Bill Text: HI HB1617 | 2022 | Regular Session | Introduced


Bill Title: Relating To Capital Improvement Projects For The Benefit Of The Thirty-first Representative District.

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced - Dead) 2022-01-26 - Referred to FIN, referral sheet 2 [HB1617 Detail]

Download: Hawaii-2022-HB1617-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

1617

THIRTY-FIRST LEGISLATURE, 2022

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirty-first REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $26,261,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the thirty-first representative district, as follows:

1.   Admiral Arthur W. Radford high school

     Plans, design, construction, and equipment for renovation of the gymnasium bathrooms and boys' and girls' locker rooms to include shower, basins, and toilets.

     Plans                          $100,000

     Design                         $100,000

     Construction                 $3,000,000

     Equipment                      $500,000

          Total funding                     $3,700,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Admiral Arthur W. Radford high school

     Plans, design, construction, and equipment for renovation and modernization of the band room to include ceiling, acoustics, bathrooms, flooring, storage, and practice rooms.

     Plans                          $100,000

     Design                         $100,000

     Construction                 $2,500,000

     Equipment                      $500,000

          Total funding                     $3,200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Aiea elementary school

     Design, construction, and equipment for campus-wide covered walkways with a solar canopy over the parking lot.

     Design                          $40,000

     Construction                 $1,570,000

     Equipment                      $300,000

          Total funding                     $1,910,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Aiea intermediate school

     Plans, land, design, construction, and equipment for a sustainable outdoor covered playcourt for physical education and learning space with weather protection.

     Plans                            $1,000

     Land                             $1,000

     Design                           $1,000

     Construction                 $2,996,000

     Equipment                        $1,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Aiea intermediate school

     Plans, land, design, construction, and equipment for a sustainable outdoor science learning space including technical infrastructure and rain and sun protection.

     Plans                            $1,000

     Land                             $1,000

     Design                           $1,000

     Construction                 $1,496,000

     Equipment                        $1,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Aiea intermediate school

     Plans, land, design, construction, and equipment for a sustainable outdoor stage, in amphitheater mode, including event technical infrastructure.

     Plans                            $1,000

     Land                             $1,000

     Design                           $1,000

     Construction                 $1,996,000

     Equipment                        $1,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Makalapa elementary school

     Design and construction for a school-wide electrical upgrade.

     Design                         $337,000

     Construction                 $1,163,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Moanalua elementary school

     Design, construction, and equipment for electrical upgrade and air conditioning improvements, ground and site improvements, equipment and appurtenances.

     Design                         $100,000

     Construction                   $400,000

     Equipment                      $100,000

          Total funding                       $600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Moanalua elementary school

     Design, construction, and equipment for a multi-purpose innovation center, ground and site improvements, equipment and appurtenances.

     Design                         $320,000

     Construction                 $2,880,000

     Equipment                       $50,000

          Total funding                     $3,250,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Moanalua high school

     Design, construction, and equipment for campus-wide telecom infrastructure upgrade.

     Design                         $175,000

     Construction                 $2,795,000

     Equipment                       $30,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Moanalua middle school

     Plans, construction, and equipment for the replacement of the existing cafeteria window louvers with double pane, tinted aluminum awning windows.

     Plans                            $6,000

     Construction                    $15,000

     Equipment                       $80,000

          Total funding                       $101,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Moanalua middle school

     Plans, design, construction, and equipment for covered playcourts between F building and portable 4/5.

     Plans                          $250,000

     Design                         $250,000

     Construction                   $500,000

     Equipment                    $1,500,000

          Total funding                     $2,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2022.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Thirty-first Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirty-first representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

feedback