Bill Text: IL SB1821 | 2011-2012 | 97th General Assembly | Enrolled
NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Creates the Carbon Dioxide Transport by Pipeline Act. Contains only a short title provision.
Sponsorship: Moderate Partisan Bill (Democrat 7-1)
Status: (Passed) 2011-08-23 - Public Act . . . . . . . . . 97-0534 [SB1821 Detail]
Download: Illinois-2011-SB1821-Enrolled.html
Bill Title: Creates the Carbon Dioxide Transport by Pipeline Act. Contains only a short title provision.
Sponsorship: Moderate Partisan Bill (Democrat 7-1)
Status: (Passed) 2011-08-23 - Public Act . . . . . . . . . 97-0534 [SB1821 Detail]
Download: Illinois-2011-SB1821-Enrolled.html
| |||||||
| |||||||
| |||||||
| 1 | AN ACT concerning regulation.
| ||||||
| 2 | Be it enacted by the People of the State of Illinois, | ||||||
| 3 | represented in the General Assembly:
| ||||||
| 4 | Section 1. Short title. This Act may be cited as the Carbon | ||||||
| 5 | Dioxide Transportation and Sequestration Act.
| ||||||
| 6 | Section 5. Legislative purpose. Pipeline transportation of | ||||||
| 7 | carbon dioxide for sequestration, enhanced oil recovery, and | ||||||
| 8 | other purposes is declared to be a public use and service, in | ||||||
| 9 | the public interest, and a benefit to the welfare of Illinois | ||||||
| 10 | and the people of Illinois because pipeline transportation is | ||||||
| 11 | necessary for sequestration, enhanced oil recovery, or other | ||||||
| 12 | carbon management purposes and thus is an essential component | ||||||
| 13 | to compliance with required or voluntary plans to reduce carbon | ||||||
| 14 | dioxide emissions from "clean coal" facilities and other | ||||||
| 15 | sources. Carbon dioxide pipelines are critical to the promotion | ||||||
| 16 | and use of Illinois coal and also advance economic development, | ||||||
| 17 | environmental protection, and energy security in the State.
| ||||||
| 18 | Section 10. Definitions. As used in this Act: | ||||||
| 19 | "Carbon dioxide pipeline" or "pipeline" means the in-state | ||||||
| 20 | portion of a pipeline, including appurtenant facilities, | ||||||
| 21 | property rights, and easements, that are used exclusively for | ||||||
| 22 | the purpose of transporting carbon dioxide to a point of sale, | ||||||
| |||||||
| |||||||
| 1 | storage, enhanced oil recovery, or other carbon management | ||||||
| 2 | application. | ||||||
| 3 | "Clean coal facility" has the meaning ascribed to that term | ||||||
| 4 | in Section 1-10 of the Illinois Power Agency Act. | ||||||
| 5 | "Clean coal SNG facility" has the meaning ascribed to that | ||||||
| 6 | term in Section 1-10 of the Illinois Power Agency Act. | ||||||
| 7 | "Commission" means the Illinois Commerce Commission. | ||||||
| 8 | "Sequester" has the meaning ascribed to that term in | ||||||
| 9 | Section 1-10 of the Illinois Power Agency Act. | ||||||
| 10 | "Transportation" means the physical movement of carbon | ||||||
| 11 | dioxide by pipeline conducted for a person's own use or account | ||||||
| 12 | or
the use or account of another person or persons.
| ||||||
| 13 | Section 15. Scope. This Act applies to the application | ||||||
| 14 | process for the issuance of a certificate of authority by an | ||||||
| 15 | owner or operator of a pipeline designed, constructed, and | ||||||
| 16 | operated to transport and to sequester carbon dioxide produced | ||||||
| 17 | by a clean coal facility, by a clean coal SNG facility, or by | ||||||
| 18 | any other source that will result in the reduction of carbon | ||||||
| 19 | dioxide emissions from that source.
| ||||||
| 20 | Section 20. Application. | ||||||
| 21 | (a) No person or entity may construct, operate, or repair a | ||||||
| 22 | carbon dioxide pipeline unless the person or entity possesses a | ||||||
| 23 | certificate of authority. | ||||||
| 24 | (b) The Commission, after a hearing, may grant an | ||||||
| |||||||
| |||||||
| 1 | application for a certificate of authority authorizing the | ||||||
| 2 | construction and operation of a carbon dioxide pipeline if it | ||||||
| 3 | makes a specific written finding as to each of the following: | ||||||
| 4 | (1) the application was properly filed; | ||||||
| 5 | (2) the applicant is fit, willing, and able to | ||||||
| 6 | construct and operate the pipeline in compliance with this | ||||||
| 7 | Act and with Commission regulations and orders of the | ||||||
| 8 | Commission or any applicable federal agencies; | ||||||
| 9 | (3) the applicant has entered into an agreement with a | ||||||
| 10 | clean coal facility, a clean coal SNG facility, or any | ||||||
| 11 | other source that will result in the reduction of carbon | ||||||
| 12 | dioxide emissions from that source; | ||||||
| 13 | (4) the applicant has filed
with the Pipeline and | ||||||
| 14 | Hazardous Materials Safety
Administration of the U.S. | ||||||
| 15 | Department of Transportation
all forms required by that | ||||||
| 16 | agency in advance of
constructing a carbon dioxide | ||||||
| 17 | pipeline; | ||||||
| 18 | (5) the applicant has filed with the U.S. Army Corps of | ||||||
| 19 | Engineers all applications for
permits required by that | ||||||
| 20 | agency in advance of constructing
a carbon dioxide | ||||||
| 21 | pipeline; | ||||||
| 22 | (6) the applicant has entered into an agreement
with | ||||||
| 23 | the Illinois Department of Agriculture that governs
the | ||||||
| 24 | mitigation of agricultural impacts associated with the
| ||||||
| 25 | construction of the proposed pipeline; | ||||||
| 26 | (7) the applicant possesses the financial,
managerial, | ||||||
| |||||||
| |||||||
| 1 | legal, and technical qualifications necessary
to construct | ||||||
| 2 | and operate the proposed carbon dioxide
pipeline; and
| ||||||
| 3 | (8) the proposed pipeline is consistent with the public | ||||||
| 4 | interest, public benefit, and legislative purpose as set | ||||||
| 5 | forth in this Act. In addition to any other evidence the | ||||||
| 6 | Commission may consider on this specific finding, the | ||||||
| 7 | Commission shall consider the following: | ||||||
| 8 | (A) any evidence of the effect of the pipeline upon | ||||||
| 9 | the economy, infrastructure, and public safety | ||||||
| 10 | presented by local governmental units that will be | ||||||
| 11 | affected by the proposed pipeline route; | ||||||
| 12 | (B) any evidence of the effect of the pipeline upon | ||||||
| 13 | property values presented by property owners who will | ||||||
| 14 | be affected by the proposed pipeline or facility, | ||||||
| 15 | provided that the Commission need not hear evidence as | ||||||
| 16 | to the actual valuation of property such as that as | ||||||
| 17 | would be presented to and determined by the courts | ||||||
| 18 | under the Eminent Domain Act; | ||||||
| 19 | (C) any evidence presented by the Department of | ||||||
| 20 | Commerce and Economic Opportunity regarding the | ||||||
| 21 | current and future local, State-wide, or regional | ||||||
| 22 | economic effect, direct or indirect, of the proposed | ||||||
| 23 | pipeline or facility including, but not limited to, | ||||||
| 24 | ability of the State to attract economic growth, meet | ||||||
| 25 | future energy requirements, and ensure compliance with | ||||||
| 26 | environmental requirements and goals; | ||||||
| |||||||
| |||||||
| 1 | (D) any evidence addressing the factors described | ||||||
| 2 | in items (1) through (8) of this subsection (b) or | ||||||
| 3 | other relevant factors that is presented by any other | ||||||
| 4 | State agency, the applicant, a party, or other entity | ||||||
| 5 | that participates in the proceeding, including | ||||||
| 6 | evidence presented by the Commission's staff; and | ||||||
| 7 | (E) any evidence presented by any State or federal | ||||||
| 8 | governmental entity as to how the proposed pipeline | ||||||
| 9 | will affect the security, stability, and reliability | ||||||
| 10 | of energy. | ||||||
| 11 | In its written order, the Commission shall address all of | ||||||
| 12 | the evidence presented, and if the order is contrary to any of | ||||||
| 13 | the evidence, the Commission shall state the reasons for its | ||||||
| 14 | determination with regard to that evidence.
| ||||||
| 15 | (c) When an applicant files its application for a | ||||||
| 16 | certificate of authority with the Commission, it shall provide | ||||||
| 17 | notice to each local government where the proposed pipeline | ||||||
| 18 | will be located and include a map of the proposed pipeline | ||||||
| 19 | route. The applicant shall also publish notice in a newspaper | ||||||
| 20 | of general circulation in each county where the proposed | ||||||
| 21 | pipeline is located. | ||||||
| 22 | (d) An application for a certificate of authority filed | ||||||
| 23 | pursuant to this Section shall request either that the | ||||||
| 24 | Commission review and approve a specific route for a carbon | ||||||
| 25 | dioxide pipeline, or that the Commission review and approve a | ||||||
| 26 | project route width that identifies the areas in which the | ||||||
| |||||||
| |||||||
| 1 | pipeline would be located, with such width ranging from the | ||||||
| 2 | minimum width required for a pipeline right-of-way up to 200 | ||||||
| 3 | feet in width. A map of the route or route width shall be | ||||||
| 4 | included in the application. The purpose for allowing the | ||||||
| 5 | option of review and approval of a project route width is to | ||||||
| 6 | provide increased flexibility during the construction process | ||||||
| 7 | to accommodate specific landowner requests, avoid | ||||||
| 8 | environmentally sensitive areas, or address special | ||||||
| 9 | environmental permitting requirements. | ||||||
| 10 | (e) The Commission's rules shall ensure that notice of an | ||||||
| 11 | application for a certificate of authority is provided within | ||||||
| 12 | 30 days after filing to the landowners along a proposed project | ||||||
| 13 | route, or to the potentially affected landowners within a | ||||||
| 14 | proposed project route width, using the notification | ||||||
| 15 | procedures set forth in the Commission's rules. If the | ||||||
| 16 | Commission grants approval of a project route width as opposed | ||||||
| 17 | to a specific project route, then the applicant must, as it | ||||||
| 18 | finalizes the actual pipeline alignment within the project | ||||||
| 19 | route width, file its final list of affected landowners with | ||||||
| 20 | the Commission at least 14 days in advance of beginning | ||||||
| 21 | construction on any tract within the project route width and | ||||||
| 22 | also provide the Commission with at least 14 days' notice | ||||||
| 23 | before filing a complaint for eminent domain in the circuit | ||||||
| 24 | court with regard to any tract within the project route width. | ||||||
| 25 | (f) The Commission shall make its determination on any | ||||||
| 26 | application for a certificate of authority filed pursuant to | ||||||
| |||||||
| |||||||
| 1 | this Section and issue its final order within 11 months after | ||||||
| 2 | the date that the application is filed. The Commission's | ||||||
| 3 | failure to act within this time period shall not be deemed an | ||||||
| 4 | approval or denial of the application. | ||||||
| 5 | (g) A final order of the Commission granting a certificate | ||||||
| 6 | of authority pursuant to this Act shall be conditioned upon the | ||||||
| 7 | applicant obtaining all required permits or approvals from the | ||||||
| 8 | Pipeline and Hazardous Materials Safety Administration of the | ||||||
| 9 | U.S. Department of Transportation, U.S. Army Corps of | ||||||
| 10 | Engineers, and Illinois Department of Agriculture, in addition | ||||||
| 11 | to all other permits and approvals necessary for the | ||||||
| 12 | construction and operation of the pipeline prior to the start | ||||||
| 13 | of any construction. The final order must specifically prohibit | ||||||
| 14 | the start of any construction until all such permits and | ||||||
| 15 | approvals have been obtained. | ||||||
| 16 | (h) Within 6 months after the Commission's entry of an | ||||||
| 17 | order approving either a specific route or a project route | ||||||
| 18 | width under this Section, the owner or operator of the carbon | ||||||
| 19 | dioxide pipeline that receives that order may file supplemental | ||||||
| 20 | applications for minor route deviations outside the approved | ||||||
| 21 | project route width, allowing for additions or changes to the | ||||||
| 22 | approved route to address environmental concerns encountered | ||||||
| 23 | during construction or to accommodate landowner requests. The | ||||||
| 24 | supplemental application shall specifically detail the | ||||||
| 25 | environmental concerns or landowner requests prompting the | ||||||
| 26 | route changes, including the names of any landowners or | ||||||
| |||||||
| |||||||
| 1 | entities involved. Notice of a supplemental application shall | ||||||
| 2 | be provided to any State agency or unit of local government | ||||||
| 3 | that appeared in the original proceeding and to any landowner | ||||||
| 4 | affected by the proposed route deviation at the time that | ||||||
| 5 | supplemental application is filed. The route deviations shall | ||||||
| 6 | be approved by the Commission no sooner than 90 days after all | ||||||
| 7 | interested parties receive notice of the supplemental | ||||||
| 8 | application, unless a written objection is filed to the | ||||||
| 9 | supplemental application within 45 days after such notice is | ||||||
| 10 | received. If a written objection is filed, then the Commission | ||||||
| 11 | shall issue an order either granting or denying the route | ||||||
| 12 | deviation within 90 days after the filing of the objection. | ||||||
| 13 | Hearings on any such supplemental application shall be limited | ||||||
| 14 | to the reasonableness of the specific variance proposed, and | ||||||
| 15 | the issues of the public interest and benefit of the project or | ||||||
| 16 | fitness of the applicant shall be considered only to the extent | ||||||
| 17 | that the route deviation has raised new concerns with regard to | ||||||
| 18 | those issues. | ||||||
| 19 | (i) A certificate of authority to construct and operate a | ||||||
| 20 | carbon dioxide pipeline issued by the Commission shall contain | ||||||
| 21 | and include all of the following: | ||||||
| 22 | (1) a grant of authority to construct and operate a | ||||||
| 23 | carbon dioxide pipeline as requested in the application, | ||||||
| 24 | subject to the laws of this State; and | ||||||
| 25 | (2) a limited grant of authority to take and acquire an | ||||||
| 26 | easement in any property or interest in property for the | ||||||
| |||||||
| |||||||
| 1 | construction, maintenance, or operation of a carbon | ||||||
| 2 | dioxide pipeline in the manner provided for the exercise of | ||||||
| 3 | the power of eminent domain under the Eminent Domain Act. | ||||||
| 4 | The limited grant of authority shall be restricted to, and | ||||||
| 5 | exercised solely for, the purpose of siting, | ||||||
| 6 | rights-of-way, and easements appurtenant, including | ||||||
| 7 | construction and maintenance. The applicant shall not | ||||||
| 8 | exercise this power until it has used reasonable and good | ||||||
| 9 | faith efforts to acquire the property or easement thereto. | ||||||
| 10 | The applicant may thereafter use this power when the | ||||||
| 11 | applicant determines that the easement is necessary to | ||||||
| 12 | avoid unreasonable delay or economic hardship to the | ||||||
| 13 | progress of activities carried out pursuant to the | ||||||
| 14 | certificate of authority.
| ||||||
| 15 | Section 25. Procedures. Notwithstanding any other | ||||||
| 16 | provision of this Act, any power granted pursuant to this Act | ||||||
| 17 | to acquire an easement is subject to, and shall be exercised in | ||||||
| 18 | accordance with, the Eminent Domain Act.
| ||||||
| 19 | Section 30. Safety. A carbon dioxide pipeline owner shall | ||||||
| 20 | construct, maintain, and operate all of its pipelines, related | ||||||
| 21 | facilities, and equipment in this State in a manner that poses | ||||||
| 22 | no undue risk to its employees or the public. The Commission | ||||||
| 23 | shall not issue any certificates or permits allowing the | ||||||
| 24 | construction of a carbon dioxide pipeline until it has adopted | ||||||
| |||||||
| |||||||
| 1 | federal safety regulations governing the construction, | ||||||
| 2 | maintenance, and operations of carbon dioxide pipelines, | ||||||
| 3 | related facilities, and equipment to ensure the safety of | ||||||
| 4 | pipeline employees and the public.
| ||||||