Bill Title: Amends the Illinois Procurement Code. Provides that when the Department of Transportation enters into a contract under the Code that provides for mobilization payments and the contractor is using the services of a subcontractor, the subcontract shall include terms requiring mobilization payments be made to the subcontractor. Provides for a schedule of mobilization payments based on the initial value of the subcontract. Defines "mobilization payment".
Spectrum: Partisan Bill (Democrat 10-0)
Status: (Passed) 2017-08-25 - Public Act . . . . . . . . . 100-0333 [HB0284 Detail]
Download: Illinois-2017-HB0284-Introduced.html
Bill Title: Amends the Illinois Procurement Code. Provides that when the Department of Transportation enters into a contract under the Code that provides for mobilization payments and the contractor is using the services of a subcontractor, the subcontract shall include terms requiring mobilization payments be made to the subcontractor. Provides for a schedule of mobilization payments based on the initial value of the subcontract. Defines "mobilization payment".
Spectrum: Partisan Bill (Democrat 10-0)
Status: (Passed) 2017-08-25 - Public Act . . . . . . . . . 100-0333 [HB0284 Detail]
Download: Illinois-2017-HB0284-Introduced.html
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
1 | AN ACT concerning finance.
| ||||||||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||||||||||||||||||||
3 | represented in the General Assembly:
| ||||||||||||||||||||||||
4 | Section 5. The Illinois Procurement Code is amended by | ||||||||||||||||||||||||
5 | adding Section 30-50 as follows:
| ||||||||||||||||||||||||
6 | (30 ILCS 500/30-50 new) | ||||||||||||||||||||||||
7 | Sec. 30-50. Mobilization payments. | ||||||||||||||||||||||||
8 | (a) As used in this Section, "mobilization payment" means | ||||||||||||||||||||||||
9 | an advance payment for the preparatory work and operations | ||||||||||||||||||||||||
10 | necessary for the movement of personnel, equipment, supplies, | ||||||||||||||||||||||||
11 | and incidentals to a project site and for all other work or | ||||||||||||||||||||||||
12 | operations that must be performed or costs incurred when | ||||||||||||||||||||||||
13 | beginning work on a project. | ||||||||||||||||||||||||
14 | (b) When a contract under this Code entered into by the | ||||||||||||||||||||||||
15 | Department of Transportation provides for mobilization | ||||||||||||||||||||||||
16 | payments and the contractor is using the services of a | ||||||||||||||||||||||||
17 | subcontractor, the subcontract shall include terms requiring | ||||||||||||||||||||||||
18 | mobilization payments be made to the subcontractor. | ||||||||||||||||||||||||
19 | Mobilization payments to a subcontractor shall be made on a | ||||||||||||||||||||||||
20 | tiered system based on the initial value of the subcontract: | ||||||||||||||||||||||||
|
| ||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||
9 | (c) This Section only applies to contracts entered into by | |||||||||||||||||||||||||||||||||
10 | the Department of Transportation.
|