By: Darby | H.B. No. 1254 |
|
||
|
||
relating to certificates of public convenience and necessity for | ||
certain transmission projects. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 37.0541, Utilities Code, is amended to | ||
read as follows: | ||
Sec. 37.0541. CONSOLIDATION OF CERTAIN PROCEEDINGS. The | ||
commission shall consolidate the proceeding on an application to | ||
obtain or amend a certificate of convenience and necessity for the | ||
construction of a transmission line with the proceeding on another | ||
application to obtain or amend a certificate of convenience and | ||
necessity for the construction of a transmission line if it is | ||
apparent from the applications or a motion to intervene in either | ||
proceeding that the transmission lines that are the subject of the | ||
separate proceedings share a common point of interconnection. [ |
||
SECTION 2. Section 37.056, Utilities Code, is amended by | ||
adding Subsections (a-1), (d-1), (d-2), and (d-3) and amending | ||
Subsection (d) to read as follows: | ||
(a-1) In this section: | ||
(1) "Interzonal" means involving more than one ERCOT | ||
load zone. | ||
(2) "Intrazonal" means involving a single ERCOT load | ||
zone. | ||
(d) The commission by rule shall establish criteria, in | ||
addition to the criteria described by Subsection (c), for granting | ||
a certificate for a transmission project that serves the ERCOT | ||
power region and[ |
||
reliability standards[ |
||
(d-1) Except as provided by Subsection (d-2), an | ||
application for a certificate described by Subsection (d) [ |
||
of the transmission project [ |
||
estimated [ |
||
decision to grant or deny the certificate the commission's findings | ||
on the comparison. The comparison must account for: | ||
(1) the probable improvement of service and reduction | ||
of costs for consumers that may be realized from the project; | ||
(2) an estimated value of the reduction in curtailment | ||
costs that may be realized from the project; | ||
(3) an estimation of reduced transmission losses that | ||
may be realized from the project; | ||
(4) an assessment of whether the project will provide | ||
improved access to the ERCOT power grid for new generation | ||
facilities and the benefits that improved access could provide to | ||
generation facilities, industrial load, and the ERCOT market; | ||
(5) an estimation of reduced future transmission | ||
investment costs that may be realized from the project; | ||
(6) an estimation of costs of projects described by | ||
Subsection (d-2) that may be avoided as a result of the project; and | ||
(7) an estimation of direct economic benefits that may | ||
be realized from the construction of the project [ |
||
(d-2) If an application does not include a comparison | ||
described by Subsection (d-1), the commission may not grant a | ||
certificate for a project described by Subsection (d) unless the | ||
commission finds that the project is needed to support a reliable | ||
and adequate transmission network, to facilitate wholesale | ||
competition, or to minimize curtailments due to interzonal | ||
constraints and intrazonal congestion. | ||
(d-3) Not less than once per year, the independent | ||
organization certified under Section 39.151 for the ERCOT power | ||
region shall identify pending applications for transmission | ||
projects that will meet commission findings under Subsection (d-2). | ||
SECTION 3. Section 39.904(k), Utilities Code, is amended to | ||
read as follows: | ||
(k) The commission and the independent organization | ||
certified for ERCOT shall study the need for increased transmission | ||
and generation capacity throughout this state and report to the | ||
legislature the results of the study and any recommendations for | ||
legislation. The report must be filed with the legislature not | ||
later than December 31 of each even-numbered year [ |
||
SECTION 4. Subchapter Z, Chapter 39, Utilities Code, is | ||
amended by adding Section 39.919 to read as follows: | ||
Sec. 39.919. CRITICAL DESIGNATION TRANSMISSION | ||
INFRASTRUCTURE PROJECTS. (a) In this section: | ||
(1) "Interzonal" means involving more than one ERCOT | ||
load zone. | ||
(2) "Intrazonal" means involving a single ERCOT load | ||
zone. | ||
(b) Not later than December 30, 2023, the independent | ||
organization certified under Section 39.151 for the ERCOT power | ||
region shall: | ||
(1) identify, in consultation with the commission, | ||
critical designation transmission infrastructure projects and the | ||
transmission and distribution utilities that will construct and | ||
operate the projects in a manner consistent with Section 37.056; | ||
and | ||
(2) submit a written description of each project to | ||
the commission. | ||
(c) Projects identified under Subsection (b) must | ||
facilitate a timely and targeted expansion of the electric power | ||
grid in ERCOT for the purposes of: | ||
(1) resolving existing interzonal and intrazonal | ||
transmission constraints, congestion, or curtailments, including | ||
generic transmission constraints; and | ||
(2) ensuring the future reliability of the ERCOT | ||
electric power grid. | ||
(d) To the extent practicable, projects identified under | ||
Subsection (b) should: | ||
(1) be cost-effective and designed to transmit high | ||
volumes of electricity in and across ERCOT load zones efficiently; | ||
(2) minimize the need for the acquisition of new | ||
rights-of-way by replacing aging infrastructure or following | ||
routes that align with existing rights-of-way or existing | ||
transmission infrastructure; | ||
(3) minimize interzonal constraints and intrazonal | ||
congestion during construction activities; | ||
(4) be designed to accommodate new solutions, | ||
including higher voltages, if the independent organization | ||
determines that new solutions are required; and | ||
(5) be designed to significantly reduce present or | ||
expected future interzonal constraints and intrazonal congestion. | ||
(e) The independent organization certified under Section | ||
39.151 for the ERCOT power region shall identify as a critical | ||
designation transmission infrastructure project under Subsection | ||
(b) a project addressing an interzonal constraint or intrazonal | ||
congestion in an area if: | ||
(1) the constraint or congestion has been present for | ||
three years or longer; and | ||
(2) the area has experienced constraint or congestion | ||
costs greater than or equal to $100 million per year in each of the | ||
previous three years. | ||
(f) The independent organization certified under Section | ||
39.151 for the ERCOT power region may consult with the independent | ||
organization's market participant segments and other stakeholders | ||
to identify projects under Subsection (b) that could facilitate: | ||
(1) the growth of the economy of this state; or | ||
(2) oil and gas, commercial, and industrial | ||
development that could provide substantial new tax revenue, | ||
landowner income, or new jobs in this state. | ||
(g) Not later than the 450th day after the date that the | ||
independent organization certified under Section 39.151 for the | ||
ERCOT power region submits a written description of a project to the | ||
commission under Subsection (b), the utility that will construct | ||
and operate the project shall submit to the commission an | ||
application for a certificate of public convenience and necessity | ||
for the project. | ||
(h) In considering an application for a certificate of | ||
public convenience and necessity for a project identified under | ||
Subsection (b), the commission is not required to consider the | ||
factors provided by Sections 37.056(c)(1) and (2). The commission | ||
shall consider all factors provided by Section 37.056, including | ||
Sections 37.056(c)(1) and (2), for a project not identified under | ||
Subsection (b). | ||
(i) If the commission issues a certificate of public | ||
convenience and necessity for a project identified under Subsection | ||
(b), the commission shall find that the project is used and useful | ||
to the utility in providing service for purposes of this section, | ||
prudent, and includable in the rate base, regardless of the extent | ||
of the utility's actual use of the project. | ||
(j) Transmission service that is facilitated through a | ||
project identified under Subsection (b) must be provided in a | ||
manner consistent with Subchapter A, Chapter 35. | ||
(k) This section expires September 1, 2032. | ||
SECTION 5. Sections 39.904(g), (h), (i), and (j), Utilities | ||
Code, are repealed. | ||
SECTION 6. The changes in law made by this Act apply only to | ||
a proceeding affecting a certificate of public convenience and | ||
necessity that commences on or after the effective date of this Act. | ||
A proceeding affecting a certificate of public convenience and | ||
necessity that commenced before the effective date of this Act is | ||
governed by the law in effect on the date the proceeding is | ||
commenced, and that law is continued in effect for that purpose. | ||
SECTION 7. The recovery of a transmission facility | ||
investment made by an electric utility to serve a competitive | ||
renewable energy zone is governed by the law in effect on the date | ||
the facility is placed in service, regardless of whether the | ||
facility is completed before, on, or after the effective date of | ||
this Act, and that law is continued in effect for that purpose. | ||
SECTION 8. This Act takes effect September 1, 2023. |