Bill Text: HI HB2769 | 2016 | Regular Session | Introduced


Bill Title: CIP; Forty-Fourth Representative District ($)

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced - Dead) 2016-02-01 - Referred to FIN, referral sheet 5 [HB2769 Detail]

Download: Hawaii-2016-HB2769-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

2769

TWENTY-EIGHTH LEGISLATURE, 2016

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE FORTY-FOURTH REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2016-2017.

     1.   To be expended by the department of education:

     A.   Waianae high school, Oahu

          Design and construction for the athletic locker room.

          Design                             $820,000

          Construction                     $7,380,000

          Total funding                    $8,200,000

     B.   Waianae high school, Oahu

          Design and construction to expand the cafeteria.

          Design                             $350,000

          Construction                     $3,150,000

          Total funding                    $3,500,000

     C.   Waianae high school, Oahu

          Design and construction to air condition the school.

          Design                           $1,000,000

          Construction                     $9,000,000

          Total funding                   $10,000,000

     D.   Waianae high school, Oahu

Design and construction for a rubberized all-weather track and field.

Design                             $175,000

Construction                     $1,575,000

Total funding                    $1,750,000

     E.   Waianae high school, Oahu

          Design and construction for the concession stand.

Design                             $100,000

Construction                       $900,000

Total funding                    $1,000,000

     F.   Waianae high school, Oahu

          Design and construction for stadium restrooms.

Design                             $820,000

Construction                     $7,380,000

Total funding                    $8,200,000

     G.   Waianae intermediate school, Oahu

          Design and construction to air condition the school.

Design                             $400,000

Construction                     $3,600,000

Total funding                    $4,000,000

     H.   Waianae intermediate school, Oahu

Plans and design of a classroom building.

Plans                              $400,000

Design                           $3,600,000

Total funding                    $4,000,000

     I.   Kamaile elementary school, Oahu

          Design and construction to air condition the school.

Design                             $350,000

Construction                     $3,150,000

Total funding                    $3,500,000

     J.   Kamaile elementary school, Oahu

          Plans, land acquisition, and design for school expansion.

Plans                               $50,000

Land acquisition                   $250,000

Design                             $200,000

Total funding                      $500,000

     K.   Kamaile elementary school, Oahu

          Construction to replace and install perimeter fencing.

Construction                       $100,000

Total funding                      $100,000

     L.   Leihoku elementary school, Oahu

          Design and construction to air condition the school.

Design                             $350,000

Construction                     $3,150,000

Total funding                    $3,500,000

     M.   Leihoku elementary school, Oahu

Design and construction for installation of security cameras.

Design                               $1,000

Construction                         $9,000

Total funding                       $10,000

     N.   Makaha elementary school, Oahu

          Construction for expansion of the library.

Construction                     $3,000,000

Total funding                    $3,000,000

     O.   Makaha elementary school, Oahu

          Construction for Americans with Disabilities Act (ADA) transition accessibility.

Construction                       $375,000

Total funding                      $375,000

     P.   Makaha elementary school, Oahu

          Design and construction to air condition the school.

Design                             $350,000

Construction                     $3,150,000

Total funding                    $3,500,000

     Q.   Waianae elementary school, Oahu

          Design and construction to air condition the school.

Design                             $350,000

Construction                     $3,150,000

Total funding                    $3,500,000

     R.   Waianae elementary school, Oahu

Design and construction for Phase II of the Administration Building for counseling and other administrative services.

Design                             $500,000

Construction                     $4,500,000

Total funding                    $5,000,000

     S.   Waianae public library, Oahu

Design and construction to install irrigation; paint the interior and exterior; replace the flooring; and reseal the parking lot.

Design                             $217,000

Construction                       $367,700

Total funding                      $584,700

     2.   To be expended by the department of land and natural resources:

     A.   Waianae small boat harbor, Oahu

          Design and construction to replace piers.

Design                             $300,000

Construction                     $2,700,000

Total funding                    $3,000,000

     B.   Noholio road drainage improvements, phase 1, Oahu

Plans and design for drainage improvements to Noholio road.

Plans                              $125,000

Design                             $125,000

Total funding                      $250,000

     C.   Makaha stream berm, phase 1, Oahu

Plans and design to repair the existing Makaha stream berm.

Plans                              $125,000

Design                             $125,000

Total funding                      $250,000

     3.   To be expended by the department of transportation:

     A.   Replace Eku stream bridge, Makaha, Oahu

Design and construction to replace Eku stream bridge at Farrington highway crossing Eku stream.

Design                           $1,900,000

Construction                    $17,100,000

Total funding                   $19,000,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2016.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Forty-Fourth Representative District

 

Description:

Appropriates funds for capital improvement projects for the benefit of the Forty-fourth Representative District.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

 