Substitute Bill No. 887

    January Session, 2015

 

*_____SB00887BA____031115____*

AN ACT CONCERNING THE FILING OF A MECHANIC'S LIEN.

Be it enacted by the Senate and House of Representatives in General Assembly convened:

Section 1. Section 49-33 of the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2015):

(a) If any person, whether classified as an independent contractor or employee, has a claim for more than ten dollars (1) for materials furnished or services rendered in the construction, raising, removal or repairs of any building or any of its appurtenances or in the improvement of any lot or in the site development or subdivision of any plot of land, or (2) for any other service rendered to an owner of land, and the claim is by virtue of an agreement with or by consent of the owner of the land upon which the building is being erected or has been erected or has been moved, or by consent of the owner of the lot being improved or by consent of the owner of the plot of land being improved or subdivided, or of some person having authority from or rightfully acting for the owner in procuring the labor or materials, or by virtue of an agreement with or by consent of the owner of land for whom such other service was rendered, the building, with the land on which it stands or the lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then the plot of land, is subject to the payment of the claim.

(b) The claim is a lien on the land, building and appurtenances or lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then on the plot of land and the claim takes precedence over any other encumbrance originating after the commencement of the services, or the furnishing of any such materials, subject to apportionment as provided in section 49-36.

(c) If any such liens exist in favor of two or more persons for materials furnished or services rendered in connection with the same construction, raising, removal or repairs of any building or any of its appurtenances, or in the improvement of any lot, or in the site development or subdivision of any plot of land, or for any other service rendered to an owner of land, no one of those persons shall have any priority over another except as hereinafter provided.

(d) If any instrument constituting a valid encumbrance upon such land other than a mechanic's lien is filed for record while the building is being constructed, raised, removed or repaired, or the lot is being improved, or the plot of land is being improved or subdivided, or while any other service is being rendered to an owner of land, all such mechanic's liens originating prior to the filing of that instrument for record take precedence over that encumbrance and no such mechanic's lien shall have priority over any other such mechanic's lien. That encumbrance and all such mechanic's liens shall take precedence over any mechanic's lien which originates for materials furnished or services rendered after the filing of that instrument for record, but no one of the mechanic's liens originating after the filing of that instrument for record has precedence over another. If any lienor waives or releases his lien or claim of precedence to any such encumbrance, that lien shall be classed with and have no priority over liens originating subsequent to that encumbrance.

(e) A mechanic's lien shall not attach to any such building or its appurtenances or to the land on which the same stands or to any lot or to any plot of land, in favor of any subcontractor to a greater extent in the whole than the amount which the owner has agreed to pay to any person through whom the subcontractor claims subject to the provisions of section 49-36.

(f) Any such subcontractor shall be subrogated to the rights of the person through whom the subcontractor claims, except that the subcontractor shall have a mechanic's lien or right to claim a mechanic's lien in the event of any default by that person subject to the provisions of sections 49-34, as amended by this act, 49-35, as amended by this act, and 49-36, provided the total of such lien or liens shall not attach to any building or its appurtenances, or to the land on which the same stands or to any lot or to any plot of land, to a greater amount in the whole than the amount by which the contract price between the owner and the person through whom the subcontractor claims exceeds the reasonable cost, either estimated or actual, as the case may be, of satisfactory completion of the contract plus any damages resulting from such default for which that person might be held liable to the owner and all bona fide payments, as defined in section 49-36, made by the owner before receiving notice of such lien or liens.

(g) In the case of the removal of any building, no such mechanic's lien shall take precedence over any encumbrance upon the land to which such building has been removed which accrued before the building was removed upon the land.

(h) If any person has a claim for more than ten dollars for materials furnished or services rendered in the construction, raising, removal or repairs of any real property, and the claim is by virtue of an agreement with or by consent of the lessee of such real property or of some person having authority from or rightfully acting for such lessee in procuring the materials or labor, then the leasehold interest in such real property is subject to the payment of the claim. This subsection shall not be construed to limit any of the rights or remedies available to such person under subsection (a) of this section.

(i) Any mechanic's lien may be foreclosed in the same manner as a mortgage.

Sec. 2. Section 49-34 of the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2015):

A mechanic's lien is not valid unless the person performing the services or furnishing the materials (1) within ninety days after he has ceased to do so, lodges with the town clerk of the town in which the building, lot or plot of land is situated a certificate in writing, which shall be recorded by the town clerk with deeds of land, (A) describing the premises, the amount claimed as a lien thereon, the name or names of the person against whom the lien is being filed and the date of the commencement of the performance of services or furnishing of materials, (B) stating that the amount claimed is justly due, as nearly as the same can be ascertained, and (C) subscribed and sworn to by the claimant, [and] (2) not later than thirty days after lodging the certificate, serves a true and attested copy of the certificate upon the owner of the building, lot or plot of land in the same manner as is provided for the service of the notice in section 49-35, as amended by this act, and (3) holds the appropriate registration or license to perform the services.

Sec. 3. Section 49-35 of the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2015):

(a) No person other than the original contractor for the construction, raising, removal or repairing of the building, or the development of any lot, or the site development or subdivision of any plot of land, or for any other service rendered to an owner of land or a subcontractor whose contract with the original contractor is in writing and has been assented to in writing by the other party to the original contract, is entitled to claim any such mechanic's lien, unless, after commencing, and not later than ninety days after ceasing, to furnish materials or render services for such construction, raising, removal or repairing, such person gives written notice to the owner of the building, lot or plot of land and to the original contractor that he or she has furnished or commenced to furnish materials, or rendered or commenced to render services, and intends to claim a lien therefor on the building, lot or plot of land; provided an original contractor shall not be entitled to such notice, unless, not later than fifteen days after commencing the construction, raising, removal or repairing of the building, or the development of any lot, or the site development or subdivision of any plot of land, or any other service rendered to an owner of land, such original contractor lodges with the town clerk of the town in which the building, lot or plot of land is situated an affidavit in writing, which shall be recorded by the town clerk with deeds of land, (1) stating the name under which such original contractor conducts business, (2) stating the original contractor's business address, and (3) describing the building, lot or plot of land. The right of any person to claim a lien under this section shall not be affected by the failure of such affidavit to conform to the requirements of this section. The notice shall be served upon the owner or original contractor, if such owner or original contractor resides in the same town in which the building is being erected, raised, removed or repaired or the lot is being improved, or the plot of land is being improved or subdivided, by any indifferent person, state marshal or other proper officer, by leaving with such owner or original contractor or at such owner's or the original contractor's usual place of abode a true and attested copy thereof. If the owner or original contractor does not reside in such town, but has a known agent therein, the notice may be so served upon the agent, otherwise it may be served by any indifferent person, state marshal or other proper officer, by mailing a true and attested copy of the notice by registered or certified mail to the owner or original contractor at the place where such owner or the original contractor resides. If such copy is returned unclaimed, notice to such owner or original contractor shall be given by publication in accordance with the provisions of section 1-2. When there are two or more owners, or two or more original contractors, the notice shall be so served on each owner and on each original contractor. The notice, with the return of the person who served it endorsed thereon, shall be returned to the original maker of the notice not later than thirty days after the filing of the certificate pursuant to section 49-34, as amended by this act.

(b) No subcontractor, without a written contract complying with the provisions of this section, and no person who furnishes material or renders services by virtue of a contract with the original contractor or with any subcontractor, may be required to obtain an agreement with, or the consent of, the owner of the land, as provided in section 49-33, as amended by this act, to enable him to claim a lien under this section.

This act shall take effect as follows and shall amend the following sections:

Section 1

October 1, 2015

49-33

Sec. 2

October 1, 2015

49-34

Sec. 3

October 1, 2015

49-35

Statement of Legislative Commissioners:

In section 1(d), "to an owner of land" was added for statutory consistency.

BA

Joint Favorable Subst.

 