Bill Text: NJ A919 | 2024-2025 | Regular Session | Introduced
Bill Title: Establishes procedures and standards regarding public service privatization contracts.
Spectrum: Slight Partisan Bill (Democrat 7-4)
Status: (Introduced) 2024-01-09 - Introduced, Referred to Assembly Labor Committee [A919 Detail]
Download: New_Jersey-2024-A919-Introduced.html
STATE OF NEW JERSEY
221st LEGISLATURE
PRE-FILED FOR INTRODUCTION IN THE 2024 SESSION
Sponsored by:
Assemblywoman VERLINA REYNOLDS-JACKSON
District 15 (Hunterdon and Mercer)
Assemblyman BENJIE E. WIMBERLY
District 35 (Bergen and Passaic)
Assemblyman ANTHONY S. VERRELLI
District 15 (Hunterdon and Mercer)
Assemblywoman ANNETTE QUIJANO
District 20 (Union)
Co-Sponsored by:
Assemblywoman Swift, Assemblymen Guardian, Sampson, Simonsen, McClellan, DeAngelo and Conaway
SYNOPSIS
Establishes procedures and standards regarding public service privatization contracts.
CURRENT VERSION OF TEXT
Introduced Pending Technical Review by Legislative Counsel.
An Act establishing procedures and standards with respect to certain privatization contracts and supplementing Title 52 of the Revised Statutes.
Be It Enacted by the Senate and General Assembly of the State of New Jersey:
1. The Legislature finds and declares that:
a. Using private contractors to provide public services formerly provided by public employees does not always promote the public interest;
b. Decisions to use private contractors to provide public services must be based on factors which promote the public interest;
c. To ensure that citizens of the State receive high quality public services at low cost, with due regard for the taxpayers of the State and the needs of public and private workers, it is necessary to regulate privatization contracts for public services and to require a thorough review and analysis of potential cost impacts prior to entering into any such privatization contract; and
d. It is appropriate to require that cost savings of the contract to the State be substantial and significant because of the hazard that the use of private contractors to provide services may prove, in the long term, to be less efficient or more expensive than expected when the contracting commences, and the ability of an agency to resume the public provision of services under those circumstances may be hindered by factors such as the divestment of equipment and capital and the loss of experienced, highly qualified personnel in connection with the contract.
2. As used in this act:
"Agency" means any department, division, board, commission or other office or officer of the State or of any political subdivision of the State, or any authority or other instrumentality of the State.
"Employee benefits" means all benefits provided to employees, including, but not limited to, pensions, paid time off and health insurance plans, including coverage provided under those plans to the employee, the employee's spouse and dependent children.
"Local agency" means any department, division, board, commission or other office or officer of any political subdivision of the State.
"Privatization contract" or "contract" means an agreement or combination or series of agreements valued at a total of $500,000 or more, if an agency is a local agency, or $1,000,000 or more if the agency is not a local agency, by which a non-governmental person or entity agrees with the agency to provide services which are substantially similar to, and in lieu of, services previously provided, in whole or in part, by regular employees of the agency which results in a loss of employment for the regular employees, except that none of the following shall be considered a privatization contract:
(1) any agreement solely to provide legal, management consulting, planning, engineering or design services;
(2) any contract solely for public work subject to the prevailing wage requirements of P.L.1963, c. 150 (C.34:11-56.25 et seq.);
(3) any contract to have services principally provided by persons with disabilities employed by rehabilitation facilities as defined under the provisions of the "Rehabilitation Facilities Set-Aside Act," P.L.1981, c.488 (C.30:6-23 et seq.);
(4) any contract with a vendor providing software or other information technology or equipment for the purpose of enhancing or increasing the productivity, efficiency, or effectiveness of regular employees of the agency in providing services; or
(5) any contract under which a vendor provides services during an emergency or other unpredictable situation which creates a need for more services than the current regular employees are able to provide during the emergency or situation, provided that there is no loss of employment for regular employees who normally provide the services.
3. No agency shall enter into a privatization contract, and no privatization contract with the agency shall be valid, unless all of the following requirements are met:
a. The agency shall solicit competitive sealed bids for each privatization contract based on a comprehensive written statement, prepared by the agency, of the quality and quantity of the services proposed to be the subject of the privatization contract, any fees, fares or other charges to the public, the current costs to the agency of providing those services, the qualifications, compensation and benefits of agency personnel currently performing those services, and a comprehensive description of the information the prospective contractor is required to provide as part of the bid as required for the evaluation of the bid pursuant to this section, and, if the bidder is awarded the contract, a comprehensive description of the information that the contractor is required to provide, including the quarterly reports required pursuant to subsections b. and c. of this section for ongoing oversight and the post-audits conducted pursuant to this act. The day designated by the agency upon which it will accept the sealed bids shall be the same for any and all parties. The statement shall be a public record, and shall be transmitted to the Office of the State Comptroller for review. The term of a privatization contract shall not exceed five years. No amendment to a privatization contract shall be valid if it has the purpose or effect of avoiding any requirement of this section.
b. Every bid for a privatization contract and every privatization contract shall require that the public not be subject to any fees, fares, or other charges greater than those currently charged, that the quantity and quality of the services performed under the contract equal or exceed the quantity and quality of services currently performed by agency employees, that the contractor has the demonstrated ability and experience to provide services of that quantity and quality, that the staff used by the contractor have certification, licensing and levels of job proficiency equal to or exceeding those of the agency employees currently performing the services, and that the rate of wages and employee benefits for each position not be less than the rate of wages and employee benefits for comparable agency employees. Each bid shall include a requirement that, in addition to the quarterly payroll records required pursuant to subsection c. of this section, quarterly reports be made to the agency regarding contractor compliance with the requirements of this subsection regarding the quality and quantity of services and any charges imposed on the public, and those reports shall be made public by the agency. The agency shall have access to all contractor records relevant to compliance with the requirements of this section.
c. For
each position in which a bidder will employ any person pursuant to the
privatization contract, the statement made by the agency pursuant to subsection
a. of this section shall include the rate of wages and employee benefits paid
by the agency to the regular agency employee or employees most comparable to
the position under the privatization contract. Each bid for a privatization
contract and every privatization contract shall include provisions specifically
stating the rate of wages and employee benefits for each position, which shall
not be less than the rate of wages and employee benefits stated by the agency
for comparable agency employees. Each contractor shall submit quarterly
payroll records to the agency, listing the name, hours worked, the hourly wage
and employee benefit rates paid to each employee, and the agency shall make the
records available upon request to any labor organization representing employees
of the contractor or employees or displaced employees of the agency. Any
contractor who fails to pay the rates of wages and employee benefits required
by the contract pursuant to this subsection shall be subject to the remedies which
apply in connection with a failure to pay the prevailing wage pursuant to the
"New Jersey Prevailing Wage Act," P.L.1963, c.150 (C.34:11-56.25 et seq.),
including, but not limited to, the withholding of payments from the agency to
the contractor pursuant to section 9 of P.L.1963, c.150 (C.34:11-56.33), the
imposition of fines and penalties by the Commissioner of Labor and Workforce
Development pursuant to sections 11 and 15 of P.L.1963, c.150 (C.34:11-56.35
and 34:11-56.39), debarment from contracting pursuant to sections 13 and 14 of
P.L.1963, c.150 (C.34:11-56.37 and 34:11-56.38), and the actions by workers to
recover unpaid amounts in civil actions pursuant to section 16 of P.L.1963,
c.150
(C.34:11-56.40). The commissioner shall have the same authority and
responsibility to conduct investigations, inspections and other activities to
enforce wage and benefit payments due under contracts pursuant to this section
as he has to conduct investigations, inspections and other activities to
enforce payments of prevailing wages pursuant to the "New Jersey Prevailing
Wage Act," P.L.1963, c.150
(C.34:11-56.25 et seq.).
d. The agency, prior to soliciting bids, shall prepare a comprehensive estimate of the costs of regular agency employees providing the services subject to the contract, including the cost of employee benefits and provide the agency personnel performing the services and the majority representative of those personnel a period of 30 days to review the agency's estimates of the cost of agency personnel performing the services and submit an alternative cost estimate based on that review and any proposal made by the majority representative to reduce costs and increase the efficiency of agency operations in a manner which is in compliance with the requirements of this section, including all requirements regarding charges to the public, the quantity and quality of services, and employee remuneration. The agency shall review any proposal and revised estimate after bidding has been completed and make a determination of whether and how much to reduce the agency's estimates of the cost of agency personnel performing the services when making the comparison with the cost to the agency of the contractor's bid pursuant to this section and determining whether the bid will provide savings for the agency. The agency shall not disclose the majority representative's alternative estimate or proposal to reduce costs prior to the completion of the bidding.
e. The contract shall require the contractor to comply with a policy of nondiscrimination and equal opportunity, take affirmative steps to provide that equal opportunity, and offer available employee positions to qualified regular employees of the agency who are displaced or dismissed from agency employment, in whole or in part, because of the privatization contract, and the agency shall, in consultation with affected agency personnel and their majority representative, and prior to the commencing of the term of the contract, prepare a plan of assistance for each employee displaced as a result of the contract, including any training needed to place the employee in a position with the contractor or the agency.
f. The contractor making the bid, and its subsidiaries, affiliates, principals and managerial or supervisory employees are not, when the bid is made or the contract is awarded, or during the ten-year period before the award were not, subject to debarment, suspension, adjudication or conviction, or any criminal conviction at any time, which debarment, suspension, adjudication or conviction is due to substantial or repeated noncompliance with any federal or State law pertaining to the operation of a business, including, but not limited to, laws regarding labor relations, workplace standards, occupational safety and health, public safety and health, environmental protection, nondiscrimination and affirmative action, tax payment and conflicts of interest.
g. The agency shall make public its determination of whether to award a contract within 60 days of the completion of the bidding.
h. If the agency determines, after soliciting and receiving bids, that one or more of the bids comply with the cost savings requirement and all other requirements of this section, the agency shall publicly designate to which of the compliant bidders it proposes to award the contract and issue a comprehensive written analysis of the total contract cost of the designated bid, including the costs of transition from public to private operation and any additional unemployment and retirement benefits of agency employees, and the costs of monitoring and administering contract performance born pursuant to this act by the agency and any State entity, including the State Auditor and the Office of the State Comptroller. If the designated bidder is headquartered outside the State, or proposes to perform any or all of the work done under contract outside the boundaries of the State, the contract cost shall be increased by the amount of income tax revenue, if any, which will be lost to the State by the corresponding elimination of agency employees.
i. The agency shall provide the Office of the State Comptroller with a copy of the proposed privatization contract and a written certification:
(1) That the agency has complied with all provisions of this section;
(2) That the agency finds that the proposed privatization contract is in the public interest and meets all requirements of this section;
(3) That the agency finds that the estimated contract cost is less than the cost of agency personnel performing the services, taking into account any reduction of that cost made by the agency pursuant to subsection d. of this section; and
(4) That sets forth the agency's estimate of the total amount of the cost savings to the agency that would be provided by the contract.
4. The Office of the State Comptroller shall, within 30 business days after receiving the certificate required by section 3 of this act, review the certification of the agency, and prohibit the agency from entering into the privatization contract if the office determines that the bid does not provide cost savings or that the agency has failed to comply with any other requirement of this section. The office may require by summons the attendance and testimony under oath of witnesses and the production of books, papers and other records relating to that review. The office may extend the time for an objection for an additional period of 30 business days beyond the original 30 business days by written notice to the agency, stating the reason for that extension. The determination shall be final and binding on the agency, unless withdrawn due to a revision of the certification by the agency found satisfactory by the office. The certification, the proposed contract, the determination and any revision of the determination, with supporting documentation, shall be made available by the office to the public on the Internet.
5. The State Auditor shall, as part of his responsibility under R.S.52:24-4, conduct an annual post audit of each privatization contract entered into after the effective date of this act and shall issue, and make available to the public and representatives of employee organizations representing affected employees, an annual report to the Governor and the Legislature regarding the contract, the first of which shall be issued not more than 90 days after the end of the first year that the contract is in effect. The report shall include an evaluation of the actual entire cost and any actual cost savings of the contract compared with the amount of cost and savings estimated when the contract was awarded, with an analysis of whether any failure to provide the amount of savings was related to misrepresentation, fraud or other malfeasance, misfeasance or nonfeasance of an agency or contractor, and a review of the compliance of the agency and the contractor with the provisions of this act, including all requirements regarding charges to the public, the quantity and quality of services, and the qualifications and remuneration of contractor employees, with an analysis of whether any non-compliance was related to misrepresentation, fraud or other malfeasance, misfeasance or nonfeasance of an agency or contractor. Any agency or contractor, or officer or agent of the agency or contractor, determined to be responsible for the misrepresentation, fraud or other malfeasance, misfeasance or nonfeasance shall be subject to penalties and sanctions as provided by law, including, where appropriate, debarment, contract rescission, damages, and reimbursement of excess charges to the public and underpayments to employees. Any finding by the State Auditor that a contractor has failed to make the wage or benefit payments required under a privatization contract shall be referred to the Commissioner of Labor and Workforce Development for appropriate enforcement actions. The post-audit reports, with supporting documentation and records, shall be made available by the State Auditor to the public on the Internet on an ongoing basis.
6. This act shall take effect on the 90th day after enactment. The provisions of this act shall apply to any privatization contract first entered into on or after the effective date of this act and to any renewal extension, or transfer to another contractor of that privatization contract, but the provisions of this act shall not apply to any privatization contract which is first entered into prior to the effective date of this act, or any renewal, extension, or transfer of that privatization contract.
STATEMENT
This bill prohibits the privatization of public services unless there are cost savings which are not based on increased charges or reduced services to the public, or lowered workforce standards. Each prospective private contractor would be required to demonstrate cost reductions based on improvements such as management efficiencies or technical innovation, not based on added burdens imposed on the members of the public using the services or the employees producing them.
The bill requires that a contract for the privatization of public services not be entered into without cost analyses demonstrating that there will be actual cost savings for the public agency and the taxpayers without increased fees, fares, or other charges to the public, reduced quantity or quality of services, or lowered workforce standards, including reduced staff qualifications and remuneration. The bill further requires sustained oversight and public disclosure regarding those contracts to provide accountability to taxpayers, public users of the services, and employees producing the services, that the cost savings actually occur without increased charges, or reduced services or workforce standards, and provides penalties and sanctions for any noncompliance involving agency or contractor misrepresentation, fraud or other malfeasance, misfeasance or nonfeasance.
The bill's prohibition on the privatization of public services does not apply to contracts for: (1) legal, management consulting, planning, engineering or design services, (2) prevailing wage construction work, (3) certain services provided by disabled individuals employed by rehabilitation facilities, (4) a vendor providing software or other information technology or equipment for the purpose of enhancing or increasing the productivity, efficiency, or effectiveness of regular employees of the agency in providing services; or (5) services which a vendor provides during an emergency or other unpredictable situation which creates a need for more services than the current regular employees are able to provide during the emergency or situation, provided that there is no loss of employment for regular employees who normally provide the services.
The bill prohibits any political subdivision from entering into a contract of $500,000 or more, and any public body, including the State, from entering into a contract of $1 million or more, to purchase from private entities services previously performed by agency employees, unless:
1. The agency solicits competitive sealed bids for the contracts based on a comprehensive statement of requirements by the agency;
2. The contract requires that the public not be charged fares, fees or other charges greater than those currently charged, that the quantity and quality of the services provided equal or exceed the quantity and quality of services currently provided, that the contractor is qualified, and that contractor employees have qualifications and wage and benefit rates at least equal to the agency employees currently performing the services. Contractors are required to submit payroll records to the agency and, upon any failure to pay the agreed upon wage and benefit rates, are subject to the remedies and penalties provided by the "New Jersey Prevailing Wage Act," P.L.1963, c.150 (C.34:11-56.25 et seq.) for failure to pay the prevailing wage;
3. The agency permits the union of the affected agency employees to review the agency's estimate of current costs and submit an alternative cost estimate and propose cost saving measures compliant with requirements of the bill and the agency reviews the union estimate and proposal and makes a determination whether to reduce the agency's estimate of current costs;
4. The contract requires compliance with antidiscrimination standards, requires available positions to be offered to qualified displaced agency employees, and requires the agency to prepare a plan of training and assistance for displaced employees;
5. The contractor and specified associates have no adjudicated record of substantial or repeated noncompliance with any federal or State law pertaining to the operation of a business, including laws regarding contracting and conflict of interest;
6. After receiving bids, the agency publicly designates the bidder to which it proposes to award the contract and issues a comprehensive written analysis of the total contract cost of the designated bid; and
7. The agency provides written certification that the agency and the proposed contract are in compliance with all provisions of the bill and the total estimated contract cost is less than the cost of agency employees performing the services, with a statement of the amount of the savings.
The bill requires the agency to make public its determination of whether to award a contract within 60 days of the completion of the bidding.
The Office of the State Comptroller would be required to review the certification and prohibit the agency from entering into the privatization contract if the office provides a written determination that the bid does not provide cost savings or that the agency has otherwise failed to comply with any requirement of the bill.
The State Auditor would be required to conduct post-audits of contracts subject to the bill, evaluating whether the projected cost savings were obtained without raising charges, cutting services, or lowering workforce standards. If the noncompliance was related to agency or contractor misrepresentation, fraud or other malfeasance, misfeasance or nonfeasance, the agency or contractor would be subject to penalties and sanctions including, where appropriate, debarment or rescission of contracts, or reimbursement of excess charges to the public and underpayments of employees.
The requirements of the bill apply to any privatization contract entered into after the effective date of the bill and any renewal, extension or transfer of that contract, but do not apply to contracts entered into before the effective date or renewals, extensions or transfers of those contracts.