Bill Text: HI HB2769 | 2016 | Regular Session | Introduced
Bill Title: CIP; Forty-Fourth Representative District ($)
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Introduced - Dead) 2016-02-01 - Referred to FIN, referral sheet 5 [HB2769 Detail]
Download: Hawaii-2016-HB2769-Introduced.html
HOUSE OF REPRESENTATIVES |
H.B. NO. |
2769 |
TWENTY-EIGHTH LEGISLATURE, 2016 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE FORTY-FOURTH REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2016-2017.
1. To be expended by the department of education:
A. Waianae high school, Oahu
Design and construction for the athletic locker room.
Design $820,000
Construction $7,380,000
Total funding $8,200,000
B. Waianae high school, Oahu
Design and construction to expand the cafeteria.
Design $350,000
Construction $3,150,000
Total funding $3,500,000
C. Waianae high school, Oahu
Design and construction to air condition the school.
Design $1,000,000
Construction $9,000,000
Total funding $10,000,000
D. Waianae high school, Oahu
Design and construction for a rubberized all-weather track and field.
Design $175,000
Construction $1,575,000
Total funding $1,750,000
E. Waianae high school, Oahu
Design and construction for the concession stand.
Design $100,000
Construction $900,000
Total funding $1,000,000
F. Waianae high school, Oahu
Design and construction for stadium restrooms.
Design $820,000
Construction $7,380,000
Total funding $8,200,000
G. Waianae intermediate school, Oahu
Design and construction to air condition the school.
Design $400,000
Construction $3,600,000
Total funding $4,000,000
H. Waianae intermediate school, Oahu
Plans and design of a classroom building.
Plans $400,000
Design $3,600,000
Total funding $4,000,000
I. Kamaile elementary school, Oahu
Design and construction to air condition the school.
Design $350,000
Construction $3,150,000
Total funding $3,500,000
J. Kamaile elementary school, Oahu
Plans, land acquisition, and design for school expansion.
Plans $50,000
Land acquisition $250,000
Design $200,000
Total funding $500,000
K. Kamaile elementary school, Oahu
Construction to replace and install perimeter fencing.
Construction $100,000
Total funding $100,000
L. Leihoku elementary school, Oahu
Design and construction to air condition the school.
Design $350,000
Construction $3,150,000
Total funding $3,500,000
M. Leihoku elementary school, Oahu
Design and construction for installation of security cameras.
Design $1,000
Construction $9,000
Total funding $10,000
N. Makaha elementary school, Oahu
Construction for expansion of the library.
Construction $3,000,000
Total funding $3,000,000
O. Makaha elementary school, Oahu
Construction for Americans with Disabilities Act (ADA) transition accessibility.
Construction $375,000
Total funding $375,000
P. Makaha elementary school, Oahu
Design and construction to air condition the school.
Design $350,000
Construction $3,150,000
Total funding $3,500,000
Q. Waianae elementary school, Oahu
Design and construction to air condition the school.
Design $350,000
Construction $3,150,000
Total funding $3,500,000
R. Waianae elementary school, Oahu
Design and construction for Phase II of the Administration Building for counseling and other administrative services.
Design $500,000
Construction $4,500,000
Total funding $5,000,000
S. Waianae public library, Oahu
Design and construction to install irrigation; paint the interior and exterior; replace the flooring; and reseal the parking lot.
Design $217,000
Construction $367,700
Total funding $584,700
2. To be expended by the department of land and natural resources:
A. Waianae small boat harbor, Oahu
Design and construction to replace piers.
Design $300,000
Construction $2,700,000
Total funding $3,000,000
B. Noholio road drainage improvements, phase 1, Oahu
Plans and design for drainage improvements to Noholio road.
Plans $125,000
Design $125,000
Total funding $250,000
C. Makaha stream berm, phase 1, Oahu
Plans and design to repair the existing Makaha stream berm.
Plans $125,000
Design $125,000
Total funding $250,000
3. To be expended by the department of transportation:
A. Replace Eku stream bridge, Makaha, Oahu
Design and construction to replace Eku stream bridge at Farrington highway crossing Eku stream.
Design $1,900,000
Construction $17,100,000
Total funding $19,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2016.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; Forty-Fourth Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the Forty-fourth Representative District.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.