation with the Department of Public Utility Control,] department shall review and increase the level of such efficiency standards by adopting regulations in accordance with the provisions of chapter 54 upon a determination that increased efficiency standards would serve to promote energy conservation in the state and would be cost-effective for consumers who purchase and use such new products, provided no such increased efficiency standards shall become effective within one year following the adoption of any amended regulations providing for such increased efficiency standards.

(3) (A) The [office, in consultation with the Department of Public Utility Control,] department shall adopt regulations, in accordance with the provisions of chapter 54, to designate additional products to be subject to the provisions of this section and to establish efficiency standards for such products upon a determination that such efficiency standards [(A)] (i) would serve to promote energy conservation in the state, [(B)] (ii) would be cost-effective for consumers who purchase and use such new products, and [(C)] (iii) that multiple products are available which meet such standards, provided no such efficiency standards shall become effective within one year following their adoption pursuant to this subdivision.

(B) The department, in consultation with the Multi-State Appliance Standards Collaborative, shall identify additional appliance and equipment efficiency standards. Not later than six months after adoption of an efficiency standard by a cooperative member state regarding a product for which no equivalent Connecticut or federal standard currently exists, the office shall adopt regulations in accordance with the provisions of chapter 54 adopting such efficiency standard unless the office makes a specific finding that such standard does not meet the criteria in subparagraph (A) of this subdivision.

(e) On or after July 1, 2006, except for commercial clothes washers, for which the date shall be July 1, 2007, commercial refrigerators and freezers, for which the date shall be July 1, 2008, and large packaged air-conditioning equipment, for which the date shall be July 1, 2009, no new product of a type set forth in subsection (b) of this section or designated by the office may be sold, offered for sale, or installed in the state unless the energy efficiency of the new product meets or exceeds the efficiency standards set forth in such regulations adopted pursuant to subsection (d) of this section.

(f) The [office, in consultation with the Department of Public Utility Control,] department shall adopt procedures for testing the energy efficiency of the new products set forth in subsection (b) of this section or designated by the department if such procedures are not provided for in the State Building Code. The [office] department shall use United States Department of Energy approved test methods, or in the absence of such test methods, other appropriate nationally recognized test methods. The manufacturers of such products shall cause samples of such products to be tested in accordance with the test procedures adopted pursuant to this subsection or those specified in the State Building Code.

(g) Manufacturers of new products set forth in subsection (b) of this section or designated by the [office] department shall certify to the [secretary] commissioner that such products are in compliance with the provisions of this section, except that certification is not required for single voltage external AC to DC power supplies and walk-in refrigerators and walk-in freezers. All single voltage external AC to DC power supplies shall be labeled as described in the January 2006 California Code of Regulations, Title 20, Section 1607 (9). The [office, in consultation with the Department of Public Utility Control,] department shall promulgate regulations governing the certification of such products. The [secretary] commissioner shall publish an annual list of such products.

(h) The Attorney General may institute proceedings to enforce the provisions of this section. Any person who violates any provision of this section shall be subject to a civil penalty of not more than two hundred fifty dollars. Each violation of this section shall constitute a separate offense, and each day that such violation continues shall constitute a separate offense.

Sec. 46. Section 16-245m of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) (1) On and after January 1, 2000, the Department of [Public Utility Control] Energy and Environmental Protection's Bureau of Public Utility shall assess or cause to be assessed a charge of three mills per kilowatt hour of electricity sold to each end use customer of an electric distribution company to be used to implement the program as provided in this section for conservation and load management programs but not for the amortization of costs incurred prior to July 1, 1997, for such conservation and load management programs.

(2) Notwithstanding the provisions of this section, receipts from such charge shall be disbursed to the resources of the General Fund during the period from July 1, 2003, to June 30, 2005, unless the department shall, on or before October 30, 2003, issue a financing order for each affected electric distribution company in accordance with sections 16-245e to 16-245k, inclusive, to sustain funding of conservation and load management programs by substituting an equivalent amount, as determined by the department in such financing order, of proceeds of rate reduction bonds for disbursement to the resources of the General Fund during the period from July 1, 2003, to June 30, 2005. The department may authorize in such financing order the issuance of rate reduction bonds that substitute for disbursement to the General Fund for receipts of both the charge under this subsection and under subsection (b) of section 16-245n, as amended by this act, and also may, in its discretion, authorize the issuance of rate reduction bonds under this subsection and subsection (b) of section 16-245n, as amended by this act, that relate to more than one electric distribution company. The department shall, in such financing order or other appropriate order, offset any increase in the competitive transition assessment necessary to pay principal, premium, if any, interest and expenses of the issuance of such rate reduction bonds by making an equivalent reduction to the charge imposed under this subsection, provided any failure to offset all or any portion of such increase in the competitive transition assessment shall not affect the need to implement the full amount of such increase as required by this subsection and by sections 16-245e to 16-245k, inclusive. Such financing order shall also provide if the rate reduction bonds are not issued, any unrecovered funds expended and committed by the electric distribution companies for conservation and load management programs, provided such expenditures were approved by the department after August 20, 2003, and prior to the date of determination that the rate reduction bonds cannot be issued, shall be recovered by the companies from their respective competitive transition assessment or systems benefits charge but such expenditures shall not exceed four million dollars per month. All receipts from the remaining charge imposed under this subsection, after reduction of such charge to offset the increase in the competitive transition assessment as provided in this subsection, shall be disbursed to the Energy Conservation and Load Management Fund commencing as of July 1, 2003. Any increase in the competitive transition assessment or decrease in the conservation and load management component of an electric distribution company's rates resulting from the issuance of or obligations under rate reduction bonds shall be included as rate adjustments on customer bills.

(3) In the financing order authorizing the economic recovery revenue bonds, or other appropriate order, the department shall reduce the charge assessed by subdivision (1) of this subsection by thirty-five per cent. Such reduction shall become effective on April 4, 2012, or such earlier date set by the department in the financing order. An amount equivalent to such reduction shall constitute a portion of the competitive transition assessment in respect of the economic recovery revenue bonds, provided any failure to offset all or any portion of such competitive transition assessment shall not affect the requirement to implement the full amount of such competitive transition assessment, as required by sections 16-245e to 16-245k, inclusive. All receipts from the remaining charge, after reduction of such charge as provided in this subsection, shall be disbursed to the Energy Conservation and Load Management Fund. The competitive transition assessment in respect to the economic recovery revenue bonds or the decrease in the conservation and load management component of an electric distribution company's rates resulting from the issuance of or obligations under the economic recovery revenue bonds shall be included as rate adjustments on customer bills.

(b) The electric distribution company shall establish an Energy Conservation and Load Management Fund which shall be held separate and apart from all other funds or accounts. Receipts from the charge imposed under subsection (a) of this section shall be deposited into the fund. Any balance remaining in the fund at the end of any fiscal year shall be carried forward in the fiscal year next succeeding. Disbursements from the fund by electric distribution companies to carry out the plan developed under subsection (d) of this section shall be authorized by the Department of [Public Utility Control] Energy and Environmental Protection upon its approval of such plan.

(c) The Department of [Public Utility Control] Energy and Environmental Protection shall appoint and convene an Energy Conservation Management Board which shall include representatives of: (1) An environmental group knowledgeable in energy conservation program collaboratives; (2) the Office of Consumer Counsel; (3) the Attorney General; (4) the Department of Energy and Environmental Protection; (5) the electric distribution companies in whose territories the activities take place for such programs; (6) a state-wide manufacturing association; (7) a chamber of commerce; (8) a state-wide business association; (9) a state-wide retail organization; (10) a representative of a municipal electric energy cooperative created pursuant to chapter 101a; (11) two representatives selected by the gas companies in this state; and (12) residential customers. Such members shall serve for a period of five years and may be reappointed. Representatives of the gas companies shall not vote on matters unrelated to gas conservation. Representatives of the electric distribution companies and the municipal electric energy cooperative shall not vote on matters unrelated to electricity conservation.

(d) (1) The Energy Conservation Management Board shall advise and assist the electric distribution companies in the development and implementation of a comprehensive plan, which plan shall be approved by the Department of [Public Utility Control] Energy and Environmental Protection, to implement cost-effective energy conservation programs and market transformation initiatives. Each program contained in the plan shall be reviewed by the electric distribution company and either accepted or rejected by the Energy Conservation Management Board prior to submission to the department for approval. The Energy Conservation Management Board shall, as part of its review, examine opportunities to offer joint programs providing similar efficiency measures that save more than one fuel resource or otherwise to coordinate programs targeted at saving more than one fuel resource. Any costs for joint programs shall be allocated equitably among the conservation programs. The Energy Conservation Management Board shall give preference to projects that maximize the reduction of federally mandated congestion charges. The Department of [Public Utility Control] Energy and Environmental Protection shall, in an uncontested proceeding during which the department may hold a public hearing, approve, modify or reject the comprehensive plan prepared pursuant to this subsection.

(2) There shall be a joint committee of the Energy Conservation Management Board and the Renewable Energy Investments Board. The board and the advisory committee shall each appoint members to such joint committee. The joint committee shall examine opportunities to coordinate the programs and activities funded by the Renewable Energy Investment Fund pursuant to section 16-245n, as amended by this act, with the programs and activities contained in the plan developed under this subsection to reduce the long-term cost, environmental impacts and security risks of energy in the state. Such joint committee shall hold its first meeting on or before August 1, 2005.

(3) Programs included in the plan developed under subdivision (1) of this subsection shall be screened through cost-effectiveness testing which compares the value and payback period of program benefits to program costs to ensure that programs are designed to obtain energy savings and system benefits, including mitigation of federally mandated congestion charges, whose value is greater than the costs of the programs. Cost-effectiveness testing shall utilize available information obtained from real-time monitoring systems to ensure accurate validation and verification of energy use. Such testing shall include an analysis of the effects of investments on increasing the state's load factor. Program cost-effectiveness shall be reviewed annually, or otherwise as is practicable. If a program is determined to fail the cost-effectiveness test as part of the review process, it shall either be modified to meet the test or shall be terminated. On or before March 1, 2005, and on or before March first annually thereafter, the board shall provide a report, in accordance with the provisions of section 11-4a, to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment (A) that documents expenditures and fund balances and evaluates the cost-effectiveness of such programs conducted in the preceding year, and (B) that documents the extent to and manner in which the programs of such board collaborated and cooperated with programs, established under section 7-233y, of municipal electric energy cooperatives. To maximize the reduction of federally mandated congestion charges, programs in the plan may allow for disproportionate allocations between the amount of contributions to the Energy Conservation and Load Management Funds by a certain rate class and the programs that benefit such a rate class. Before conducting such evaluation, the board shall consult with the Renewable Energy Investments Board. The report shall include a description of the activities undertaken during the reporting period jointly or in collaboration with the Renewable Energy Investment Fund established pursuant to subsection (c) of section 16-245n, as amended by this act.

(4) Programs included in the plan developed under subdivision (1) of this subsection may include, but not be limited to: (A) Conservation and load management programs, including programs that benefit low-income individuals; (B) research, development and commercialization of products or processes which are more energy-efficient than those generally available; (C) development of markets for such products and processes; (D) support for energy use assessment, real-time monitoring systems, engineering studies and services related to new construction or major building renovation; (E) the design, manufacture, commercialization and purchase of energy-efficient appliances and heating, air conditioning and lighting devices; (F) program planning and evaluation; (G) indoor air quality programs relating to energy conservation; (H) joint fuel conservation initiatives programs targeted at reducing consumption of more than one fuel resource; (I) public education regarding conservation; and (J) the demand-side technology programs recommended by the procurement plan approved by the Department of [Public Utility Control] Energy and Environmental Protection pursuant to section 16a-3a. Such support may be by direct funding, manufacturers' rebates, sale price and loan subsidies, leases and promotional and educational activities. The plan shall also provide for expenditures by the Energy Conservation Management Board for the retention of expert consultants and reasonable administrative costs provided such consultants shall not be employed by, or have any contractual relationship with, an electric distribution company. Such costs shall not exceed five per cent of the total revenue collected from the assessment.

(e) Notwithstanding the provisions of subsections (a) to (d), inclusive, of this section, the Department of Public Utility Control shall authorize the disbursement of a total of one million dollars in each month, commencing with July, 2003, and ending with July, 2005, from the Energy Conservation and Load Management Funds established pursuant to said subsections. The amount disbursed from each Energy Conservation and Load Management Fund shall be proportionately based on the receipts received by each fund. Such disbursements shall be deposited in the General Fund.

(f) No later than December 31, 2006, and no later than December thirty-first every five years thereafter, the Energy Conservation Management Board shall, after consulting with the Renewable Energy Investments Board, conduct an evaluation of the performance of the programs and activities of the fund and submit a report, in accordance with the provisions of section 11-4a, of the evaluation to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

(g) Repealed by P.A. 06-186, S. 91, effective July 1, 2006.

Sec. 47. Section 16-245n of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) For purposes of this section, "renewable energy" means solar photovoltaic energy, solar thermal, geothermal energy, wind, ocean thermal energy, wave or tidal energy, fuel cells, landfill gas, hydropower that meets the low-impact standards of the Low-Impact Hydropower Institute, hydrogen production and hydrogen conversion technologies, low emission advanced biomass conversion technologies, alternative fuels, used for electricity generation including ethanol, biodiesel or other fuel produced in Connecticut and derived from agricultural produce, food waste or waste vegetable oil, provided the Commissioner of Energy and Environmental Protection determines that such fuels provide net reductions in greenhouse gas emissions and fossil fuel consumption, usable electricity from combined heat and power systems with waste heat recovery systems, thermal storage systems and other energy resources and emerging technologies which have significant potential for commercialization and which do not involve the combustion of coal, petroleum or petroleum products, municipal solid waste or nuclear fission.

(b) On and after July 1, 2004, the Department of [Public Utility Control] Energy and Environmental Protection's Bureau of Public Utility shall assess or cause to be assessed a charge of not less than one mill per kilowatt hour charged to each end use customer of electric services in this state which shall be deposited into the Renewable Energy Investment Fund established under subsection (c) of this section. Notwithstanding the provisions of this section, receipts from such charges shall be disbursed to the resources of the General Fund during the period from July 1, 2003, to June 30, 2005, unless the department shall, on or before October 30, 2003, issue a financing order for each affected distribution company in accordance with sections 16-245e to 16-245k, inclusive, to sustain funding of renewable energy investment programs by substituting an equivalent amount, as determined by the department in such financing order, of proceeds of rate reduction bonds for disbursement to the resources of the General Fund during the period from July 1, 2003, to June 30, 2005. The department may authorize in such financing order the issuance of rate reduction bonds that substitute for disbursement to the General Fund for receipts of both charges under this subsection and subsection (a) of section 16-245m, as amended by this act, and also may in its discretion authorize the issuance of rate reduction bonds under this subsection and subsection (a) of section 16-245m, as amended by this act, that relate to more than one electric distribution company. The department shall, in such financing order or other appropriate order, offset any increase in the competitive transition assessment necessary to pay principal, premium, if any, interest and expenses of the issuance of such rate reduction bonds by making an equivalent reduction to the charges imposed under this subsection, provided any failure to offset all or any portion of such increase in the competitive transition assessment shall not affect the need to implement the full amount of such increase as required by this subsection and sections 16-245e to 16-245k, inclusive. Such financing order shall also provide if the rate reduction bonds are not issued, any unrecovered funds expended and committed by the electric distribution companies for renewable resource investment through deposits into the Renewable Energy Investment Fund, provided such expenditures were approved by the department following August 20, 2003, and prior to the date of determination that the rate reduction bonds cannot be issued, shall be recovered by the companies from their respective competitive transition assessment or systems benefits charge except that such expenditures shall not exceed one million dollars per month. All receipts from the remaining charges imposed under this subsection, after reduction of such charges to offset the increase in the competitive transition assessment as provided in this subsection, shall be disbursed to the Renewable Energy Investment Fund commencing as of July 1, 2003. Any increase in the competitive transition assessment or decrease in the renewable energy investment component of an electric distribution company's rates resulting from the issuance of or obligations under rate reduction bonds shall be included as rate adjustments on customer bills.

(c) There is hereby created a Renewable Energy Investment Fund. [which shall be within Connecticut Innovations, Incorporated for administrative purposes only.] The fund may receive any amount required by law to be deposited into the fund and may receive any federal funds as may become available to the state for renewable energy investments. Upon authorization of the Renewable Energy Investments Board established pursuant to subsection (d) of this section, [Connecticut Innovations, Incorporated,] the department may use any amount in said fund for expenditures that promote investment in renewable energy sources in accordance with a comprehensive plan developed by it to foster the growth, development and commercialization of renewable energy sources, related enterprises and stimulate demand for renewable energy and deployment of renewable energy sources that serve end use customers in this state and for the further purpose of supporting operational demonstration projects for advanced technologies that reduce energy use from traditional sources. Such expenditures may include, but not be limited to, reimbursement for services provided by the administrator of the fund including a management fee, disbursements from the fund to develop and carry out the plan developed pursuant to subsection (d) of this section, grants, direct or equity investments, contracts or other actions which support research, development, manufacture, commercialization, deployment and installation of renewable energy technologies, and actions which expand the expertise of individuals, businesses and lending institutions with regard to renewable energy technologies.

(d) There is hereby created a Renewable Energy Investments Board to act on matters related to the Renewable Energy Investment Fund, including, but not limited to, development of a comprehensive plan and expenditure of funds. The Renewable Energy Investments Board shall, in such plan, give preference to projects that maximize the reduction of federally mandated congestion charges. The Renewable Energy Investments Board shall make a draft of the comprehensive plan available for public comment for not less than thirty days. The board shall conduct three public hearings in three different regions of the state on the draft comprehensive plan and shall include a summarization of all public comments received at said public hearings in the final comprehensive plan approved by the board. The board shall provide a copy of the comprehensive plan, in accordance with the provisions of section 11-4a, to the joint standing committees of the General Assembly having cognizance of matters relating to energy and commerce. The Department of [Public Utility Control] Energy and Environmental Protection shall, in an uncontested proceeding, during which the department may hold a public hearing, approve, modify or reject the comprehensive plan prepared pursuant to this subsection.

(e) The Renewable Energy Investments Board shall include not more than fifteen individuals with knowledge and experience in matters related to the purpose and activities of the Renewable Energy Investment Fund. The board shall consist of the following members: (1) One person with expertise regarding renewable energy resources appointed by the speaker of the House of Representatives; (2) one person representing a state or regional organization primarily concerned with environmental protection appointed by the president pro tempore of the Senate; (3) one person with experience in business or commercial investments appointed by the majority leader of the House of Representatives; (4) one person representing a state or regional organization primarily concerned with environmental protection appointed by the majority leader of the Senate; (5) one person with experience in business or commercial investments appointed by the minority leader of the House of Representatives; (6) the Commissioner of Emergency Management and Homeland Security or the commissioner's designee; (7) one person with expertise regarding renewable energy resources appointed by the Governor; (8) two persons with experience in business or commercial investments appointed by the board of directors of Connecticut Innovations, Incorporated; (9) a representative of a state-wide business association, manufacturing association or chamber of commerce appointed by the minority leader of the Senate; (10) the Consumer Counsel; (11) the Secretary of the Office of Policy and Management or the secretary's designee; (12) the Commissioner of Energy and Environmental Protection or the commissioner's designee; (13) a representative of organized labor appointed by the Governor; and (14) a representative of residential customers or low-income customers appointed by Governor. On a biennial basis, the board shall elect a chairperson and vice-chairperson from among its members and shall adopt such bylaws and procedures it deems necessary to carry out its functions. The board may establish committees and subcommittees as necessary to conduct its business.

(f) The board shall issue annually a report to the Department of [Public Utility Control] Energy and Environmental Protection reviewing the activities of the Renewable Energy Investment Fund in detail, including the condominium renewable energy grant program established pursuant to section 65 of this act, and shall provide a copy of such report, in accordance with the provisions of section 11-4a, to the joint standing committees of the General Assembly having cognizance of matters relating to energy and commerce and the Office of Consumer Counsel. The report shall include a description of the programs and activities undertaken during the reporting period jointly or in collaboration with the Energy Conservation and Load Management Funds established pursuant to section 16-245m, as amended by this act.

(g) There shall be a joint committee of the Energy Conservation Management Board and the Renewable Energy Investments Board, as provided in subdivision (2) of subsection (d) of section 16-245m, as amended by this act.

(h) No later than December 31, 2006, and no later than December thirty-first every five years thereafter, the board shall, after consulting with the Energy Conservation Management Board, conduct an evaluation of the performance of the programs and activities of the fund and submit a report, in accordance with the provisions of section 11-4a, of the evaluation to the joint standing committees of the General Assembly having cognizance of matters relating to energy and commerce.

Sec. 48. Section 16a-3a of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The [electric distribution companies, in consultation with the Connecticut Energy Advisory Board, established pursuant to section 16a-3,] Department of Energy and Environmental Protection shall review the state's energy and capacity resource assessment and develop a comprehensive plan for the procurement of energy resources, including, but not limited to, conventional and renewable generating facilities, energy efficiency, load management, demand response, combined heat and power facilities, distributed generation and other emerging energy technologies to meet the projected requirements of their customers in a manner that minimizes the cost of such resources to customers over time and maximizes consumer benefits consistent with the state's environmental goals and standards. Such plan shall seek to lower the cost of electricity.

(b) On or before January 1, 2008, and biennially thereafter, the Department of Energy and Environmental Protection, in consultation with the Connecticut Energy Advisory Board and the companies, shall [submit to the Connecticut Energy Advisory Board] prepare an assessment of (1) the energy and capacity requirements of customers for the next three, five and ten years, (2) the manner of how best to eliminate growth in electric demand, (3) how best to level electric demand in the state by reducing peak demand and shifting demand to off-peak periods, (4) the impact of current and projected environmental standards, including, but not limited to, those related to greenhouse gas emissions and the federal Clean Air Act goals and how different resources could help achieve those standards and goals, (5) energy security and economic risks associated with potential energy resources, and (6) the estimated lifetime cost and availability of potential energy resources.

(c) Resource needs shall first be met through all available energy efficiency and demand reduction resources that are cost-effective, reliable and feasible. The projected customer cost impact of any demand-side resources considered pursuant to this subsection shall be reviewed on an equitable bases with nondemand-side resources. The procurement plan shall specify (1) the total amount of energy and capacity resources needed to meet the requirements of all customers, (2) the extent to which demand-side measures, including efficiency, conservation, demand response and load management can cost-effectively meet these needs, (3) needs for generating capacity and transmission and distribution improvements, (4) how the development of such resources will reduce and stabilize the costs of electricity to consumers, and (5) the manner in which each of the proposed resources should be procured, including the optimal contract periods for various resources.

(d) The procurement plan shall consider: (1) Approaches to maximizing the impact of demand-side measures; (2) the extent to which generation needs can be met by renewable and combined heat and power facilities; (3) the optimization of the use of generation sites and generation portfolio existing within the state; (4) fuel types, diversity, availability, firmness of supply and security and environmental impacts thereof, including impacts on meeting the state's greenhouse gas emission goals; (5) reliability, peak load and energy forecasts, system contingencies and existing resource availabilities; (6) import limitations and the appropriate reliance on such imports; and (7) the impact of the procurement plan on the costs of electric customers. Such plan shall include options for lowering the cost of electricity.

(e) The [board, in consultation with the regional independent system operator, shall review and approve or review, modify and approve] Department of Energy and Environmental Protection, in consultation with the electric distribution companies, the regional independent system operator, and the Connecticut Energy Advisory Board, shall develop a procurement plan and hold public hearings on the proposed procurement plan. [as submitted not later than one hundred twenty days after receipt. For calendar years 2009 and thereafter, the board shall conduct such review not later than sixty days after receipt. For the purpose of reviewing the plan, the Commissioners of Transportation and Agriculture and the chairperson of the Public Utilities Control Authority, or their respective designees, shall not participate as members of the board. The electric distribution companies shall provide any additional information requested by the board that is relevant to the consideration of the procurement plan. In the course of conducting such review, the board shall conduct a public hearing, may retain the services of a third-party entity with experience in the area of energy procurement and may consult with the regional independent system operator. The board shall submit the reviewed procurement plan, together with a statement of any unresolved issues, to the Department of Public Utility Control. The department shall consider the procurement plan in an uncontested proceeding and shall conduct a hearing and provide an opportunity for interested parties to submit comments regarding the procurement plan. Not later than one hundred twenty days after submission of the procurement plan, the department shall approve, or modify and approve, the procurement plan.] The department's Bureau of Energy shall, after the public hearing, make recommendations to the Commissioner of Energy and Environmental Protection regarding plan modifications. Said commissioner shall approve, modify or reject the plan.

(f) On or before September 30, [2009] 2011, and every two years thereafter, the Department of [Public Utility Control] Energy and Environmental Protection shall report to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment regarding goals established and progress toward implementation of the procurement plan established pursuant to this section, as well as any recommendations for the process.

(g) All electric distribution companies' costs associated with the development of the resource assessment and the development of the procurement plan shall be recoverable through the systems benefits charge.

Sec. 49. (NEW) (Effective from passage) (a) The plan developed, pursuant to section 16a-3a of the general statutes, as amended by this act, to be adopted in 2012 shall (1) indicate specific options to reduce the price of electricity and maintain such reductions for another five years. Such options may include the procurement of new sources of generation. In reviewing new sources of generation, the plan shall determine whether the private wholesale market can supply such additional sources or whether state financial assistance, long-term purchasing of electricity contracts or other interventions are needed to achieve the goal; (2) analyze in-state renewable sources of electricity in comparison to transmission line upgrades or new projects and out-of-state renewable energy sources, provided such analysis also considers the benefits of additional jobs and other economic impacts; (3) include an examination of other states' best practices to determine why electricity rates are lower elsewhere in the region; (4) assess and compare the cost of transmission line projects, new power sources, renewable sources of electricity, conservation and distributed generation projects to ensure the state pursues only the least-cost alternative projects; (5) continually monitor supply and distribution systems to identify potential need for transmission line projects early enough to identify alternatives; and (6) assess the least cost alternative to address reliability concerns, including, but not limited to, lowering electricity demand through conservation and distributed generation projects before an electric distribution company submits a proposal for transmission lines or transmission line upgrades to the independent system operator or the Federal Energy Regulatory Commission.

(b) If, on and after July 1, 2012, the 2012 plan contains an option to procure new sources of generation, the Department of Energy and Environmental Protection shall pursue the most cost-effective approach. If the department seeks new sources of generation, it shall issue a notice of interest for generation without any financial assistance, including, but not limited to, long-term contract financing or ratepayer guarantees. If the department fails to receive any responsive proposal, it shall issue a request for proposals that may include such financial assistance.

(c) On or before February 1, 2012, the department shall report to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding state policy and legislative changes the department feels would most likely lower the state's electricity rates.

Sec. 50. (NEW) (Effective July 1, 2011) (a) On or before June 30, 2012, the Department of Energy and Environmental Protection shall conduct a proceeding regarding development of low-income discounted rates for service provided by electric distribution companies, as defined in section 16-1 of the general statutes, as amended by this act, to low-income customers with an annual income that does not exceed sixty per cent of median income. Such proceeding shall include, but not be limited to, a review, for individuals who receive means-tested assistance administered by the state or federal governments, of the current and future availability of rate discounts through the department's electricity purchasing pool operated pursuant to section 16a-14e of the general statutes, energy assistance benefits available through any plan adopted pursuant to section 16a-41a of the general statutes, state funded or administered programs, conservation assistance available pursuant to section 16-245m of the general statutes, as amended by this act, assistance funded or administered by said department or the Department of Social Services, or matching payment program benefits available pursuant to subsection (b) of section 16-262c of the general statutes. Such proceeding shall also include an analysis of the cost of imposing a utility termination moratorium in households with a child two years of age or younger. The department shall (1) coordinate resources and programs, to the extent practicable; (2) develop rates that take into account the indigency of persons of poverty status and allow such persons' households to meet the costs of essential energy needs; (3) encourage the households to agree to have a home energy audit as a prerequisite to qualification; and (4) prepare an analysis of the benefits and anticipated costs of such low-income discounted rates.

(b) The department shall determine which, if any, of its programs shall be modified, terminated or have their funding reduced because such program beneficiaries would benefit more by the establishment of a low-income or discount rate. The department shall establish a rate reduction that is equal to the anticipated funds transferred from the programs modified, terminated or reduced by the department pursuant to this section and the reduced cost of providing service to those eligible for such discounted or low-income rates, any available energy assistance and other sources of coverage for such rates, including, but not limited to, generation available through the electricity purchasing pool operated by the department. The department may issue recommendations regarding programs administered by the Department of Social Services.

(c) The department shall order (1) filing by each electric company of proposed rates consistent with the department's decision pursuant to subsection (a) of this section not later than sixty days after its issuance; and (2) appropriate modification of existing low-income programs. Each company shall conduct outreach to make its low-income or discounted rates available to eligible customers and report to the department at least annually regarding its outreach activities and the results of such activities.

(d) The cost of low-income and discounted rates and related outreach activities pursuant to this section shall be paid (1) through the normal rate-making procedures of the department, (2) on a semiannual basis through the systems benefits charge for an electric distribution company, and (3) solely from the funds of the programs modified, terminated or reduced by the department pursuant to this section and the reduced cost of providing service to those eligible for such discounted or low-income rates, any available energy assistance and other sources of coverage for such rates, including, but not limited to, generation available through the electricity purchasing pool operated by the department.

(e) On or before July 1, 2013, the department shall report, in accordance with section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the benefits and costs of the low-income or discounted rates established pursuant to subsection (a) of this section, including, but not limited to, possible impacts on existing customers who qualify for state assistance, and any recommended modifications. If the low-income rate is not less than ninety per cent of the standard service rate, the department shall include in its report steps to achieve that goal.

(f) The department shall adopt regulations, in accordance with the provisions of chapter 54 of the general statutes, to implement the provisions of this section.

Sec. 51. (NEW) (Effective July 1, 2011) (a) As used in this section:

(1) "Energy improvements" means any renovation or retrofitting of qualifying real property to reduce energy consumption or installation of a renewable energy system to service qualifying real property, provided such renovation, retrofit or installation is permanently fixed to such qualifying real property;

(2) "Qualifying real property" means a single-family or multifamily residential dwelling or a nonresidential commercial or industrial building, regardless of ownership, that a municipality has determined can benefit from energy improvements;

(3) "Property owner" means an owner of qualifying real property who desires to install energy improvements and provides free and willing consent to the contractual assessment; and

(4) "Sustainable energy program" means a municipal program that authorizes a municipality to enter into contractual assessments on qualifying real property with property owners to finance the purchase and installation of energy improvements to qualifying real property within its municipal boundaries.

(b) Any municipality, that determines it is in the public interest, may establish a sustainable energy program to facilitate the increase of energy efficiency and renewable energy. A municipality shall make such a determination after issuing public notice and providing an opportunity for public comment regarding the establishment of a sustainable energy program.

(c) Notwithstanding the provisions of section 7-374 of the general statutes or any other public or special act that limits or imposes conditions on municipal bond issues, any municipality that establishes a sustainable energy program under this section may issue bonds, as necessary, for the purpose of (1) financing energy improvements; (2) related energy audits; and (3) renewable energy system feasibility studies and the verification of the installation of such improvements. Such financing shall be secured by special contractual assessments on the qualifying real property.

(d) (1) Any municipality that establishes a sustainable energy program pursuant to this section may partner with another municipality or state agency to (A) maximize the opportunities for accessing public funds and private capital markets for long-term sustainable financing, and (B) secure state or federal funds available for this purpose.

(2) Any municipality that establishes a sustainable energy program and issues bonds pursuant to this section may supplement the security of such bonds with any other legally available funds solely at the municipality's discretion.

(3) Any municipality that establishes a sustainable energy program pursuant to this section may use the services of one or more private, public or quasi-public third-party administrators to provide support for the program.

(e) Before establishing a program under this section, the municipality shall provide notice to the electric distribution company, as defined in section 16-1 of the general statutes, as amended by this act, that services the municipality.

(f) If the owner of record of qualifying real property requests financing for energy improvements under this section, the municipality implementing the sustainable energy program shall:

(1) Require performance of an energy audit or renewable energy system feasibility analysis on the qualifying real property before approving such financing;

(2) Enter into a contractual assessment on the qualifying real property with the property owner in a principal amount sufficient to pay the costs of energy improvements and any associated costs the municipality determines will benefit the qualifying real property and may cover any associated costs;

(3) Impose requirements and criteria to ensure that the proposed energy improvements are consistent with the purpose of the program; and

(4) Impose requirements and conditions on the financing to ensure timely repayment, including, but not limited to, procedures for placing a lien on a property for which an owner defaults on repayment.

(g) Any assessment levied pursuant to this section shall have a term not to exceed the calculated payback period for the installed energy improvements, as determined by the municipality, and shall have no prepayment penalty. The municipality shall set a fixed rate of interest for the repayment of the principal assessed amount at the time the assessment is made. Such interest rate, as may be supplemented with state or federal funding as may become available, shall be sufficient to pay the financing costs of the program, including delinquencies.

(h) Assessments levied pursuant to this section and the interest and any penalties thereon shall constitute a lien against the qualifying real property on which they are made until they are paid. Such lien shall be levied and collected in the same manner as the general taxes of the municipality on real property, including, in the event of default or delinquency, with respect to any penalties and remedies and lien priorities, provided such lien shall not have priority over any prior mortgages.

(i) The area encompassing the sustainable energy program in a municipality may be the entire municipal jurisdiction of the municipality or a subset of such.

Sec. 52. Section 16-244c of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) (1) On and after January 1, 2000, each electric distribution company shall make available to all customers in its service area, the provision of electric generation and distribution services through a standard offer. Under the standard offer, a customer shall receive electric services at a rate established by the Department of [Public Utility Control] Energy and Environmental Protection pursuant to subdivision (2) of this subsection. Each electric distribution company shall provide electric generation services in accordance with such option to any customer who affirmatively chooses to receive electric generation services pursuant to the standard offer or does not or is unable to arrange for or maintain electric generation services with an electric supplier. The standard offer shall automatically terminate on January 1, 2004. While providing electric generation services under the standard offer, an electric distribution company may provide electric generation services through any of its generation entities or affiliates, provided such entities or affiliates are licensed pursuant to section 16-245, as amended by this act.

(2) Not later than October 1, 1999, the Department of [Public Utility Control] Energy and Environmental Protection shall establish the standard offer for each electric distribution company, effective January 1, 2000, which shall allocate the costs of such company among electric transmission and distribution services, electric generation services, the competitive transition assessment and the systems benefits charge. The department shall hold a hearing that shall be conducted as a contested case in accordance with chapter 54 to establish the standard offer. The standard offer shall provide that the total rate charged under the standard offer, including electric transmission and distribution services, the conservation and load management program charge described in section 16-245m, as amended by this act, the renewable energy investment charge described in section 16-245n, as amended by this act, electric generation services, the competitive transition assessment and the systems benefits charge shall be at least ten per cent less than the base rates, as defined in section 16-244a, in effect on December 31, 1996. The standard offer shall be adjusted to the extent of any increase or decrease in state taxes attributable to sections 12-264 and 12-265 and any other increase or decrease in state or federal taxes resulting from a change in state or federal law and shall continue to be adjusted during such period pursuant to section 16-19b. Notwithstanding the provisions of section 16-19b, the provisions of said section 16-19b shall apply to electric distribution companies. The standard offer may be adjusted, by an increase or decrease, to the extent approved by the department, in the event that (A) the revenue requirements of the company are affected as the result of changes in (i) legislative enactments other than public act 98-28, (ii) administrative requirements, or (iii) accounting standards occurring after July 1, 1998, provided such accounting standards are adopted by entities independent of the company that have authority to issue such standards, or (B) an electric distribution company incurs extraordinary and unanticipated expenses required for the provision of safe and reliable electric service to the extent necessary to provide such service. Savings attributable to a reduction in taxes shall not be shifted between customer classes.

(3) The price reduction provided in subdivision (2) of this subsection shall not apply to customers who, on or after July 1, 1998, are purchasing electric services from an electric company or electric distribution company, as the case may be, under a special contract or flexible rate tariff, and the company's filed standard offer tariffs shall reflect that such customers shall not receive the standard offer price reduction.

(b) (1) (A) On and after January 1, 2004, each electric distribution company shall make available to all customers in its service area, the provision of electric generation and distribution services through a transitional standard offer. Under the transitional standard offer, a customer shall receive electric services at a rate established by the Department of [Public Utility Control] Energy and Environmental Protection pursuant to subdivision (2) of this subsection. Each electric distribution company shall provide electric generation services in accordance with such option to any customer who affirmatively chooses to receive electric generation services pursuant to the transitional standard offer or does not or is unable to arrange for or maintain electric generation services with an electric supplier. The transitional standard offer shall terminate on December 31, 2006. While providing electric generation services under the transitional standard offer, an electric distribution company may provide electric generation services through any of its generation entities or affiliates, provided such entities or affiliates are licensed pursuant to section 16-245, as amended by this act.

(B) The department shall conduct a proceeding to determine whether a practical, effective, and cost-effective process exists under which an electric customer, when initiating electric service, may receive information regarding selecting electric generating services from a qualified entity. The department shall complete such proceeding on or before December 1, 2005, and shall implement the resulting decision on or before March 1, 2006, or on such later date that the department considers appropriate. An electric distribution company's costs of participating in the proceeding and implementing the results of the department's decision shall be recoverable by the company as generation services costs through an adjustment mechanism as approved by the department.

(2) (A) Not later than December 15, 2003, the Department of [Public Utility Control] Energy and Environmental Protection shall establish the transitional standard offer for each electric distribution company, effective January 1, 2004.

(B) The department shall hold a hearing that shall be conducted as a contested case in accordance with chapter 54 to establish the transitional standard offer. The transitional standard offer shall provide that the total rate charged under the transitional standard offer, including electric transmission and distribution services, the conservation and load management program charge described in section 16-245m, as amended by this act, the renewable energy investment charge described in section 16-245n, as amended by this act, electric generation services, the competitive transition assessment and the systems benefits charge, and excluding federally mandated congestion costs, shall not exceed the base rates, as defined in section 16-244a, in effect on December 31, 1996, excluding any rate reduction ordered by the department on September 26, 2002.

(C) (i) Each electric distribution company shall, on or before January 1, 2004, file with the department an application for an amendment of rates pursuant to section 16-19, which application shall include a four-year plan for the provision of electric transmission and distribution services. The department shall conduct a contested case proceeding pursuant to sections 16-19 and 16-19e to approve, reject or modify the application and plan. Upon the approval of such plan, as filed or as modified by the department, the department shall order that such plan shall establish the electric transmission and distribution services component of the transitional standard offer.

(ii) Notwithstanding the provisions of this subparagraph, an electric distribution company that, on or after September 1, 2002, completed a proceeding pursuant to sections 16-19 and 16-19e, shall not be required to file an application for an amendment of rates as required by this subparagraph. The department shall establish the electric transmission and distribution services component of the transitional standard offer for any such company equal to the electric transmission and distribution services component of the standard offer established pursuant to subsection (a) of this section in effect on July 1, 2003, for such company. If such electric distribution company applies to the department, pursuant to section 16-19, for an amendment of its rates on or before December 31, 2006, the application of the electric distribution company shall include a four-year plan.

(D) The transitional standard offer (i) shall be adjusted to the extent of any increase or decrease in state taxes attributable to sections 12-264 and 12-265 and any other increase or decrease in state or federal taxes resulting from a change in state or federal law, (ii) shall be adjusted to provide for the cost of contracts under subdivision (2) of subsection (j) of this section and the administrative costs for the procurement of such contracts, and (iii) shall continue to be adjusted during such period pursuant to section 16-19b. Savings attributable to a reduction in taxes shall not be shifted between customer classes. Notwithstanding the provisions of section 16-19b, the provisions of section 16-19b shall apply to electric distribution companies.

(E) The transitional standard offer may be adjusted, by an increase or decrease, to the extent approved by the department, in the event that (i) the revenue requirements of the company are affected as the result of changes in (I) legislative enactments other than public act 03-135 or public act 98-28, (II) administrative requirements, or (III) accounting standards adopted after July 1, 2003, provided such accounting standards are adopted by entities that are independent of the company and have authority to issue such standards, or (ii) an electric distribution company incurs extraordinary and unanticipated expenses required for the provision of safe and reliable electric service to the extent necessary to provide such service.

(3) The price provided in subdivision (2) of this subsection shall not apply to customers who, on or after July 1, 2003, purchase electric services from an electric company or electric distribution company, as the case may be, under a special contract or flexible rate tariff, provided the company's filed transitional standard offer tariffs shall reflect that such customers shall not receive the transitional standard offer price during the term of said contract or tariff.

(4) (A) In addition to its costs received pursuant to subsection (h) of this section, as compensation for providing transitional standard offer service, each electric distribution company shall receive an amount equal to five-tenths of one mill per kilowatt hour. Revenues from such compensation shall not be included in calculating the electric distribution company's earnings for purposes of, or in determining whether its rates are just and reasonable under, sections 16-19, 16-19a and 16-19e, including an earnings sharing mechanism. In addition, each electric distribution company may earn compensation for mitigating the prices of the contracts for the provision of electric generation services, as provided in subdivision (2) of this subsection.

(B) The department shall conduct a contested case proceeding pursuant to the provisions of chapter 54 to establish an incentive plan for the procurement of long-term contracts for transitional standard offer service by an electric distribution company. The incentive plan shall be based upon a comparison of the actual average firm full requirements service contract price for electricity obtained by the electric distribution company compared to the regional average firm full requirements service contract price for electricity, adjusted for such variables as the department deems appropriate, including, but not limited to, differences in locational marginal pricing. If the actual average firm full requirements service contract price obtained by the electric distribution company is less than the actual regional average firm full requirements service contract price for the previous year, the department shall split five-tenths of one mill per kilowatt hour equally between ratepayers and the company. Revenues from such incentive plan shall not be included in calculating the electric distribution company's earnings for purposes of, or in determining whether its rates are just and reasonable under sections 16-19, 16-19a and 16-19e. The department may, as it deems necessary, retain a third party entity with expertise in energy procurement to assist with the development of such incentive plan.

(c) (1) On and after January 1, 2007, each electric distribution company shall provide electric generation services through standard service to any customer who (A) does not arrange for or is not receiving electric generation services from an electric supplier, and (B) does not use a demand meter or has a maximum demand of less than five hundred kilowatts.

(2) Not later than October 1, 2006, and periodically as required by subdivision (3) of this subsection, but not more often than every calendar quarter, the Department of Public Utility Control shall establish the standard service price for such customers pursuant to subdivision (3) of this subsection. Each electric distribution company shall recover the actual net costs of procuring and providing electric generation services pursuant to this subsection, provided such company mitigates the costs it incurs for the procurement of electric generation services for customers who are no longer receiving service pursuant to this subsection.

(3) An electric distribution company providing electric generation services pursuant to this subsection shall [mitigate the variation of the price of the service offered to its customers by procuring] procure electric generation services contracts in the manner prescribed in [a plan approved by the department. Such plan shall require the procurement of a portfolio of service contracts sufficient to meet the projected load of the electric distribution company. Such plan shall require that the portfolio of service contracts be procured in an overlapping pattern of fixed periods at such times and in such manner and duration as the department determines to be most likely to produce just, reasonable and reasonably stable retail rates while reflecting underlying wholesale market prices over time. The portfolio of contracts shall be assembled in such manner as to invite competition; guard against favoritism, improvidence, extravagance, fraud and corruption; and secure a reliable electricity supply while avoiding unusual, anomalous or excessive pricing. The portfolio of contracts procured under such plan shall be for terms of not less than six months, provided contracts for shorter periods may be procured under such conditions as the department shall prescribe to (A) ensure the lowest rates possible for end-use customers; (B) ensure reliable service under extraordinary circumstances; and (C) ensure the prudent management of the contract portfolio] section 30 of this act. An electric distribution company may receive a bid for an electric generation services contract from any of its generation entities or affiliates, provided such generation entity or affiliate submits its bid the business day preceding the first day on which an unaffiliated electric supplier may submit its bid and further provided the electric distribution company and the generation entity or affiliate are in compliance with the code of conduct established in section 16-244h.

(4) [The] For standard service contracts procured prior to department approval of the plan developed pursuant to section 30 of this act, the department, in consultation with the Office of Consumer Counsel, [shall] may retain the services of a third-party entity with expertise in the area of energy procurement to oversee [the initial development of the] any request for proposals and the procurement of contracts by an electric distribution company or such entity selected by the department pursuant to subdivision (3) of this subsection, for the provision of electric generation services offered pursuant to this subsection. Costs associated with the retention of such third-party entity shall be included in the cost of electric generation services that is included in such price.

(5) [Each] For standard service contracts procured prior to department approval of the plan developed pursuant to section 66 of this act, each bidder for a standard service contract shall submit its bid to the electric distribution company or such entity selected by the department, pursuant to subdivision (3) of this subsection, and the third-party entity who shall jointly review the bids and submit an overview of all bids together with a joint recommendation to the department as to the preferred bidders. The department may, within ten business days of submission of the overview, reject the recommendation regarding preferred bidders. In the event that the department rejects the preferred bids, the electric distribution company or such entity selected by the department, pursuant to subdivision (2) of this subsection, and the third-party entity shall rebid the service pursuant to this subdivision. The department shall review each bid in an uncontested proceeding that shall include a public hearing and in which the Consumer Counsel and Attorney General may participate.

(d) (1) Notwithstanding the provisions of this section regarding the electric generation services component of the transitional standard offer or the procurement of electric generation services under standard service, section 16-244h or 16-245o, as amended by this act, the Department of [Public Utility Control] Energy and Environmental Protection may, from time to time, direct an electric distribution company to offer, through an electric supplier or electric suppliers, before January 1, 2007, one or more alternative transitional standard offer options or, on or after January 1, 2007, one or more alternative standard service options. Such alternative options shall include, but not be limited to, an option that consists of the provision of electric generation services that exceed the renewable portfolio standards established in section 16-245a and may include an option that utilizes strategies or technologies that reduce the overall consumption of electricity of the customer.

(2) (A) The department shall develop such alternative option or options in a contested case conducted in accordance with the provisions of chapter 54. The department shall determine the terms and conditions of such alternative option or options, including, but not limited to, (i) the minimum contract terms, including pricing, length and termination of the contract, and (ii) the minimum percentage of electricity derived from Class I or Class II renewable energy sources, if applicable. The electric distribution company shall, under the supervision of the department, subsequently conduct a bidding process in order to solicit electric suppliers to provide such alternative option or options.

(B) The department may reject some or all of the bids received pursuant to the bidding process.

(3) The department may require an electric supplier to provide forms of assurance to satisfy the department that the contracts resulting from the bidding process will be fulfilled.

(4) An electric supplier who fails to fulfill its contractual obligations resulting from this subdivision shall be subject to civil penalties, in accordance with the provisions of section 16-41, or the suspension or revocation of such supplier's license or a prohibition on the acceptance of new customers, following a hearing that is conducted as a contested case, in accordance with the provisions of chapter 54.

(e) (1) On and after January 1, 2007, an electric distribution company shall serve customers that are not eligible to receive standard service pursuant to subsection (c) of this section as the supplier of last resort. This subsection shall not apply to customers purchasing power under contracts entered into pursuant to section 16-19hh.

(2) An electric distribution company shall procure electricity at least every calendar quarter to provide electric generation services to customers pursuant to this subsection. The Department of [Public Utility Control] Energy and Environmental Protection shall determine a price for such customers that reflects the full cost of providing the electricity on a monthly basis. Each electric distribution company shall recover the actual net costs of procuring and providing electric generation services pursuant to this subsection, provided such company mitigates the costs it incurs for the procurement of electric generation services for customers that are no longer receiving service pursuant to this subsection.

(f) On and after January 1, 2000, and until such time the regional independent system operator implements procedures for the provision of back-up power to the satisfaction of the Department of [Public Utility Control] Energy and Environmental Protection, each electric distribution company shall provide electric generation services to any customer who has entered into a service contract with an electric supplier that fails to provide electric generation services for reasons other than the customer's failure to pay for such services. Between January 1, 2000, and December 31, 2006, an electric distribution company may procure electric generation services through a competitive bidding process or through any of its generation entities or affiliates. On and after January 1, 2007, such company shall procure electric generation services through a competitive bidding process pursuant to a plan submitted by the electric distribution company and approved by the department. Such company may procure electric generation services through any of its generation entities or affiliates, provided such entity or affiliate is the lowest qualified bidder and provided further any such entity or affiliate is licensed pursuant to section 16-245, as amended by this act.

(g) An electric distribution company is not required to be licensed pursuant to section 16-245, as amended by this act, to provide standard offer electric generation services in accordance with subsection (a) of this section, transitional standard offer service pursuant to subsection (b) of this section, standard service pursuant to subsection (c) of this section, supplier of last resort service pursuant to subsection (e) of this section or back-up electric generation service pursuant to subsection (f) of this section.

(h) The electric distribution company shall be entitled to recover reasonable costs incurred as a result of providing standard offer electric generation services pursuant to the provisions of subsection (a) of this section, transitional standard offer service pursuant to subsection (b) of this section, standard service pursuant to subsection (c) of this section or back-up electric generation service pursuant to subsection (f) of this section. The provisions of this section and section 16-244a shall satisfy the requirements of section 16-19a until January 1, 2007.

(i) The Department of [Public Utility Control] Energy and Environmental Protection shall establish, by regulations adopted pursuant to chapter 54, procedures for when and how a customer is notified that his electric supplier has defaulted and of the need for the customer to choose a new electric supplier within a reasonable period of time.

(j) (1) Notwithstanding the provisions of subsection (d) of this section regarding an alternative transitional standard offer option or an alternative standard service option, an electric distribution company providing transitional standard offer service, standard service, supplier of last resort service or back-up electric generation service in accordance with this section shall contract with its wholesale suppliers to comply with the renewable portfolio standards. The Department of [Public Utility Control] Energy and Environmental Protection shall annually conduct a contested case, in accordance with the provisions of chapter 54, in order to determine whether the electric distribution company's wholesale suppliers met the renewable portfolio standards during the preceding year. An electric distribution company shall include a provision in its contract with each wholesale supplier that requires the wholesale supplier to pay the electric distribution company an amount of five and one-half cents per kilowatt hour if the wholesale supplier fails to comply with the renewable portfolio standards during the subject annual period. The electric distribution company shall promptly transfer any payment received from the wholesale supplier for the failure to meet the renewable portfolio standards to the Renewable Energy Investment Fund for the development of Class I renewable energy sources. Any payment made pursuant to this section shall not be considered revenue or income to the electric distribution company.

(2) Notwithstanding the provisions of subsection (d) of this section regarding an alternative transitional standard offer option or an alternative standard service option, an electric distribution company providing transitional standard offer service, standard service, supplier of last resort service or back-up electric generation service in accordance with this section shall, not later than July 1, [2008] 2012, file with the Department of [Public Utility Control] Energy and Environmental Protection for its approval one or more long-term power purchase contracts from Class I renewable energy source projects located in Connecticut that receive funding from the Renewable Energy Investment Fund, [and that are not less than one megawatt in size,] at a price that is either, at the determination of the project owner, (A) not more than the total of the comparable wholesale market price for generation plus five and one-half cents per kilowatt hour, or (B) [fifty per cent of the wholesale market electricity cost at the point at which transmission lines intersect with each other or interface with the distribution system, plus the project cost of fuel indexed to natural gas futures contracts on the New York Mercantile Exchange at the natural gas pipeline interchange located in Vermillion Parish, Louisiana that serves as the delivery point for such futures contracts, plus the fuel delivery charge for transporting fuel to the project, plus five] twelve and one-half cents per kilowatt hour adjusted for inflation. The Department of Energy and Environmental Protection, in consultation with the Renewable Energy Investments Board, shall solicit offers from such projects not later than October 1, 2011. In its approval of such contracts, the department shall give preference to purchase contracts from those projects that would provide a financial benefit to ratepayers [or] and would enhance the reliability of the electric transmission system of the state. Such projects shall be located in this state. The one-hundred-fifty-megawatt limit for such projects may be exceeded only if the contracts for wind generation, Class I renewable energy sources and alternative renewable energy sources pursuant to this section and contracts committed as of the effective date of this section exceed such limit. The owner of a fuel cell project principally manufactured in this state shall be allocated all available air emissions credits and tax credits attributable to the project and no less than fifty per cent of the energy credits in the Class I renewable energy credits program established in section 16-245a attributable to the project. On and after October 1, 2007, and until September 30, 2008, such contracts shall be comprised of not less than a total, apportioned among each electric distribution company, of one hundred twenty-five megawatts; and on and after October 1, 2008, such contracts shall be comprised of not less than a total, apportioned among each electrical distribution company, of one hundred fifty megawatts. The cost of such contracts and the administrative costs for the procurement of such contracts directly incurred shall be eligible for inclusion in the adjustment to the transitional standard offer as provided in this section and any subsequent rates for standard service, provided such contracts are for a period of time sufficient to provide financing for such projects, but not less than ten years, and are for projects which began operation on or after July 1, 2003. Except as provided in this subdivision, the amount from Class I renewable energy sources contracted under such contracts shall be applied to reduce the applicable Class I renewable energy source portfolio standards. For purposes of this subdivision, the department's determination of the comparable wholesale market price for generation shall be based upon a reasonable estimate. On or before September 1, 2007, the department, in consultation with the Office of Consumer Counsel and the Renewable Energy Investments [Advisory Council] Board, shall study the operation of such renewable energy contracts and report its findings and recommendations to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

(k) (1) As used in this section:

(A) "Participating electric supplier" means an electric supplier that is licensed by the department to provide electric service, pursuant to this subsection, to residential or small commercial customers.

(B) "Residential customer" means a customer who is eligible for standard service and who takes electric distribution-related service from an electric distribution company pursuant to a residential tariff.

(C) "Small commercial customer" means a customer who is eligible for standard service and who takes electric distribution-related service from an electric distribution company pursuant to a small commercial tariff.

(D) "Qualifying electric offer" means an offer to provide full requirements commodity electric service and all other generation-related service to a residential or small commercial customer at a fixed price per kilowatt hour for a term of no less than one year.

(2) In the manner determined by the department, residential or small commercial service customers (A) initiating new utility service, (B) reinitiating service following a change of residence or business location, (C) making an inquiry regarding their utility rates, or (D) seeking information regarding energy efficiency shall be offered the option to learn about their ability to enroll with a participating electric supplier. Customers expressing an interest to learn about their electric supply options shall be informed of the qualifying electric offers then available from participating electric suppliers. The electric distribution companies shall describe then available qualifying electric offers through a method reviewed and approved by the department. The information conveyed to customers expressing an interest to learn about their electric supply options shall include, at a minimum, the price and term of the available electric supply option. Customers expressing an interest in a particular qualifying electric offer shall be immediately transferred to a call center operated by that participating electric supplier.

(3) Not later than September 1, 2007, the department shall establish terms and conditions under which a participating electric supplier can be included in the referral program described in subdivision (2) of this subsection. Such terms shall include, but not be limited to, requiring participating electrical suppliers to offer time-of-use and real-time use rates to residential customers.

(4) Each calendar quarter, participating electric suppliers shall be allowed to list qualifying offers to provide electric generation service to residential and small commercial customers with each customer's utility bill. The department shall determine the manner such information is presented in customers' utility bills.

(5) Any customer that receives electric generation service from a participating electric supplier may return to standard service or may choose another participating electric supplier at any time, including during the qualifying electric offer, without the imposition of any additional charges. Any customer that is receiving electric generation service from an electric distribution company pursuant to standard service can switch to another participating electric supplier at any time without the imposition of additional charges.

(l) Each electric distribution company shall offer to bill customers on behalf of participating electric suppliers and to pay such suppliers in a timely manner the amounts due such suppliers from customers for generation services, less a percentage of such amounts that reflects uncollectible bills and overdue payments as approved by the Department of [Public Utility Control] Energy and Environmental Protection.

(m) On or before July 1, 2007, the Department of [Public Utility Control] Energy and Environmental Protection shall initiate a proceeding to examine whether electric supplier bills rendered pursuant to section 16-245d, as amended by this act, and any regulations adopted thereunder sufficiently enable customers to compare pricing policies and charges among electric suppliers.

(n) The department shall conduct a proceeding to determine the cost of billing, collection and other services provided by the electric distribution companies or the department solely for the benefit of participating electric suppliers and aggregators. The department shall order an equitable allocation of such costs among electric suppliers and aggregators. As part of this same proceeding, the department shall also determine the costs that the electric distribution companies incur solely for the benefit of standard service and last resort service customers. The department shall allocate and provide for the equitable recovery of such costs from standard service or last resort service customers.

[(n)] (o) Nothing in the provisions of this section shall preclude an electric distribution company from entering into standard service supply contracts or standard service supply components with electric generating facilities.

Sec. 53. Section 16-245d of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) The Department of [Public Utility Control] Energy and Environmental Protection shall, by regulations adopted pursuant to chapter 54, develop a standard billing format that enables customers to compare pricing policies and charges among electric suppliers. [Not later than January 1, 2006, the] The department shall adopt regulations, in accordance with the provisions of chapter 54, to provide that an electric supplier, until October 1, 2011, may provide direct billing and collection services for electric generation services and related federally mandated congestion charges that such supplier provides to its customers [that have] with a maximum demand of not less than one hundred kilowatts [and] that choose to receive a bill directly from such supplier and, on and after October 1, 2011, shall provide direct billing and collection services for electric generation services and related federally mandated congestion charges that such suppliers provide to their customers or may choose to obtain such billing and collection service through an electric distribution company and pay its pro rata share in accordance with the provisions of subsection (h) of section 16-244c, as amended by this act. Any customer of an electric supplier, which is choosing to provide direct billing, who paid for the cost of billing and other services to an electric distribution company shall receive a credit on their monthly bill.

(1) An electric supplier that chooses to provide billing and collection services shall, in accordance with the billing format developed by the department, include the following information in each customer's bill: (A) The total amount owed by the customer, which shall be itemized to show (i) the electric generation services component and any additional charges imposed by the electric supplier, and (ii) federally mandated congestion charges applicable to the generation services; (B) any unpaid amounts from previous bills, which shall be listed separately from current charges; (C) the rate and usage for the current month and each of the previous twelve months in bar graph form or other visual format; (D) the payment due date; (E) the interest rate applicable to any unpaid amount; (F) the toll-free telephone number of the Department of Public Utility Control for questions or complaints; and (G) the toll-free telephone number and address of the electric supplier.

(2) An [electric company,] electric distribution company [or electric supplier that provides direct billing of the electric generation service component and related federally mandated congestion charges, as the case may be,] shall, in accordance with the billing format developed by the department, include the following information in each customer's bill: [, as appropriate: (1)] (A) The total amount owed by the customer, which shall be itemized to show, [(A)] (i) the electric generation services component [and any additional charges imposed by the electric supplier, if applicable, (B)] if the customer obtains standard service or last resort service from the electric distribution company, (ii) the distribution charge, including all applicable taxes and the systems benefits charge, as provided in section 16-245l, [(C)] (iii) the transmission rate as adjusted pursuant to subsection (d) of section 16-19b, [(D)] (iv) the competitive transition assessment, as provided in section 16-245g, [(E)] (v) federally mandated congestion charges, and [(F)] (vi) the conservation and renewable energy charge, consisting of the conservation and load management program charge, as provided in section 16-245m, as amended by this act, and the renewable energy investment charge, as provided in section 16-245n, as amended by this act; [(2)] (B) any unpaid amounts from previous bills which shall be listed separately from current charges; [(3)] (C) except for customers subject to a demand charge, the rate and usage for the current month and each of the previous twelve months in the form of a bar graph or other visual form; [(4)] (D) the payment due date; [(5)] (E) the interest rate applicable to any unpaid amount; [(6)] (F) the toll-free telephone number of the electric distribution company to report power losses; [(7)] (G) the toll-free telephone number of the Department of Public Utility Control for questions or complaints; [(8) the toll-free telephone number and address of the electric supplier; and (9)] and (H) if a customer has a demand of five hundred kilowatts or less during the preceding twelve months, a statement about the availability of information concerning electric suppliers pursuant to section 16-245p.

(b) The regulations shall provide guidelines for determining until October 1, 2011, the billing relationship between the electric distribution company and electric suppliers, including, but not limited to, the allocation of partial bill payments and late payments between the electric distribution company and the electric supplier. An electric distribution company that provides billing services for an electric supplier shall be entitled to recover from the electric supplier all reasonable transaction costs to provide such billing services as well as a reasonable rate of return, in accordance with the principles in subsection (a) of section 16-19e.

Sec. 54. Section 16-245o of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) To protect a customer's right to privacy from unwanted solicitation, each electric company or electric distribution company, as the case may be, shall distribute to each customer a form approved by the Department of [Public Utility Control] Energy and Environmental Protection which the customer shall submit to the customer's electric or electric distribution company in a timely manner if the customer does not want the customer's name, address, telephone number and rate class to be released to electric suppliers. On and after July 1, 1999, each electric or electric distribution company, as the case may be, shall make available to all electric suppliers customer names, addresses, telephone numbers, if known, and rate class, unless the electric company or electric distribution company has received a form from a customer requesting that such information not be released. Additional information about a customer for marketing purposes shall not be released to any electric supplier unless a customer consents to a release by one of the following: (1) An independent third-party telephone verification; (2) receipt of a written confirmation received in the mail from the customer after the customer has received an information package confirming any telephone agreement; (3) the customer signs a document fully explaining the nature and effect of the release; or (4) the customer's consent is obtained through electronic means, including, but not limited to, a computer transaction.

(b) All electric suppliers shall have equal access to customer information required to be disclosed under subsection (a) of this section. No electric supplier shall have preferential access to historical distribution company customer usage data.

(c) No electric or electric distribution company shall include in any bill or bill insert anything that directly or indirectly promotes a generation entity or affiliate of the electric distribution company. No electric supplier shall include a bill insert in an electric bill of an electric distribution company.

(d) All marketing information provided pursuant to the provisions of this section shall be formatted electronically by the electric company or electric distribution company, as the case may be, in a form that is readily usable by standard commercial software packages. Updated lists shall be made available within a reasonable time, as determined by the department, following a request by an electric supplier. Each electric supplier seeking the information shall pay a fee to the electric company or electric distribution company, as the case may be, which reflects the incremental costs of formatting, sorting and distributing this information, together with related software changes. Customers shall be entitled to any available individual information about their loads or usage at no cost.

(e) Each electric supplier shall, prior to the initiation of electric generation services, provide the potential customer with a written notice describing the rates, information on air emissions and resource mix of generation facilities operated by and under long-term contract to the supplier, terms and conditions of the service, and a notice describing the customer's right to cancel the service, as provided in this section. No electric supplier shall provide electric generation services unless the customer has signed a service contract or consents to such services by one of the following: (1) An independent third-party telephone verification; (2) receipt of a written confirmation received in the mail from the customer after the customer has received an information package confirming any telephone agreement; (3) the customer signs a [document fully explaining the nature and effect of the initiation of the service] contract that conforms with the provisions of this section; or (4) the customer's consent is obtained through electronic means, including, but not limited to, a computer transaction. Each electric supplier shall provide each customer with a demand of less than one hundred kilowatts, a written contract that conforms with the provisions of this section and maintain records of such signed service contract or consent to service for a period of not less than two years from the date of expiration of such contract, which records shall be provided to the division or the customer upon request. Each contract for electric generation services shall contain all material terms of the agreement, a clear and conspicuous statement explaining the rates that such customer will be paying, including the circumstances under which the rates may change, a statement that provides specific directions to the customer as to how to compare the price term in the contract to the customer's existing electric generation service charge on the electric bill and how long those rates are guaranteed. Such contract shall also include a clear and conspicuous statement providing the customer's right to cancel such contract not later than three days after signature or receipt in accordance with the provisions of this subsection, describing under what circumstances, if any, the supplier may terminate the contract and describing any penalty for early termination of such contract. Each contract shall be signed by the customer, or otherwise agreed to in accordance with the provisions of this subsection. A customer who has a maximum demand of five hundred kilowatts or less shall, until midnight of the third business day after the latter of the day on which the customer enters into a service agreement or the day on which the customer receives the written contract from the electric supplier as provided in this section, have the right to cancel a contract for electric generation services entered into with an electric supplier.

[(f) An electric supplier shall not advertise or disclose the price of electricity in such a manner as to mislead a reasonable person into believing that the electric generation services portion of the bill will be the total bill amount for the delivery of electricity to the customer's location. When advertising or disclosing the price for electricity, the electric supplier shall also disclose the electric distribution company's average current charges, including the competitive transition assessment and the systems benefits charge, for that customer class.]

(f) (1) Any third-party agent who contracts with or is otherwise compensated by an electric supplier to sell electric generation services shall be a legal agent of the electric supplier. No third-party agent may sell electric generation services on behalf of an electric supplier unless (A) the third-party agent is an employee or independent contractor of such electric supplier, and (B) the third-party agent has received appropriate training directly from such electric supplier.

(2) On or after July 1, 2011, all sales and solicitations of electric generation services by an electric supplier, aggregator or agent of an electric supplier or aggregator to a customer with a maximum demand of one hundred kilowatts or less conducted and consummated entirely by mail, door-to-door sale, telephone or other electronic means, during a scheduled appointment at the premises of a customer or at a fair, trade or business show, convention or exposition in addition to complying with the provisions of subsection (e) of this section shall:

(A) For any sale or solicitation, including from any person representing such electric supplier, aggregator or agent of an electric supplier or aggregator (i) identify the person and the electric generation services company or companies the person represents; (ii) provide a statement that the person does not represent an electric distribution company; (iii) explain the purpose of the solicitation; and (iv) explain all rates, fees, variable charges and terms and conditions for the services provided; and

(B) For door-to-door sales to customers with a maximum demand of one hundred kilowatts, which shall include the sale of electric generation services in which the electric supplier, aggregator or agent of an electric supplier or aggregator solicits the sale and receives the customer's agreement or offer to purchase at a place other than the seller's place of business, be conducted (i) in accordance with any municipal and local ordinances regarding door-to-door solicitations, (ii) between the hours of ten o'clock a.m. and six o'clock p.m., and (iii) with both English and Spanish written materials available. Any representative of an electric supplier, aggregator or agent of an electric supplier or aggregator shall prominently display or wear a photo identification badge stating the name of such person's employer or the electric supplier the person represents. Each such supplier, aggregator or agent shall conduct a criminal background check on each person such entity employs to conduct such door-to-door sales and no one who has been convicted of a felony or a misdemeanor involving robbery, theft, misrepresentation or any other similar crime shall be employed to conduct such sales.

(3) No electric supplier, aggregator or agent of an electric supplier or aggregator shall advertise or disclose the price of electricity to mislead a reasonable person into believing that the electric generation services portion of the bill will be the total bill amount for the delivery of electricity to the customer's location. When advertising or disclosing the price for electricity, the electric supplier, aggregator or agent of an electric supplier or aggregator shall also disclose the electric distribution company's current charges, including the competitive transition assessment and the systems benefits charge, for that customer class.

(4) No entity, including an aggregator or agent of an electric supplier or aggregator, who sells or offers for sale any electric generation services for or on behalf of an electric supplier, shall engage in any deceptive acts or practices in the marketing, sale or solicitation of electric generation services.

(5) Each electric supplier shall disclose to the Department of Public Utility Control in a standardized format (A) the amount of additional renewable energy credits such supplier will purchase beyond required credits, (B) where such additional credits are being sourced from, and (C) the types of renewable energy sources that will be purchased. Each electric supplier shall only advertise renewable energy credits purchased beyond those required pursuant to section 16-245a and shall report to the department the renewable energy sources of such credits and whenever the mix of such sources changes.

(6) No contract for electric generation services by an electric supplier shall require a residential customer to pay any fee for termination or early cancellation of a contract in excess of (A) one hundred dollars; or (B) twice the estimated bill for energy services for an average month, whichever is less, provided when an electric supplier offers a contract, it provides the residential customer an estimate of such customer's average monthly bill.

(7) An electric supplier shall not make a material change in the terms or duration of any contract for the provision of electric generation services by an electric supplier without the express consent of the customer. Nothing in this subdivision shall restrict an electric supplier from renewing a contract by clearly informing the customer, in writing, not less than thirty days nor more than sixty days before the renewal date, of the renewal terms and of the option not to accept the renewal offer, provided no fee pursuant to subdivision (6) of this section shall be charged to a customer who terminates or cancels such renewal not later than seven business days after receiving the first billing statement for the renewed contract.

(g) Each electric supplier, aggregator or agent of an electric supplier or aggregator shall comply with the provisions of the telemarketing regulations adopted pursuant to 15 USC 6102.

(h) Any violation of this section shall be deemed an unfair or deceptive trade practice under subsection (a) of section 42-110b. Any contract for electric generation services that the division finds to be the product of unfair or deceptive marketing practices or in material violation of the provisions of this section shall be void and unenforceable. Any waiver of the provisions of this section by a customer of electric generation services shall be deemed void and unenforceable by the electric supplier.

(i) Any violation or failure to comply with any provision of this section shall be subject to (1) civil penalties by the department in accordance with section 16-41, (2) the suspension or revocation of an electric supplier or aggregator's license, or (3) a prohibition on accepting new customers following a hearing that is conducted as a contested case in accordance with chapter 54.

(j) The department may adopt regulations, in accordance with the provisions of chapter 54, to include, but not be limited to, abusive switching practices, solicitations and renewals by electric suppliers.

Sec. 55. Subsection (g) of section 16-245 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(g) As conditions of continued licensure, in addition to the requirements of subsection (c) of this section: (1) The licensee shall comply with the National Labor Relations Act and regulations, if applicable; (2) the licensee shall comply with the Connecticut Unfair Trade Practices Act and applicable regulations; (3) each generating facility operated by or under long-term contract to the licensee shall comply with regulations adopted by the Commissioner of Energy and Environmental Protection, pursuant to section 22a-174j; (4) the licensee shall comply with the portfolio standards, pursuant to section 16-245a; (5) the licensee shall be a member of the New England Power Pool or its successor or have a contractual relationship with one or more entities who are members of the New England Power Pool or its successor and the licensee shall comply with the rules of the regional independent system operator and standards and any other reliability guidelines of the regional independent systems operator; (6) the licensee shall agree to cooperate with the department and other electric suppliers in the event of an emergency condition that may jeopardize the safety and reliability of electric service; (7) the licensee shall comply with the code of conduct established pursuant to section 16-244h; (8) for a license to a participating municipal electric utility, the licensee shall provide open and nondiscriminatory access to its distribution facilities to other licensed electric suppliers; (9) the licensee or the entity or entities with whom the licensee has a contractual relationship to purchase power shall be in compliance with all applicable licensing requirements of the Federal Energy Regulatory Commission; (10) each generating facility operated by or under long-term contract to the licensee shall be in compliance with chapter 277a and state environmental laws and regulations; (11) the licensee shall comply with the renewable portfolio standards established in section 16-245a; (12) the licensee shall offer a time-of-use rate option to customers that provides for a peak period use rate of at least a five hundred per cent increase in the standard nonpeak use rate. Such peak period shall be not more than four hours in any twenty-four-hour period. The standard nonpeak use rate under this option shall be less than the standard use rate offer by such supplier to the customer. Nothing in this subdivision shall preclude such supplier from offering other time of use options; and [(12)] (13) the licensee shall acknowledge that it is subject to chapters 208, 212, 212a and 219, as applicable, and the licensee shall pay all taxes it is subject to in this state. Also as a condition of licensure, the department shall prohibit each licensee from declining to provide service to customers for the reason that the customers are located in economically distressed areas. The department may establish additional reasonable conditions to assure that all retail customers will continue to have access to electric generation services.

Sec. 56. (NEW) (Effective July 1, 2011) (a) For the two-year period starting January 1, 2012, and ending June 30, 2014, the aggregate net annual cost recovered from electric ratepayers pursuant to sections 57 to 62, inclusive, of this act, shall not exceed one-half of one per cent of total retail electricity sales revenues of each electric distribution company. For the two-year period starting July 1, 2014, and ending June 30, 2016, the aggregate net annual cost recovered for electric ratepayers pursuant to sections 57 to 62, inclusive, of this act and subsection (i) of section 16-245n of the general statutes, as amended by this act, shall not exceed three-fourths of one per cent of total retail electricity sales revenues of each electric distribution company. For each twelve-month period starting July 1, 2016, and every July first thereafter for the duration of the solar programs established pursuant to sections 57 to 62, inclusive, of this act and subsection (i) of section 16-245n of the general statutes, as amended by this act, the aggregate net cost of such programs recovered for electric ratepayers shall not exceed one per cent of total retail electricity sales revenues of each electric distribution company.

(b) The Department of Energy and Environmental Protection shall net out the incentives paid by the Renewable Energy Investment Fund pursuant to section 16-245n of the general statutes, as amended by this act, for solar deployment programs against the aggregate annual costs identified in this section.

(c) The Department of Energy and Environmental Protection shall report to the joint standing committee of the General Assembly having cognizance of matters relating to energy when the annual cost cap is within twenty per cent of being exceeded. If the department projects that the annual cost cap will be exceeded, the department shall take measures to ensure such cap will not be exceeded. Such measures may include: (1) Delay or modify the development of solar electric generating facilities by electric distribution companies pursuant to subsection (e) of section 60 of this act; (2) temporarily suspend the availability of production-based incentives to customers not already eligible to receive such incentives under section 60 of this act; and (3) extend the scheduled electric distribution company solar renewable energy credit procurement plans under subsection (i) of section 16-245n of the general statutes, as amended by this act. If the department determines that cost mitigation measures are required, it shall reduce proportionally the annual funding for the programs identified in subdivisions (1) to (3), inclusive, of this subsection and only to the extent required to bring projected annual costs below the cost cap.

(d) On or before January 1, 2015, the Department of Energy and Environmental Protection shall report to the joint standing committee of the General Assembly having cognizance of matters relating to energy on the cost and charges involved in the implementation of this program, including a cost-benefit analysis.

Sec. 57. (NEW) (Effective July 1, 2011) (a) The Renewable Energy Investments Board, created in section 16-245n of the general statutes, as amended by this act, shall structure and implement a residential solar investment program pursuant to this section and shall result in a minimum of thirty megawatts of new residential solar photovoltaic installations located in this state on or before December 31, 2022. For the purposes of this section and sections 65 and 66 of this act, "residential" means dwellings with one to four units.

(b) The Renewable Energy Investments Board shall offer direct financial incentives, in the form of performance-based incentives or expected performance-based buydowns, for the purchase or lease of qualifying residential solar photovoltaic systems. For the purposes of this section, "performance-based incentives" means incentives paid out on a per kilowatt-hour basis, and "expected performance-based buydowns" means incentives paid out as a one-time upfront incentive based on expected system performance. The board shall consider willingness to pay studies and verified solar photovoltaic system characteristics, such as operational efficiency, size, location, shading and orientation, when determining the type and amount of incentive. Notwithstanding the provisions of subdivision (1) of subsection (j) of section 16-244c of the general statutes, as amended by this act, the amount of renewable energy produced from Class I renewable energy sources receiving tariff payments or included in utility rates under this section shall be applied to reduce the electric distribution company's Class I renewable energy source portfolio standard.

(c) Beginning with the comprehensive plan covering the period from July 1, 2011, to June 30, 2013, the Renewable Energy Investments Board shall develop and publish in each such plan a proposed schedule for the offering of performance-based incentives or expected performance-based buydowns over the duration of any such solar incentive program. Such schedule shall: (1) Provide for a series of solar capacity blocks the combined total of which shall be a minimum of thirty megawatts and projected incentive levels for each such block; (2) provide incentives that are sufficient to meet reasonable payback expectations of the residential consumer, taking into consideration the estimated cost of residential solar installations, the value of the energy offset by the system and the availability and estimated value of other incentives, including, but not limited to, federal and state tax incentives and revenues from the sale of solar renewable energy credits; (3) provide incentives that decline over time and will foster the sustained, orderly development of a state-based solar industry; (4) automatically adjust to the next block once the board has issued reservations for financial incentives provided pursuant to this section from the board fully committing the target solar capacity and available incentives in that block; and (5) provide comparable economic incentives for the purchase or lease of qualifying residential solar photovoltaic systems. The board may retain the services of a third-party entity with expertise in the area of solar energy program design to assist in the development of the incentive schedule or schedules. The department shall review and approve such schedule. Nothing in this subsection shall restrict the board from modifying the approved incentive schedule before the issuance of its next comprehensive plan to account for changes in federal or state law or regulation or developments in the solar market when such changes would affect the expected return on investment for a typical residential solar photovoltaic system by twenty per cent or more.

(d) The Renewable Energy Investments Board shall establish and periodically update program guidelines, including, but not limited to, requirements for systems and program participants related to: (1) Eligibility criteria; (2) standards for deployment of energy efficient equipment or building practices as a condition for receiving incentive funding; (3) procedures to provide reasonable assurance that such reservations are made and incentives are paid out only to qualifying residential solar photovoltaic systems demonstrating a high likelihood of being installed and operated as indicated in application materials; and (4) reasonable protocols for the measurement and verification of energy production.

(e) The Renewable Energy Investments Board shall maintain on its web site the schedule of incentives, solar capacity remaining in the current block and available funding and incentive estimators.

(f) Funding for the residential performance-based incentive program and expected performance-based buydowns shall be apportioned from the moneys collected under the surcharge specified in section 16-245n of the general statutes, as amended by this act, provided such apportionment shall not exceed one-third of the total surcharge collected annually, and supplemented by federal funding as may become available.

(g) The Renewable Energy Investments Board shall identify barriers to the development of a permanent Connecticut-based solar workforce and shall make provision for comprehensive training, accreditation and certification programs through institutions and individuals accredited and certified to national standards.

(h) On or before January 1, 2014, and every two years thereafter for the duration of the program, the Renewable Energy Investments Board shall report to the joint standing committee of the General Assembly having cognizance of matters relating to energy on progress toward the goals identified in subsection (a) of this section.

Sec. 58. (NEW) (Effective July 1, 2011) (a) Commencing on January 1, 2012, and within the period established in subsection (a) of section 21 of this act, each electric distribution company shall solicit and file with the Department of Energy and Environmental Protection for its approval, one or more long-term power purchase contracts with owners or developers of customer-sited solar photovoltaic generation projects that are less than two thousand kilowatts in size, located on the customer side of the revenue meter and serve the distribution system of the electric distribution company.

(b) Solicitations conducted by the electric distribution company shall be for the purchase of solar renewable energy credits produced by eligible customer-sited solar photovoltaic generating projects over the duration of the long-term contract. For purposes of this section, a long-term contract is a contract for a minimum of fifteen years. The electric distribution company may solicit proposals for a combination of renewable energy and associated solar renewable energy credits.

(c) The aggregate procurement of solar renewable energy credits by electric distribution companies pursuant to this section shall be no less than four million three hundred fifty thousand. The production of a megawatt hour of electricity from a Class I solar renewable energy source first placed in service on or after the effective date of this section shall create one solar renewable energy credit. A solar renewable energy credit shall have an effective life covering the year in which the credit was created and the following calendar year. The obligation to purchase solar renewable energy credits shall be apportioned to electric distribution companies based on their respective distribution system loads at the commencement of the procurement period, as determined by the department. An electric distribution company shall not be required to enter into a contract that provides a payment of more than three hundred fifty dollars per megawatt hour in the initial year of the contract.

(d) Notwithstanding subdivision (1) of subsection (j) of section 16-244c of the general statutes, as amended by this act, an electric distribution company may retire the solar renewable energy credits it procures through long-term contracting to satisfy its obligation pursuant to section 16-245a of the general statutes.

(e) Nothing in this section shall preclude the resale or other disposition of energy or associated solar renewable energy credits purchased by the electric distribution company, provided the distribution company shall net the cost of payments made to projects under the long-term contracts against the proceeds of the sale of energy or solar renewable energy credits and the difference shall be credited or charged to distribution customers through a reconciling component of electric rates as determined by the department.

Sec. 59. (NEW) (Effective July 1, 2011) (a) Each electric distribution company shall, not later than one hundred eighty days after the effective date of this section, propose a five-year solar solicitation plan that shall include a timetable and methodology for soliciting proposals for long-term solar renewable energy credits or energy contracts from in-state generators and that shall end in calendar year 2022. The electric distribution company's solar solicitation plan shall be subject to the review and approval of the department, provided contracts comprising no less than twenty-five per cent of the electric distribution company's obligation shall be submitted for department approval on or before January 1, 2013, no less than fifty per cent of such obligation shall be submitted for such approval on or before July 1, 2015, and no less than seventy-five per cent of such obligation shall be submitted for such approval on or before July 1, 2017.

(b) The electric distribution company's approved solar solicitation plan shall be designed to foster a diversity of solar project sizes and participation among all eligible customer classes subject to cost-effectiveness considerations. Separate procurement processes shall be conducted for (1) systems up to fifty kilowatts; (2) systems greater than fifty kilowatts but less than two hundred kilowatts; and (3) systems between two hundred and two thousand kilowatts. The Department of Energy and Environmental Protection shall give preference to competitive bidding for resources of more than fifty kilowatts, unless the department determines that an alternative methodology is in the best interests of the electric distribution company's customers and the development of a competitive and self-sustaining solar market. Systems up to fifty kilowatts in size shall be eligible to receive, on an ongoing and continuous basis, a solar renewable energy credit offer price equivalent to the weighted average accepted bid price in the most recent solicitation for systems greater than fifty kilowatts but less than two hundred kilowatts, plus an additional incentive of ten per cent. Participation in the direct incentive program under section 56 of this act shall not disqualify an owner or operator of a qualified residential solar energy system to be eligible for this offer price. The offer price shall remain open at least until the electric distribution company has satisfied its procurement requirement for solar renewable energy credits, as specified in section 58 of this act. Once the offer price is closed, the owner or holder of a residential solar renewable energy credit may bid any outstanding or future credits in a competitive solicitation conducted by the electric distribution company pursuant to this subsection.

(c) Each electric distribution company shall execute its approved five-year solicitation plan and submit for review by the Department of Energy and Environmental Protection and approval of its preferred solar procurement plan comprised of any proposed contract or contracts with independent solar developers.

(d) The Department of Energy and Environmental Protection shall hold a hearing that shall be conducted as an uncontested case, in accordance with the provisions of chapter 54 of the general statutes, to approve, reject or modify an application for approval of the electric distribution company's solar procurement plan. The department shall only approve such proposed plan if the department finds that (1) the solicitation and evaluation conducted by the electric distribution company was the result of a fair, open, competitive and transparent process; (2) approval of the solar procurement plan would result in the greatest expected ratepayer value from solar energy or solar renewable energy credits at the lowest reasonable cost; and (3) such procurement plan satisfies other criteria established in the approved solicitation plan. The department shall not approve any proposal made under such plan unless it determines that the plan and proposals encompass all foreseeable sources of revenue or benefits and that such proposals, together with such revenue or benefits, would result in the greatest expected ratepayer value from solar energy or solar renewable energy credits. The department may, in its discretion, retain the services of an independent consultant with expertise in the area of energy procurement. The independent consultant shall be unaffiliated with the electric distribution company or its affiliates and shall not, directly or indirectly, have benefited from employment or contracts with the electric distribution company or its affiliates in the preceding five years, except as an independent consultant. For purposes of such audit, the electric distribution company shall provide the independent consultant immediate and continuing access to all documents and data reviewed, used or produced by the electric distribution company in its bid solicitation and evaluation process. The electric distribution company shall make all its personnel, agents and contractors used in the bid solicitation and evaluation available for interview by the consultant. The electric distribution company shall conduct any additional modeling requested by the independent auditor to test the assumptions and results of the bid evaluation process. The independent consultant shall not participate in or advise the electric distribution company with respect to any decisions in the bid solicitation or bid evaluation process. The department's administrative costs in reviewing the electric distribution company's solar procurement plan and the costs of the consultant shall be recovered through a reconciling component of electric rates as determined by the department.

(e) The electric distribution company shall be entitled to recover its reasonable costs of complying with its approved solar procurement plan through a reconciling component of electric rates as determined by the department.

(f) If, by January 1, 2013, the department has not received proposed long-term solar renewable energy credit contracts consisting of at least twenty-five per cent of each electric distribution company's procurement obligation or by July 1, 2015, has not received proposed long-term solar renewable energy contracts consisting of at least fifty per cent of each electric distribution company's procurement obligation, or by July 1, 2017, has not received proposed long-term solar renewable energy contracts consisting of at least seventy-five per cent of each electric distribution company's procurement obligation, respectively, the department shall notify the electric distribution company of the shortfall. Unless, upon petition by the electric distribution company, the department grants the distribution company an extension not to exceed ninety days to correct this deficiency, the electric distribution company shall be assessed a noncompliance fee of five hundred dollars for each solar renewable energy credit shortfall in the initial year of the procurement, with the per credit fee declining by seven per cent annually over the duration of the ten-year solicitation plan. The noncompliance fees associated with the procurement shortfall shall be collected by the distribution company, maintained in a separate interest-bearing account and disbursed to the department on a quarterly basis. Funds collected by the department pursuant to this section shall be used to support the deployment of solar photovoltaic generating systems installed in the state with priority given to otherwise underserved market segments, including, but not limited to, low-income housing, schools and other public buildings and nonprofits.

(g) No project that receives funding pursuant to this section shall be eligible for funding pursuant to section 61 of this act.

(h) Not later than sixty days after its approval of the distribution company procurement plans submitted on or before January 1, 2013, the Department of Energy and Environmental Protection shall submit a report to the joint standing committee of the General Assembly having cognizance of matters relating to energy. The report shall document for each distribution company procurement plan: (1) The total number of solar renewable energy credits bid relative to the number of solar renewable energy credits requested by the distribution company; (2) the total number of bidders in each market segment; (3) the number of contracts awarded; and (4) the total weighted average price of the solar renewable energy credits or energy so purchased. The department shall not report individual bid information or other proprietary information.

Sec. 60. (NEW) (Effective July 1, 2011) (a) On or before July 1, 2012, the Department of Energy and Environmental Protection, in consultation with the Office of Policy and Management and the Department of Public Works, shall, within available funding, complete, or cause to be completed by private vendors, a comprehensive solar feasibility survey of facilities owned or operated by the state with a load of fifty kilowatts or more. The survey shall rank state-owned or operated facilities based on their technical feasibility to accommodate solar photovoltaic generating systems by considering such factors as: (1) On-site energy consumption; (2) building orientation; (3) roof age and condition; (4) shading and the potential for obstruction to sunlight over the life of the solar system; (5) structural load capacity; (6) availability of ancillary facilities, such as parking lots, walkways or maintenance areas; (7) nonenergy related amenities; and (8) other factors that the Department of Energy and Environmental Protection deems may bear on the technical feasibility of such solar deployment.

(b) The Department of Energy and Environmental Protection, shall, within available funding, issue one or more requests for proposals for the deployment of solar photovoltaic generating systems at state-owned or operated facilities. Any such request for proposals shall be structured to maximize the state's ability to secure incentives available from the federal government or other sources. The department may seek in any request for proposals the services of an entity to finance, design, construct, own or maintain such solar photovoltaic system under a long-term solar services agreement. Any such entity chosen to provide such services shall not be considered a public service company under section 16-1 of the general statutes, as amended by this act.

Sec. 61. (NEW) (Effective July 1, 2011) (a) Each electric distribution company shall, not later than July 1, 2012, file with the Department of Energy and Environmental Protection for its approval a tariff for production-based payments to owners or operators of Class I solar renewable energy source projects located in this state that are not less than one megawatt and connected directly to the distribution system of an electric distribution company.

(b) Such tariffs shall provide production-based payments for a period not less than fifteen years from the in-service date of the Class I solar renewable energy source project at a price that is, at the determination of the Department of Energy and Environmental Protection, a cost-based payment consisting of the fully allocated cost of constructing and operating a Class I solar renewable energy source of from one megawatt to seven and one-half megawatts were such construction and operation to be undertaken or procured by the electric distribution company itself. In calculating the cost-based tariff, the department shall consider actual cost data for Class I solar energy sources constructed and operated by the electric distribution company pursuant to subsection (e) of this section taking into consideration all available state and federal incentives.

(c) Such tariffs shall include a per project eligibility cap of seven and one-half megawatts and an aggregate eligibility cap of fifty megawatts, apportioned among each electric distribution company in proportion to distribution load.

(d) The cost of such tariff payments shall be eligible for inclusion in any subsequent rates, provided such payments are for projects operational on or after the effective date of this section, and recovered through a reconciling component of electric rates as determined by the Department of Energy and Environmental Protection.

(e) On and after July 1, 2012, electric distribution companies may construct, own and operate solar electric generating facilities up to one-third of their proportional share of the total cap amounts specified under subsection (c) of this section, provided any such development shall be phased in over a period of no less than three years. Such projects shall be located on brownfields or other locations in a targeted investment community. The Department of Energy and Environmental Protection in a contested case, shall (1) authorize the electric distribution company to recover in rates its costs to construct, own and operate solar electric generating facilities, including a reasonable return on its investment not to exceed eight per cent, if such approval would result in a reasonable cost of meeting the solar energy requirements pursuant to said subsection (c) of this section and that such investment will not restrict competition or restrict growth in the state's solar energy industry or unfairly employ in a manner which would restrict competition in the market for solar energy systems any financial, marketing, distributing or generating advantage that the electric distribution company may exercise as a result of its authority to operate as a public service company, and (2) establish a mechanism for the electric distribution company to use a portion of such revenues to offset the development of an economic development rate to benefit residents of such targeted investment community.

(f) Notwithstanding the provisions of subdivision (1) of subsection (j) of section 16-244c of the general statutes, as amended by this act, the amount of renewable energy produced from Class I renewable energy sources receiving tariff payments or included in utility rates under this section shall be applied to reduce the electric distribution company's Class I renewable energy source portfolio standard.

(g) No project that receives funding pursuant to this section shall be eligible for funding pursuant to section 59 of this act.

(h) On or before September 1, 2013, the department, in consultation with the Office of Consumer Counsel and the Renewable Energy Investments Board, shall study the operation of solar renewable energy tariffs and shall report, in accordance with the provisions of section 11-4a of the general statutes, its findings and recommendations to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

(i) The department shall suspend the tariff established pursuant to this section upon the earlier of (1) an electric distribution company reaching its aggregate cap pursuant to subsection (c) of this section, or (2) three years from the effective date of the tariff.

Sec. 62. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection in consultation with the Renewable Energy Investment Fund established in section 16-245n of the general statutes, as amended by this act, and the Conservation and Load Management Fund established in section 16-245m of the general statutes, as amended by this act, shall develop coordinated programs to create a self-sustaining market for solar thermal systems for electricity, natural gas and fuel oil customers.

Sec. 63. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection shall provide an additional incentive of up to five per cent of the then-applicable incentive provided pursuant to sections 57 and 62 of this act for the use of major system components manufactured or assembled in Connecticut, and another additional incentive of up to five per cent of the then applicable incentive provided pursuant to sections 57 and 62 of this act for the use of major system components manufactured or assembled in a distressed municipality, as defined in section 32-9p of the general statutes, or a targeted investment community, as defined in section 32-222 of the general statutes.

Sec. 64. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection shall require each electric distribution company to notify its customers on an ongoing basis regarding the availability of time-of-use meters, if applicable.

Sec. 65. (NEW) (Effective October 1, 2011) The Renewable Energy Investments Board created pursuant to section 16-245n of the general statutes, as amended by this act, in consultation with the Department of Energy and Environmental Protection, may establish a program to be known as the "condominium renewable energy grant program". Under such program, the board may provide grants to residential condominium associations and residential condominium owners, within available funds, for purchasing renewable energy sources, including solar energy, geothermal energy and fuel cells or other energy-efficient hydrogen-fueled energy.

Sec. 66. (NEW) (Effective July 1, 2011) (a) On or before January 1, 2012, and annually thereafter, the procurement officer of the Department of Energy and Environmental Protection in consultation with each electric distribution company and in consultation with others at the procurement officer's discretion shall develop a plan for the procurement of electric generation services and related wholesale electricity market products that will enable each electric distribution company to manage a portfolio of contracts to reduce the average cost of standard service while maintaining standard service cost volatility within reasonable levels. Each procurement plan shall provide for the competitive solicitation for load-following electric service and may include a provision for the use of other contracts, including, but not limited to, contracts for generation or other electricity market products and financial contracts, and may provide for the use of varying lengths of contracts. If such plan includes the purchase of full requirements contracts, it shall include an explanation of why such purchases are in the best interests of standard service customers.

(b) An electric distribution company shall recover all reasonable and prudent costs incurred in connection with the development and implementation of the approved procurement plan, including costs of contracts entered into in accordance with the plan.

(c) The procurement officer shall, not less than quarterly, meet with the Commissioner of Energy and Environmental Protection and prepare a written report on the implementation of the plan and recommend any necessary adjustments to the plan to address market conditions or to otherwise reduce the costs of standard service. Such quarterly reports shall be public documents. After considering such report and recommendation, the commissioner may amend the plan by written order.

(d) The costs of procurement for standard service shall be borne solely by the standard service customers.

(e) (1) After department approval of the plan developed pursuant to this section, if an electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of section 16-244c of the general statutes, as amended by this act, seeks to enter into a purchase of energy or other market products for standard service of greater than one year and up to three years in duration, such company or entity shall propose the details of such proposed purchase to the department. The department shall review each proposed purchase in an uncontested proceeding that shall include a public hearing and in which the Consumer Counsel and Attorney General may participate. The department, in consultation with the Office of Consumer Counsel, may retain the services of a third-party entity with expertise in the area of energy procurement to assist in the development or review of the proposed purchase. The department may approve, with or without modification, or reject the proposed purchase as it deems appropriate. Any approval of the proposed purchase shall include a maximum price that the electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of said section 16-244c may agree to pay for the proposed purchase. After such approval, the electric distribution company or such entity selected by the department pursuant to said subdivision (2) of subsection (c) of said section 16-244c shall procure the energy or market products at the lowest price available to it from sellers qualified to transact with the procuring entity, subject to the maximum price set forth in the department's approval.

(2) After department approval of the plan developed pursuant to this section, if an electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of said section 16-244c seeks to enter into a purchase of energy or other market products for standard service of one year or less in duration, such company or entity shall propose the details of such proposed purchase to the department. The department may retain the services of a third-party entity with expertise in the area of energy procurement to assist in the review of the proposed purchase. The department may approve, with or without modification, or reject the proposed purchase as the department deems appropriate. Any approval of the proposed purchase shall include a maximum price that the electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of said section 16-244c may agree to pay for the proposed purchase. After such approval, the electric distribution company or such entity selected by the department pursuant to said subdivision (2) of subsection (c) of said section 16-244c shall procure the energy or market products at the lowest price available to it from sellers qualified to transact with the procuring entity, subject to the maximum price set forth in the department's approval.

(3) Any contract for standard service of greater than three years in duration, or any contract for standard service that would directly result in the construction of a generating facility is subject to the review and approval of the department. The electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of said section 16-244c shall execute such contract subject to approval of the department and shall present such contract to the department for approval. The department shall review each contract in an uncontested proceeding that shall include a public hearing and in which the Consumer Counsel and Attorney General may participate. The department, in consultation with the Office of Consumer Counsel, may retain the services of a third-party entity with expertise in the area of energy procurement to assist in the development or review of the contract. The department shall issue a decision on the contract within ninety days of submission by the electric distribution company or such entity selected by the department pursuant to subdivision (2) of subsection (c) of said section 16-244c. The Department of Energy and Environmental Protection shall report annually in accordance with the provisions of section 11-4a to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding implementation of the plan and recommendations for modification.

Sec. 67. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection Bureau of Public Utility shall initiate a docket to consider the buy down of an electric distribution company's current standard service contract to reduce ratepayer bills and conduct a cost benefit analysis of such a buy down. If the department, as a result of such docket, determines such a buy down is in the best interest of ratepayers, the department shall proceed with such buy down.

Sec. 68. Subsection (b) of section 16-32f of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(b) Not later than October 1, 2005, and annually thereafter, a gas company, as defined in section 16-1, as amended by this act, shall submit to the Department of [Public Utility Control] Energy and Environmental Protection a gas conservation plan, in accordance with the provisions of this section, to implement cost-effective energy conservation programs and market transformation initiatives. All supply and conservation and load management options shall be evaluated and selected within an integrated supply and demand planning framework. Such plan shall be funded during each state fiscal year by the revenue from the tax imposed by section 12-264 on the gross receipts of sales of all public services companies that is in excess of the revenue estimate for said tax that is approved by the General Assembly in the appropriations act for such fiscal year, provided (1) the amount of such excess revenue that shall be allocated to fund such plan in any state fiscal year shall not exceed ten million dollars, and (2) in the fiscal years commencing July 1, 2011, July 1, 2012, and July 1, 2013, fifty per cent of such excess revenue shall be allocated to the natural gas projects within the energy savings infrastructure pilot program pursuant to subdivision (2) of section 90 of this act. Before the accounts for the General Fund have been closed for each fiscal year, such excess revenue shall be deposited by the Comptroller in an account held by the Energy Conservation Management Board, established pursuant to section 16-245m, as amended by this act. Services provided under the plan shall be available to all gas company customers. Each gas company shall apply to the Energy Conservation Management Board for reimbursement for expenditures pursuant to the plan. The department shall, in an uncontested proceeding during which the department may hold a public hearing, approve, modify or reject the plan.

Sec. 69. Subsection (e) of section 16-243v of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(e) Beginning February 1, 2010, a certified Connecticut electric efficiency partner may only receive funding if selected in a request for proposal developed, issued and evaluated by the department. In evaluating a proposal, the department shall take into consideration the potential to reduce customers' electric demand including peak electric demand, and associated electric charges tied to electric demand and peak electric demand growth, including, but not limited to, federally mandated congestion charges and other electric costs, and shall utilize a cost benefit test established pursuant to subsection (c) of this section to rank responses for selection. The department shall determine the portion of the total cost of each project that shall be paid by the customer participating in this program and the portion of the total cost of each project that shall be paid by all electric ratepayers and collected pursuant to the provisions of this subsection. In making such determination, the department shall (1) ensure that all ratepayer investments maintain a minimum [two-to-one] one-and-one-half-to-one payback ratio, and (2) specify that participating Connecticut electric efficiency partners shall maintain the technology for a period sufficient to achieve such investment payback ratio. The annual ratepayer contribution shall not exceed sixty million dollars. Not less than seventy-five per cent of such annual ratepayer investment shall be used for the technologies themselves and for the fiscal years commencing July 1, 2011, July 1, 2012, and July 1, 2013, five million dollars of such annual ratepayer investment shall be used for combined heat and power projects and five million dollars of such annual ratepayer investment shall be used for fuel oil burner, boiler and furnace replacement projects, under the energy savings infrastructure pilot program established pursuant to section 90 of this act. No Connecticut electric efficiency partner shall receive funding pursuant to this subsection if such partner has received or is receiving funding from the Energy Conservation and Load Management Funds for such technology. The department may conduct additional requests for proposals from time to time as it deems appropriate. The department shall specify the manner in which a Connecticut electric efficiency partner shall address measures of effectiveness and shall include performance milestones.

Sec. 70. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection shall require the Energy Conservation Management Board, the Renewable Energy Investments Board and electric distribution companies, as defined in section 16-1 of the general statutes, as amended by this act, to establish a program to provide financial assistance for energy conservation and load management projects to electric distribution company customers in underserved communities. The aggregate financial assistance such program shall provide shall be in an amount equal to at least three per cent of the moneys collected for the Energy Conservation and Load Management and at least three per cent of the moneys collected for the Renewable Energy Investment Funds pursuant to sections 16-245m and 16-245n of the general statutes, as amended by this act. Such funds shall be provided for programs directly benefiting residential or small business electric customers in underserved communities. The moneys for the program shall be derived (1) initially from, if available, the federal American Recovery and Reinvestment Act of 2009, and (2) for conservation projects from the Energy Conservation and Load Management and renewable energy projects from Renewable Energy Investment Funds. Such program shall include a job training component for existing or potential minority business enterprises, as defined in section 4a-60g of the general statutes. For the purposes of this section, "underserved communities" means municipalities meeting the criteria set forth in subsection (a) of section 32-70 of the general statutes. The department shall report, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy on or before February 1, 2012, and annually thereafter, regarding the program established pursuant to this section.

Sec. 71. (NEW) (Effective July 1, 2011) On or before September 1, 2011, the Department of Energy and Environmental Protection shall initiate a request for proposals to consider bilateral purchasing contracts for electricity from existing or new generators, provided such contract shall be for a term of not less than five years and not more than fifteen years, shall reduce electricity rates by pricing such electricity on a cost-of-service basis, power purchase agreement or other mechanism the department determines to be in the best interest of Connecticut's customers and shall directly, or in combination with other initiatives, provide electricity at lower rates for Connecticut consumers.

Sec. 72. (NEW) (Effective July 1, 2011) On or before September 1, 2011, the Department of Energy and Environmental Protection shall review any proposed commercial transmission line project (1) in which a Connecticut electric distribution company may have a financial interest, or (2) that may be constructed in whole or in part in this state to determine whether to obtain electricity from such transmission lines at a rate that will lower electricity rates for Connecticut consumers.

Sec. 73. (Effective from passage) On or before August 1, 2011, the Department of Energy and Environmental Protection shall initiate a study to identify the impact on Connecticut ratepayers and the New England and state wholesale electric power market of the operation of the regional independent system operator, as defined in section 16-1 of the general statutes, as amended by this act, and of Market Rule 1 as promulgated by said regional independent system operator. Such study shall include, but not be limited to, (1) a review of the accountability of said independent system operator to Connecticut ratepayers and energy policymakers, (2) consideration of strategies and mechanisms that may mitigate any adverse impacts Market Rule 1 may have on wholesale generation prices in Connecticut and New England and may reduce Connecticut's reliance on the wholesale power market, including, but not limited to, long-term contracts, (3) consideration of the costs and benefits associated with participating in said independent system operator and any potential benefits of joining another independent system operator or operating outside of the existing independent operator systems, (4) an examination of the framework within the Federal Energy Regulatory Commission that has contributed to the state's high rates, and (5) consideration of methods to foster greater transparency in any such system. On or before January 1, 2012, the department shall report, in accordance with the provisions of section 11-4a of the general statutes, its findings to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

Sec. 74. Subparagraph (B) of subdivision (6) of subsection (c) of section 7-148 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(B) (i) Lay out, construct, reconstruct, repair, maintain, operate, alter, extend and discontinue sewer and drainage systems and sewage disposal plants;

(ii) Enter into or upon any land for the purpose of correcting the flow of surface water through watercourses which prevent, or may tend to prevent, the free discharge of municipal highway surface water through said courses;

(iii) Regulate the laying, location and maintenance of gas pipes, water pipes, drains, sewers, poles, wires, conduits and other structures in the streets and public places of the municipality;

(iv) Prohibit and regulate the discharge of drains from roofs of buildings over or upon the sidewalks, streets or other public places of the municipality or into sanitary sewers;

(v) Enter into performance-based energy contracts;

Sec. 75. (NEW) (Effective July 1, 2011) On or before October 1, 2011, the Department of Energy and Environmental Protection shall establish a natural gas conversion program to allow a gas company to finance the conversion to gas heat by potential residential customers who heat their homes with electricity. The department shall adopt regulations in accordance with the provisions of chapter 54 of the general statutes to establish procedures and terms for such program and shall, on or before January 1, 2012, and annually thereafter, report in accordance with the provisions of section 11-4a of the general statutes to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment regarding the progress of said program.

Sec. 76. (NEW) (Effective from passage) The Department of Energy and Environmental Protection shall prepare a study on the potential costs savings and benefits to ratepayers, including, but not limited to, emissions reductions, repowering some or all of the state's coal-fired and oil-fired generation facilities built before 1990. On or before February 1, 2012, the Department of Energy and Environmental Protection shall submit the study, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

Sec. 77. (NEW) (Effective from passage) Each state agency shall develop a plan to reduce its energy use by at least ten per cent and shall submit such plan to the Office of Policy and Management on or before October 1, 2011. On or before October 1, 2012, and annually thereafter, each state agency shall report, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the plan and its implementation.

Sec. 78. Section 16-245aa of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) There is established an account to be known as the "municipal renewable energy and efficient energy grant account", which shall be a separate, nonlapsing account within the Renewable Energy Investment Fund, established pursuant to section 16-245n. The account shall contain any moneys required or permitted by law to be deposited in the account and any funds received from any public or private contributions, gifts, grants, donations, bequests or devises to the fund. [Connecticut Innovations, Incorporated,] The Department of Energy and Environmental Protection may make grants-in-aid from the fund in accordance with the provisions of subsection (b) of this section.

(b) [Connecticut Innovations, Incorporated] The Department of Energy and Environmental Protection, in consultation with the [Department of Public Utility Control, the] Department of Education and the Department of Emergency Management and Homeland Security, shall establish a municipal renewable energy and efficient energy generation grant program. [Connecticut Innovations, Incorporated,] The Department of Energy and Environmental Protection shall make grants under said program to municipalities for the purchase of (1) renewable energy sources, including solar energy, geothermal energy and fuel cells or other energy-efficient hydrogen-fueled energy, or (2) energy-efficient generation sources, including units providing combined heat-and-power operations with greater than sixty-five per cent efficiency or such higher efficiency level as [Connecticut Innovations, Incorporated,] the Department of Energy and Environmental Protection may prescribe, for municipal buildings. [Connecticut Innovations, Incorporated,] The Department of Energy and Environmental Protection shall give priority to applications for grants for disaster relief centers and high schools. Each grant shall be in an amount that makes the cost of purchasing and operating the renewable energy or energy-efficient generation source competitive with the municipality's current electricity expenses.

(c) On or before October 1, 2007, [Connecticut Innovations, Incorporated,] the Department of Energy and Environmental Protection shall develop an application for grants-in-aid under this section for the purpose of purchasing and operating renewable energy or energy-efficient generation sources and may receive applications from municipalities for such grants-in-aid on and after said date. Applications shall include, but not be limited to, a complete description of the proposed renewable energy or energy-efficient generation source.

(d) Commencing with the fiscal year ending June 30, 2008, and for each of the five consecutive fiscal years thereafter, until the fiscal year ending June 30, 2012, not less than ten million dollars shall be available from the municipal renewable energy and efficient energy generation grant account for grants-in-aid to municipalities for the purpose of purchasing and operating renewable energy or energy-efficient generation sources. Any balance of such amount not used for such grants-in-aid during a fiscal year shall be carried forward for the fiscal year next succeeding for such grants-in-aid.

(e) On or before January 1, 2009, and annually thereafter, [Connecticut Innovations, Incorporated,] the Department of Energy and Environmental Protection shall report on the effectiveness of said program to the joint standing committee of the General Assembly having cognizance of matters relating to energy.

Sec. 79. Section 16a-38p of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

(a) For the purposes described in subsection (b) of this section, the State Bond Commission shall have the power, from time to time, to authorize the issuance of bonds of the state in one or more series and in principal amounts not exceeding in the aggregate ten million dollars.

(b) The proceeds of the sale of said bonds, to the extent of the amount stated in subsection (a) of this section, shall be used by [Connecticut Innovations, Incorporated,] the Department of Energy and Environmental Protection for the purpose of funding the net project costs, or the balance of any projects after applying any public or private financial incentives available, for any renewable energy or combined heat and power projects in state buildings. The funds shall be made available through the Renewable Energy Investment Fund, established pursuant to section 16-245n. Eligible state buildings shall be Leadership in Energy and Environmental Design (LEED) certified or in the process of becoming LEED certified or in the process of becoming LEED silver rating certified or receive a two-globe rating in the green Globes USA design program or in the process of receiving a two-globe rating in the Green Globes USA design program.

(c) All provisions of section 3-20, or the exercise of any right or power granted thereby, which are not inconsistent with the provisions of this section are hereby adopted and shall apply to all bonds authorized by the State Bond Commission pursuant to this section, and temporary notes in anticipation of the money to be derived from the sale of any such bonds so authorized may be issued in accordance with said section 3-20 and from time to time renewed. Such bonds shall mature at such time or times not exceeding twenty years from their respective dates as may be provided in or pursuant to the resolution or resolutions of the State Bond Commission authorizing such bonds. None of said bonds shall be authorized except upon a finding by the State Bond Commission that there has been filed with it a request for such authorization which is signed by or on behalf of the [Secretary of the Office of Policy and Management] Commissioner of Energy and Environmental Protection and states such terms and conditions as said commission, in its discretion, may require. Said bonds issued pursuant to this section shall be general obligations of the state and the full faith and credit of the state of Connecticut are pledged for the payment of the principal of and interest on said bonds as the same become due, and accordingly and as part of the contract of the state with the holders of said bonds, appropriation of all amounts necessary for punctual payment of such principal and interest is hereby made, and the State Treasurer shall pay such principal and interest as the same become due.

Sec. 80. Section 32-39 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

The purposes of the corporation shall be to stimulate and encourage the research and development of new technologies, businesses and products, to encourage the creation and transfer of new technologies, to assist existing businesses in adopting current and innovative technological processes, to stimulate and provide services to industry that will advance the adoption and utilization of technology, to achieve improvements in the quality of products and services, to stimulate and encourage the development and operation of new and existing science parks and incubator facilities, and to promote science, engineering, mathematics and other disciplines that are essential to the development and application of technology within Connecticut by the infusion of financial aid for research, invention and innovation in situations in which such financial aid would not otherwise be reasonably available from commercial or other sources, and for these purposes the corporation shall have the following powers:

(1) To have perpetual succession as a body corporate and to adopt bylaws, policies and procedures for the regulation of its affairs and conduct of its businesses as provided in section 32-36;

(2) To enter into venture agreements with persons, upon such terms and on such conditions as are consistent with the purposes of this chapter, for the advancement of financial aid to such persons for the research, development and application of specific technologies, products, procedures, services and techniques, to be developed and produced in this state, and to condition such agreements upon contractual assurances that the benefits of increasing or maintaining employment and tax revenues shall remain in this state and shall accrue to it;

(3) To solicit, receive and accept aid, grants or contributions from any source of money, property or labor or other things of value, to be held, used and applied to carry out the purposes of this chapter, subject to the conditions upon which such grants and contributions may be made, including but not limited to, gifts or grants from any department or agency of the United States or the state;

(4) To invest in, acquire, lease, purchase, own, manage, hold and dispose of real property and lease, convey or deal in or enter into agreements with respect to such property on any terms necessary or incidental to the carrying out of these purposes; provided, however, that all such acquisitions of real property for the corporation's own use with amounts appropriated by the state to the corporation or with the proceeds of bonds supported by the full faith and credit of the state shall be subject to the approval of the Secretary of the Office of Policy and Management and the provisions of section 4b-23;

(5) To borrow money or to guarantee a return to the investors in or lenders to any capital initiative, to the extent permitted under this chapter;

(6) To hold patents, copyrights, trademarks, marketing rights, licenses, or any other evidences of protection or exclusivity as to any products as defined herein, issued under the laws of the United States or any state or any nation;

(7) To employ such assistants, agents and other employees as may be necessary or desirable, which employees shall be exempt from the classified service and shall not be employees, as defined in subsection (b) of section 5-270; establish all necessary or appropriate personnel practices and policies, including those relating to hiring, promotion, compensation, retirement and collective bargaining, which need not be in accordance with chapter 68, and the corporation shall not be an employer as defined in subsection (a) of section 5-270; and engage consultants, attorneys and appraisers as may be necessary or desirable to carry out its purposes in accordance with this chapter;

(8) To make and enter into all contracts and agreements necessary or incidental to the performance of its duties and the execution of its powers under this chapter;

(9) To sue and be sued, plead and be impleaded, adopt a seal and alter the same at pleasure;

(10) With the approval of the State Treasurer, to invest any funds not needed for immediate use or disbursement, including any funds held in reserve, in obligations issued or guaranteed by the United States of America or the state of Connecticut and in other obligations which are legal investments for retirement funds in this state;

(11) To procure insurance against any loss in connection with its property and other assets in such amounts and from such insurers as it deems desirable;

(12) To the extent permitted under its contract with other persons, to consent to any termination, modification, forgiveness or other change of any term of any contractual right, payment, royalty, contract or agreement of any kind to which the corporation is a party;

(13) To do anything necessary and convenient to render the bonds to be issued under section 32-41 more marketable;

(14) To acquire, lease, purchase, own, manage, hold and dispose of personal property, and lease, convey or deal in or enter into agreements with respect to such property on any terms necessary or incidental to the carrying out of these purposes;

(15) In connection with any application for assistance under this chapter, or commitments therefor, to make and collect such fees as the corporation shall determine to be reasonable;

(16) To enter into venture agreements with persons, upon such terms and conditions as are consistent with the purposes of this chapter to provide financial aid to such persons for the marketing of new and innovative services based on the use of a specific technology, product, device, technique, service or process;

(17) To enter into limited partnerships or other contractual arrangements with private and public sector entities as the corporation deems necessary to provide financial aid which shall be used to make investments of seed venture capital in companies based in or relocating to the state in a manner which shall foster additional capital investment, the establishment of new businesses, the creation of new jobs and additional commercially-oriented research and development activity. The repayment of such financial aid shall be structured in such manner as the corporation deems will best encourage private sector participation in such limited partnerships or other arrangements. The board of directors, executive director, officers and staff of the corporation may serve as members of any advisory or other board which may be established to carry out the purposes of this subdivision;

(18) To account for and audit funds of the corporation and funds of any recipients of financial aid from the corporation;

(19) To advise the Governor, the General Assembly, the Commissioner of Economic and Community Development and the Commissioner of Higher Education on matters relating to science, engineering and technology which may have an impact on state policies, programs, employers and residents, and on job creation and retention;

(20) To promote technology-based development in the state;

(21) To encourage and promote the establishment of and, within available resources, to provide financial aid to advanced technology centers;

(22) To maintain an inventory of data and information concerning state and federal programs which are related to the purposes of this chapter and to serve as a clearinghouse and referral service for such data and information;

(23) To conduct and encourage research and studies relating to technological development;

(24) To provide technical or other assistance and, within available resources, to provide financial aid to the Connecticut Academy of Science and Engineering, Incorporated, in order to further the purposes of this chapter;

(25) To recommend a science and technology agenda for the state that will promote the formation of public and private partnerships for the purpose of stimulating research, new business formation and growth and job creation;

(26) To encourage and provide technical assistance and, within available resources, to provide financial aid to existing manufacturers and other businesses in the process of adopting innovative technology and new state-of-the-art processes and techniques;

(27) To recommend state goals for technological development and to establish policies and strategies for developing and assisting technology-based companies and for attracting such companies to the state;

(28) To promote and encourage and, within available resources, to provide financial aid for the establishment, maintenance and operation of incubator facilities;

(29) To promote and encourage the coordination of public and private resources and activities within the state in order to assist technology-based entrepreneurs and business enterprises;

(30) To provide services to industry that will stimulate and advance the adoption and utilization of technology and achieve improvements in the quality of products and services;

(31) To promote science, engineering, mathematics and other disciplines that are essential to the development and application of technology;

(32) To coordinate its efforts with existing business outreach centers, as described in section 32-9qq;

(33) To do all acts and things necessary and convenient to carry out the purposes of this chapter;

(34) To accept from the department: (A) Financial assistance, (B) revenues or the right to receive revenues with respect to any program under the supervision of the department, and (C) loan assets or equity interests in connection with any program under the supervision of the department; to make advances to and reimburse the department for any expenses incurred or to be incurred by it in the delivery of such assistance, revenues, rights, assets, or interests; to enter into agreements for the delivery of services by the corporation, in consultation with the department, the Connecticut Housing Finance Authority and the Connecticut Development Authority, to third parties which agreements may include provisions for payment by the department to the corporation for the delivery of such services; and to enter into agreements with the department or with the Connecticut Development Authority or Connecticut Housing Finance Authority for the sharing of assistants, agents and other consultants, professionals and employees, and facilities and other real and personal property used in the conduct of the corporation's affairs;

(35) To transfer to the department: (A) Financial assistance, (B) revenues or the right to receive revenues with respect to any program under the supervision of the corporation, and (C) loan assets or equity interests in connection with any program under the supervision of the corporation, provided the transfer of such financial assistance, revenues, rights, assets or interests is determined by the corporation to be practicable, within the constraints and not inconsistent with the fiduciary obligations of the corporation imposed upon or established upon the corporation by any provision of the general statutes, the corporation's bond resolutions or any other agreement or contract of the corporation and to have no adverse effect on the tax-exempt status of any bonds of the state;

(36) With respect to any capital initiative, to create, with one or more persons, one or more affiliates and to provide, directly or indirectly, for the contribution of capital to any such affiliate, each such affiliate being expressly authorized to exercise on such affiliate's own behalf all powers which the corporation may exercise under this section, in addition to such other powers provided to it by law;

(37) To provide financial aid to enable biotechnology and other technology companies to lease, acquire, construct, maintain, repair, replace or otherwise obtain and maintain production, testing, research, development, manufacturing, laboratory and related and other facilities, improvements and equipment;

(38) To provide financial aid to persons developing smart buildings, as defined in section 32-23d, incubator facilities or other information technology intensive office and laboratory space;

[(39) To administer the Renewable Energy Investment Fund established pursuant to section 16-245n;]

[(40)] (39) To provide financial aid to persons developing or constructing the basic buildings, facilities or installations needed for the functioning of the media and motion picture industry in this state;

[(41)] (40) To coordinate the development and implementation of strategies regarding technology-based talent and innovation among state and quasi-public agencies, including the creation and administration of the Connecticut Small Business Innovation Research Office to act as a centralized clearinghouse and provide technical assistance to applicants in developing small business innovation research programs in conformity with the federal program established pursuant to the Small Business Research and Development Enhancement Act of 1992, P.L. 102-564, as amended, and other proposals.

Sec. 81. Section 16-245z of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

Not later than October 1, 2005, the Department of [Public Utility Control] Energy and Environmental Protection and the Energy Conservation Management Board, established in section 16-245m, as amended by this act, shall establish links on their Internet web sites to the Energy Star program or successor program that promotes energy efficiency and each electric distribution company shall establish a link under its conservation programs on its Internet web site to the Energy Star program or such successor program.

Sec. 82. (NEW) (Effective July 1, 2011) (a) On or before January 1, 2012, the Department of Energy and Environmental Protection Bureau of Energy shall review available financing programs to determine what exists on the state and national levels and recommend how best to establish a state program of financing renewable energy and conservation. The department shall consider various sources of financing, including, but not limited to, mortgages, bonds and the establishment of loan loss reserves to leverage private capital, provided such sources of financing shall not include any ratepayer contribution.

(b) The department shall report, in accordance with the provisions of section 11-4a of the general statutes to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding its review conducted pursuant to subsection (a) of this section.

Sec. 83. (NEW) (Effective July 1, 2011) (a) The Department of Energy and Environmental Protection shall establish a pilot program to support through loans, grants or power purchase agreements sustainable practices and economic prosperity of Connecticut farms by using agricultural waste with on-site anaerobic digestion facilities to generate electricity and heat. As part of the pilot program, the department may approve no more than five projects, each of which shall have a maximum size of five hundred kilowatts. On or before January 1, 2012, and annually thereafter, the department shall report, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the program established pursuant to this subsection.

(b) The Department of Energy and Environmental Protection shall establish a virtual net metering pilot program. Such program shall be open to thirty electric distribution company customers, divided between the companies as follows: Twenty projects to the company with a greater service area and ten projects to the company with a smaller service area. An electric distribution company customer with more than one account with such company and with meters that are within one mile of each other shall be eligible for participation in the program established pursuant to this subsection. On or before January 1, 2012, and annually thereafter, the department shall report, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the program established pursuant to this subsection.

Sec. 84. Section 17b-801 of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

[(a) The Commissioner of Social Services shall administer a state-appropriated fuel assistance program to provide, within available appropriations, fuel assistance to elderly and disabled persons whose household gross income is above the income eligibility guidelines for the Connecticut energy assistance program but does not exceed two hundred per cent of federal poverty guidelines. The income eligibility guidelines for the state-appropriated fuel assistance program shall be determined, annually, by the Commissioner of Social Services, in conjunction with the Secretary of the Office of Policy and Management. The commissioner may adopt regulations, in accordance with the provisions of chapter 54, to implement the provisions of this subsection.

(b) The commissioner shall administer a state-appropriated weatherization assistance program to provide, within available appropriations, weatherization assistance in accordance with the provisions of the state plan implementing the weatherization assistance block grant program authorized by the federal Low-Income Home Energy Assistance Act of 1981, and programs of fuel assistance and weatherization assistance with funds authorized by the federal Low-Income Home Energy Assistance Act of 1981 and by the U.S. Department of Energy in accordance with 10 CFR Part 440 promulgated under Title IV of the Energy Conservation and Production Act, as amended, and oil settlement funds in accordance with subsections (b) and (c) of section 4-28. The commissioner shall adopt regulations in accordance with the provisions of chapter 54, (1) establishing priorities for determining which households shall receive such weatherization assistance, (2) requiring that such weatherization assistance for energy conservation measures other than the retrofitting of heating systems be provided only for any dwelling unit for which an energy audit has been conducted in accordance with the provisions of sections 16a-45a to 16a-46c, inclusive, (3) requiring that the only criterion for determining which energy conservation measures shall be implemented pursuant to this subsection in any such dwelling unit shall be the simple payback calculated for each energy conservation measure recommended in the energy audit conducted for such unit, (4) establishing the maximum allowable payback period for such energy conservation measures and (5) establishing conditions for the waiver of the provisions of subdivisions (1) to (4), inclusive, of this subsection in the event of emergencies. The programs provided for under this subsection shall include a program of fuel and weatherization assistance for emergency shelters for homeless individuals and victims of domestic violence. The commissioner may adopt regulations, in accordance with the provisions of chapter 54, to implement and administer the program of fuel and weatherization assistance for emergency shelters.]

[(c)] The Commissioner of Social Services shall administer, within available appropriations, a crime prevention and safety program for residences occupied by elderly and disabled persons who are eligible for the weatherization assistance block grant program authorized by the federal Low-Income Home Energy Assistance Act of 1981 or the state-appropriated weatherization assistance program. The program shall be operated through the community action agencies and the municipal agency responsible for said low income weatherization program. The program may provide for the purchase and installation, where necessary, of devices which allow a person inside a dwelling unit to view the area outside the door, or doors with windows, locks on windows and doors, and smoke detectors. The installation of devices under this program shall be done at the time weatherization is done.

Sec. 85. (NEW) (Effective July 1, 2011) (a) The Commissioner of Energy and Environmental Protection shall administer a state-appropriated fuel assistance program to provide, within available appropriations, fuel assistance to elderly and disabled persons whose household gross income is above the income eligibility guidelines for the Connecticut energy assistance program but does not exceed two hundred per cent of federal poverty guidelines. The income eligibility guidelines for the state-appropriated fuel assistance program shall be determined, annually, by the Commissioner of Energy and Environmental Protection, in conjunction with the Secretary of the Office of Policy and Management. The commissioner may adopt regulations, in accordance with the provisions of chapter 54 of the general statutes, to implement the provisions of this subsection.

(b) The commissioner shall administer a state-appropriated weatherization assistance program to provide, within available appropriations, weatherization assistance in accordance with the provisions of the state plan implementing the weatherization assistance block grant program authorized by the federal Low-Income Home Energy Assistance Act of 1981, and programs of fuel assistance and weatherization assistance with funds authorized by the federal Low-Income Home Energy Assistance Act of 1981 and by the United States Department of Energy in accordance with 10 CFR Part 440 promulgated under Title IV of the Energy Conservation and Production Act, as amended, and oil settlement funds in accordance with subsections (b) and (c) of section 4-28 of the general statutes. The commissioner shall adopt regulations in accordance with the provisions of chapter 54 of the general statutes, (1) establishing priorities for determining which households shall receive such weatherization assistance, (2) requiring that such weatherization assistance for energy conservation measures other than the retrofitting of heating systems be provided only for any dwelling unit for which an energy audit has been conducted in accordance with the provisions of sections 16a-45a to 16a-46c, inclusive, of the general statutes, (3) requiring that the only criterion for determining which energy conservation measures shall be implemented pursuant to this subsection in any such dwelling unit shall be the simple payback calculated for each energy conservation measure recommended in the energy audit conducted for such unit, (4) establishing the maximum allowable payback period for such energy conservation measures, and (5) establishing conditions for the waiver of the provisions of subdivisions (1) to (4), inclusive, of this subsection in the event of emergencies. The programs provided for under this subsection shall include a program of fuel and weatherization assistance for emergency shelters for homeless individuals and victims of domestic violence. The commissioner may adopt regulations, in accordance with the provisions of chapter 54 of the general statutes, to implement and administer the program of fuel and weatherization assistance for emergency shelters.

Sec. 86. (NEW) (Effective July 1, 2011) There is established within the Department of Energy and Environmental Protection an Office of Energy Efficient Businesses. The office shall provide in-state businesses (1) a single point of contact for any state business interested in energy efficiency, renewable energy or conservation projects, (2) information on loans and grants for energy efficiency, renewable energy projects and conservation, (3) audit and assessment services, including, but not limited to, outreach to businesses by qualified entities, and (4) any other service deemed relevant by said office.

Sec. 87. (NEW) (Effective July 1, 2011) On and after July 1, 2011, an electric distribution company, as defined in section 16-1 of the general statutes, as amended by this act, shall notify the Department of Energy and Environmental Protection and the joint standing committee of the General Assembly having cognizance of matters relating to energy before such company expresses concerns to the independent system operator, as defined in said section 16-1, identifying any reliability issues concerning the system.

Sec. 88. (Effective July 1, 2011) On or before January 1, 2012, the Department of Energy and Environmental Protection shall conduct a cost-effectiveness analysis to compare the use of Class III electricity credits with long-term contracts for the development of combined heat and power or efficiency resources. The department shall report the results of such analysis in accordance with the provisions of section 11-4a of the general statutes to the joint standing committee of the General Assembly having cognizance of matters relating to energy on or before February 1, 2012.

Sec. 89. (NEW) (Effective July 1, 2011) (a) On or before January 1, 2012, the Department of Energy and Environmental Protection shall initiate an uncontested proceeding to establish a feed-in tariff that shall decline over time to include, but not be limited to, wind, fuel cells, biomass, geothermal and energy efficiency projects. As a result of such proceeding, the department shall establish the parameters of such program, which shall include, but not be limited to, a subject to the cap established pursuant to section 56 of this act on tariffs established pursuant to this section and a requirement that no ratepayer money fund such program.

(b) On or before January 1, 2012, and annually thereafter, the department shall report, in accordance with the provisions of section 11-4a of the general statutes, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the feed-in tariff established pursuant to this section.

Sec. 90. (NEW) (Effective July 1, 2011) (a) As used in this section:

(1) "Eligible entity" means (A) any residential, commercial, institutional or industrial customer of an electric distribution company or natural gas company, as defined in section 16-1 of the general statutes, as amended by this act, who employs or installs an eligible in-state energy savings technology, (B) an energy service company certified as a Connecticut electric efficiency partner by the Department of Energy and Environmental Protection, or (C) an installer certified by the Renewable Energy Investments Fund; and

(2) "Energy savings infrastructure" means tangible equipment, installation, labor, cost of engineering, permits, application fees and other reasonable costs incurred by eligible entities for operating eligible in-state energy savings technologies designed to reduce electricity consumption, natural gas consumption, heating oil consumption or promote combined heat and power systems.

(b) The Department of Energy and Environmental Protection shall establish an energy savings infrastructure pilot program consisting of financial incentives for the installation of combined heat and power systems, energy efficient heating oil burners, boilers and furnaces and natural gas boilers and furnaces by eligible entities. On or before June 30, 2014, the department shall evaluate the efficacy of the program established pursuant to this section.

(c) (1) On or before October 1, 2011, the department shall begin accepting applications for financial incentives for combined heat and power systems of not more than one megawatt of power. To qualify for such financial incentives, such combined heat and power system shall reduce energy costs at an amount equal to or greater than the amount of the installation cost of the system within ten years of the installation. The department shall review the current market conditions for such systems, including any existing federal or state financial incentives, and determine the appropriate financial incentives under this program necessary to encourage installation of such systems. These financial incentives may include providing private financial institutions with loan loss protection or grants to lower borrowing costs. Financial incentives pursuant to this subdivision shall not exceed two hundred dollars per kilowatt. A project accepted for such incentives shall qualify for a waiver of (A) the backup power rate under section 16-243o of the general statutes, and (B) the requirement to provide baseload electricity under section 16-243i of the general statutes. Any purchase of natural gas for any combined heat and power system installed pursuant to this subdivision shall not include a distribution charge pursuant to section 16-243l of the general statutes.

(2) On or before December 31, 2011, the department shall begin accepting applications for financial incentives for the installation of more efficient fuel oil and natural gas boilers and furnaces that replace existing boilers or furnaces that are not less than seven years old with an efficiency rating of not more than seventy-five per cent. A qualifying fuel oil furnace shall have an efficiency rating of not less than eighty-six per cent. A qualifying fuel oil boiler shall have an efficiency rating of not less than eighty-six per cent with thermal purge or temperature reset controls. A qualifying natural gas boiler shall have an annual fuel utilization efficiency rating of not less than ninety per cent and a qualifying natural gas furnace shall have an annual fuel utilization efficiency rating of not less than ninety-five per cent. The department shall review the current market conditions for such systems and equipment upgrades, including, but not limited to, any existing federal or state financial incentives, and establish the appropriate financial incentives under this program necessary to encourage such upgrades. Financial incentives shall provide private financial institutions with loan loss protection or grants to lower borrowing costs and, if the department deems it necessary, grants to the lending financial institution to lower borrowing costs and allow for a ten-year loan. Such financial incentive package shall ensure that the annual loan payment by the applicant shall be at not more than the projected annual energy savings less one hundred dollars. Any loan provided as a financial incentive pursuant to this subdivision shall include the cost of any related incentives, as determined by the department. The department shall arrange with an electric distribution or gas company to provide for payment of any loan made as financial assistance under this subdivision through the loan recipient's monthly electric or gas bill, as applicable.

(d) Eligible entities seeking a loan under the loan program established in this section shall (1) contract with Connecticut-based licensed contractors, installers or tradesmen for the installation of an eligible in-state energy savings technology; (2) provide evidence of the cost of purchase and installation of the eligible in-state energy savings technology; and (3) periodically provide evidence of the operation and functionality of the eligible in-state energy savings technology to ensure that such technology is operating as intended during the term of the loan.

(e) The department shall develop a prescriptive one-page loan application. Such application shall include, but not be limited to: (1) Detailed information, specifications and documentation of the eligible in-state energy technology's installed costs and projected energy savings, and (2) for requests for loans in excess of one hundred thousand dollars, certification by a licensed professional engineer, licensed contractor, installer or tradesman with a state license held in good standing.

(f) On or before October 1, 2011, the department shall establish a plan that includes procedures and parameters for its energy savings infrastructure pilot program established pursuant to this section.

(g) On or before October 1, 2014, the department shall, in accordance with the provisions of section 11-4a of the general statutes, report to the joint standing committee of the General Assembly having cognizance of matters relating to energy with regard to the projects assisted by the energy savings infrastructure pilot program established pursuant to this section, the amount of public funding, the energy savings from the technologies installed and any recommendations for changes to the program, including, but not limited to, incentives that encourage consumers to install more efficient fuel oil and natural gas boilers and furnaces prior to failure or gross inefficiency of their current heating system.

Sec. 91. Section 16-243i of the general statutes is repealed and the following is substituted in lieu thereof (Effective July 1, 2011):

[(a)] The Department of [Public Utility Control] Energy and Environmental Protection shall, not later than January 1, [2006] 2012, establish a program to [grant awards to retail end use customers of electric distribution companies to fund the capital costs of obtaining projects of customer-side distributed resources, as defined in section 16-1. Any project shall receive a one-time, nonrecurring award in an amount of not less than two hundred dollars and not more than five hundred dollars per kilowatt of capacity for such customer-side distributed resources, recoverable from federally mandated congestion charges, as defined in section 16-1. No such award may be made unless the projected reduction in federally mandated congestion charges attributed to the project for such distributed resources is greater than the amount of the award. The amount of an award shall depend on the impact that the customer-side distributed resources project has on reducing federally mandated congestion charges, as defined in section 16-1. Not later than October 1, 2005, the department shall conduct a contested case proceeding, in accordance with chapter 54, to establish additional standards for the amount of such awards and additional criteria and the process for making such awards.

(b) The Department of Public Utility Control shall, not later than January 1, 2006, establish a program to grant to an electric distribution company a one-time, nonrecurring award to educate, assist and promote investments in customer-side distributed resources developed in such company's service territory, which resources the department determines will reduce federally mandated congestion charges, in accordance with the following: (1) On or before January 1, 2008, two hundred dollars per kilowatt of such resources, (2) on or before January 1, 2009, one hundred fifty dollars per kilowatt of such resources, (3) on or before January 1, 2010, one hundred dollars per kilowatt of such resources, and (4) fifty dollars per kilowatt of such resources thereafter. Payment of the award shall be made at the time each such resource becomes operational. The cost of the award shall be recoverable from federally mandated congestion charges. Revenues from such awards shall not be included in calculating the electric distribution company's earnings for the purpose of determining whether its rates are just and reasonable under sections 16-19, 16-19a and 16-19e] promote the development of new combined heat and power projects in Connecticut through low-interest loans, grants or power purchase agreements. The amount of such loans, grants and power purchase agreements shall be determined by the department on an individualized basis for each proposed combined heat and power project with the goal of minimizing costs to the general class of ratepayers, ensuring that the project developer has a significant share of the financial burden and risk, while ensuring the development of projects that benefit Connecticut's economy, ratepayers or environment. The department shall determine if the benefits of such project to Connecticut's ratepayers, economy or environment are sufficient to justify ratepayer investment. The program established pursuant to this section shall not exceed two hundred fifty megawatts, and the department shall review the program annually. If the department determines during an annual review that the net cost to ratepayers of this program exceeds twenty-five million dollars, the department shall not approve additional projects that require ratepayer subsidies. For purposes of department review of the net cost to ratepayers of the program, the department shall take into account both (1) the benefits of any power purchase agreements for ratepayers, any estimated benefits of avoided costs of building alternative electric infrastructure, or other benefits, and (2) the costs of all ratepayer subsidies, the cost of power purchase agreements, and other costs.

(c) (1) The Department of Energy and Environmental Protection shall on or before March 1, 2012, establish a program to promote the development of new combined heat and power projects in Connecticut that are below three megawatts in capacity size. The department shall set one or more standardized grant amounts, loan amounts and power purchase agreements for such projects to limit the administrative burden of project approvals for the department and the project proponent. Such standardized provisions shall seek to minimize costs for the general class of ratepayers, ensuring that the project developer has a significant share of the financial burden and risk, while ensuring the development of projects that benefit Connecticut's economy, ratepayers, or environment. The department may in its discretion decline to support a proposed project if the benefits of such project to Connecticut's ratepayers, economy or environment, including emissions reductions, are too meager to justify ratepayer or taxpayer investment.

(2) The program established pursuant to this section shall not exceed fifty megawatts, and the department shall review the program annually. If the department determines during an annual review that the net cost to ratepayers of this program exceeds fifteen million dollars, the department shall not approve additional projects that require ratepayer subsidies. For purposes of department review of the net cost to ratepayers of the program, the department shall take into account both (1) the benefits of any power purchase agreements for ratepayers, any estimated benefits of avoided costs of building alternative electric infrastructure, or other benefits, and (2) the costs of all ratepayer subsidies, the cost of power purchase agreements, and other costs.

Sec. 92. Subsection (b) of section 7-233e of the general statutes is amended by adding subdivision (30) as follows (Effective July 1, 2011):

(NEW) (30) To bid on standard service pursuant to section 16-244c of the general statutes.

Sec. 93. (NEW) (Effective July 1, 2011) The Department of Energy and Environmental Protection shall develop with leading research and academic institutions a set of innovation hubs, including, but not limited to, electric vehicle infrastructure and electricity storage.

Sec. 94. Sections 16-1b, 16-19uu and 16-261a of the general statutes and section 139 of public act 10-179 are repealed. (Effective July 1, 2011)

This act shall take effect as follows and shall amend the following sections:

Section 1

July 1, 2011

New section

Sec. 2

July 1, 2011

4-5

Sec. 3

July 1, 2011

4-38c

Sec. 4

July 1, 2011

4-67e

Sec. 5

July 1, 2011

4b-47(a) and (b)

Sec. 6

July 1, 2011

4d-90(a)

Sec. 7

July 1, 2011

4d-100(a)

Sec. 8

July 1, 2011

16-1

Sec. 9

July 1, 2011

16-2

Sec. 10

July 1, 2011

16-2c

Sec. 11

July 1, 2011

16-8(a) and (b)

Sec. 12

July 1, 2011

16-50j

Sec. 13

July 1, 2011

16a-3

Sec. 14

July 1, 2011

16a-3c

Sec. 15

July 1, 2011

16a-4

Sec. 16

July 1, 2011

16a-7b(b)

Sec. 17

July 1, 2011

16a-7c(a)

Sec. 18

July 1, 2011

16a-22c

Sec. 19

July 1, 2011

16a-23t(f)

Sec. 20

July 1, 2011

16a-37w

Sec. 21

July 1, 2011

16a-38k(b)

Sec. 22

July 1, 2011

16a-39

Sec. 23

July 1, 2011

16a-40

Sec. 24

July 1, 2011

16a-41b

Sec. 25

July 1, 2011

16a-46

Sec. 26

July 1, 2011

16a-46c

Sec. 27

July 1, 2011

21a-86a

Sec. 28

July 1, 2011

21a-86c(a)

Sec. 29

July 1, 2011

22a-174l

Sec. 30

July 1, 2011

22a-1b

Sec. 31

July 1, 2011

22a-2

Sec. 32

July 1, 2011

22a-5

Sec. 33

July 1, 2011

22a-11

Sec. 34

July 1, 2011

22a-119(e)

Sec. 35

July 1, 2011

22a-198

Sec. 36

July 1, 2011

22a-354i

Sec. 37

July 1, 2011

22a-354w

Sec. 38

July 1, 2011

22a-371(d)

Sec. 39

July 1, 2011

23-8

Sec. 40

July 1, 2011

23-102

Sec. 41

July 1, 2011

25-32i

Sec. 42

July 1, 2011

25-33o

Sec. 43

July 1, 2011

25-157

Sec. 44

July 1, 2011

28-24

Sec. 45

July 1, 2011

16a-48

Sec. 46

July 1, 2011

16-245m

Sec. 47

July 1, 2011

16-245n

Sec. 48

July 1, 2011

16a-3a

Sec. 49

from passage

New section

Sec. 50

July 1, 2011

New section

Sec. 51

July 1, 2011

New section

Sec. 52

July 1, 2011

16-244c

Sec. 53

July 1, 2011

16-245d

Sec. 54

July 1, 2011

16-245o

Sec. 55

July 1, 2011

16-245(g)

Sec. 56

July 1, 2011

New section

Sec. 57

July 1, 2011

New section

Sec. 58

July 1, 2011

New section

Sec. 59

July 1, 2011

New section

Sec. 60

July 1, 2011

New section

Sec. 61

July 1, 2011

New section

Sec. 62

July 1, 2011

New section

Sec. 63

July 1, 2011

New section

Sec. 64

July 1, 2011

New section

Sec. 65

October 1, 2011

New section

Sec. 66

July 1, 2011

New section

Sec. 67

July 1, 2011

New section

Sec. 68

July 1, 2011

16-32f(b)

Sec. 69

July 1, 2011

16-243v(e)

Sec. 70

July 1, 2011

New section

Sec. 71

July 1, 2011

New section

Sec. 72

July 1, 2011

New section

Sec. 73

from passage

New section

Sec. 74

July 1, 2011

7-148(c)(6)(B)

Sec. 75

July 1, 2011

New section

Sec. 76

from passage

New section

Sec. 77

from passage

New section

Sec. 78

July 1, 2011

16-245aa

Sec. 79

July 1, 2011

16a-38p

Sec. 80

July 1, 2011

32-39

Sec. 81

July 1, 2011

16-245z

Sec. 82

July 1, 2011

New section

Sec. 83

July 1, 2011

New section

Sec. 84

July 1, 2011

17b-801

Sec. 85

July 1, 2011

New section

Sec. 86

July 1, 2011

New section

Sec. 87

July 1, 2011

New section

Sec. 88

July 1, 2011

New section

Sec. 89

July 1, 2011

New section

Sec. 90

July 1, 2011

New section

Sec. 91

July 1, 2011

16-243i

Sec. 92

July 1, 2011

7-233e(b)

Sec. 93

July 1, 2011

New section

Sec. 94

July 1, 2011

Repealer section

Statement of Purpose:

To reduce energy costs and promote renewable energy.

[Proposed deletions are enclosed in brackets. Proposed additions are indicated by underline, except that when the entire text of a bill or resolution or a section of a bill or resolution is new, it is not underlined.]

Co-Sponsors:

SEN. WILLIAMS, 29th Dist.; SEN. LOONEY, 11th Dist.

SEN. FONFARA, 1st Dist.

S.B. 1