65964.2.
(a) A small cell shall be a permitted use subject only to a permitting process adopted by a city or county pursuant to subdivision (b) if it satisfies the following requirements:(1) The small cell is located in the public rights-of-way in any zone or in any zone that includes a commercial or industrial use.
(2) The small cell complies with all applicable federal, state, and local health and safety regulations, including the federal Americans with Disabilities Act of 1990 (42 U.S.C. Sec. 12101 et seq.).
(3) The small cell is not located
on a fire department facility.
(b) (1) A city or county may require that the small cell be approved pursuant to a building permit or its functional equivalent in connection with placement outside of the public rights-of-way or an encroachment permit or its functional equivalent issued consistent with Sections 7901 and 7901.1 of the Public Utilities Code for the placement in public rights-of-way, and any additional ministerial permits, provided that all permits are issued within the timeframes required by state and federal law.
(2) Permits issued pursuant to this subdivision may be subject to the following:
(A) The same permit requirements as for similar construction projects and applied in a
nondiscriminatory manner.
(B) A requirement to submit additional information showing that the small cell complies with the Federal Communications Commission’s regulations concerning radio frequency emissions referenced in Section 332(c)(7)(B)(iv) of Title 47 of the United States Code.
(C) A condition that the applicable permit may be rescinded if construction is not substantially commenced within one year. Absent a showing of good cause, an applicant under this section may not renew the permit or resubmit an application to develop a small cell at the same location within six months of
rescission.
(D) A condition that small cells no longer used to provide service shall be removed at no cost to the city or county.
(E) Compliance with building codes, including building code structural requirements.
(F) A condition that the applicant pay all electricity costs associated with the operation of the small cell.
(G) A condition to comply with feasible design and collocation standards on a small cell to be installed on property not in the
rights-of-way.
(3) Permits issued pursuant to this subdivision shall not be subject to:
(A) Requirements to provide additional services, directly or indirectly, including, but not limited to, in-kind contributions from the applicant such as reserving fiber, conduit, or pole space.
(B) The submission of any additional information other than that required of similar construction projects, except as specifically provided in this section.
(C) Limitations on routine maintenance or the replacement of small cells with small cells that are substantially similar, the same size or smaller.
(D) The regulation of any micro wireless facilities mounted on a span of wire.
(4) Notwithstanding any other provision of this section, a city or county shall not impose permitting requirements or fees on the installation, placement, maintenance, or replacement of micro wireless facilities that are suspended, whether embedded or attached, on cables or lines that are strung between existing utility poles in compliance with state safety codes.
(c) A city or county shall not preclude the leasing or licensing of its vertical infrastructure located in public
rights-of-way or public utility easements under the terms set forth in this subdivision. Vertical infrastructure shall be made available for the placement of small cells under fair and reasonable fees, subject to the requirements in subdivision (d), terms, and
conditions, which may include feasible design and collocation standards. A city or county may reserve capacity on vertical infrastructure if the city or county adopts a resolution finding, based on substantial evidence in the record, that the capacity is needed for projected city or county uses.
(d) (1) A city or county may charge the following fees:
(A) An annual administrative permit fee charge not to exceed two hundred fifty dollars ($250) for each small cell attached to city or county vertical infrastructure.
(B) An annual attachment rate that does not exceed an amount resulting from the following requirements:
(i) The city or county shall calculate the rate by multiplying the percentage of the total usable space that would be occupied by the attachment by the annual costs of ownership of the vertical infrastructure and its anchor, if any.
(ii) The city or county shall not levy a rate that exceeds the estimated amount required to provide use of the vertical infrastructure for which the annual recurring rate is levied. If the rate creates revenues in excess of actual costs, the city or county shall use those revenues to reduce the rate.
(iii) For purposes of this subparagraph:
(I) “Annual costs of ownership” means the annual capital costs and annual operating costs of the vertical infrastructure, which shall be the average costs of all similar vertical infrastructure owned or controlled by the city or county. The basis for the computation of annual capital costs shall be historical capital costs less depreciation. The accounting upon which the historical capital costs are determined shall include a credit for all reimbursed capital costs. Depreciation shall be based upon the average service life of the vertical infrastructure. Annual cost of ownership does not include costs for any property not necessary for use by the small cell.
(II) “Usable space” means the space above the minimum grade that can be used for the attachment of antennas and associated ancillary equipment.
(C) A one-time reimbursement fee for actual costs incurred by the city or county for rearrangements performed at the request of the small cell provider.
(2) A city or county shall comply with the following before adopting or increasing the rate described in subparagraph (B) of paragraph (1):
(A) At least 14 days before the hearing described in subparagraph (C), the city or county shall provide notice of the time and place of the meeting, including a general explanation of the matter to be considered.
(B) At least 10 days before the hearing described in subparagraph (C), the city or county shall make available to the public data indicating the cost, or
estimated cost, to make vertical structures available for use under this section if the city or county
adopts or increases the proposed rate.
(C) The city or county shall, as a part of a regularly scheduled public meeting, hold at least one open and public hearing at which time the city or county shall permit the public to make oral or written presentations relating to the rate. The city or county shall include a description of the rate in the notice and agenda of the public meeting in accordance with the Ralph M. Brown Act (Chapter 9 (commencing with Section 54950.5) of Part 1 of Division 2 of Title 5).
(D) The city or county may approve the ordinance or resolution to adopt or increase the rate at a regularly scheduled open meeting that occurs at least 30 days after the initial public meeting described in subparagraph (C).
(3) A judicial action or proceeding to attack, review, set aside, void, or annul an ordinance or resolution adopting, or increasing, a fee described in this subdivision, shall be commenced within 120 days of the effective date of the ordinance or resolution adopting or increasing the fee. A city or county or interested person shall bring an action described in this paragraph pursuant to Chapter 9 (commencing with Section 860) of Title 10 of Part 2 of the Code of Civil Procedure in a court of competent jurisdiction.
(4) This subdivision does not prohibit a wireless service provider and a city or county from mutually agreeing to an annual administrative permit fee charge
or attachment rate that is less than different from the fees or rates established above.
(e) A city or county shall not discriminate against the deployment of a small cell on property owned by the city or county and shall make space available on property not located in the public rights-of-way under terms and conditions that are no less favorable than the terms and conditions under which the space is made available for comparable commercial projects or uses. These installations shall be subject to reasonable and nondiscriminatory rates, terms, and conditions, which may include feasible design and collocation standards.
(f) This section does not alter, modify, or amend any franchise or franchise requirements under state or federal law, including Section 65964.5.
(g) For purposes of this section, the following terms have the following meanings:
(1) “Micro wireless facility” means a small cell that is no larger than 24 inches long, 15 inches in width, 12 inches in height, and that has an exterior antenna, if any, no longer than 11 inches.
(2) (A) “Small cell” means a wireless telecommunications facility, as defined in paragraph (2) of subdivision (d) of Section 65850.6, or a wireless facility that uses licensed or unlicensed spectrum and that meets the
following qualifications:
(i) The small cell antennas on the structure, excluding the associated equipment, total no more than six cubic feet in volume, whether an array or separate.
(ii) Any individual piece of associated equipment on pole structures does not exceed nine cubic feet.
(iii) The cumulative total of associated equipment on pole structures does not exceed 21 cubic feet.
(iv) The cumulative total of any ground-mounted equipment along with the associated equipment on any pole or nonpole structure does not exceed 35 cubic feet.
(v) The following types of associated ancillary equipment are not
included in the calculation of equipment volume:
(I) Electric meters and any required pedestal.
(II) Concealment elements.
(III) Any telecommunications demarcation box.
(IV) Grounding equipment.
(V) Power transfer switch.
(VI) Cutoff switch.
(VII) Vertical cable runs for the connection of power and other services.
(VIII) Equipment concealed within an existing building or structure.
(B) “Small cell” includes a micro wireless
facility.
(C) “Small cell” does not include the following:
(i) Wireline backhaul facility, which is defined to mean a facility used for the transport of communications data by wire from wireless facilities to a network.
(ii) Coaxial or fiber optic cables that are not immediately adjacent to or directly associated with a particular antenna or collocation.
(iii) Wireless facilities placed in any historic district listed in the National Park Service Certified State or Local Historic Districts or in any historical district listed on the California Register of Historical Resources or placed in coastal zones subject to the jurisdiction of the
California Coastal Commission.
(iv) The underlying vertical infrastructure.
(3) (A) “Vertical infrastructure” means all poles or similar facilities owned or controlled by a city or county that are in the public rights-of-way or public utility easements and meant for, or used in whole or in part for, communications service, electric service, lighting, traffic control, or similar functions.
(B) For purposes of this paragraph, the term “controlled” means having the right to allow subleases or sublicensing. A city or county may impose feasible design or collocation standards for small cells placed on vertical infrastructure, including the placement of associated equipment on the vertical infrastructure or the
ground.
(h) Existing agreements between a wireless service provider, or its agents and assigns, and a city, a county, or a city or county’s agents and assigns, regarding the leasing or licensing of vertical infrastructure entered into before the operative date of this section remain in effect, subject to applicable termination or other provisions in the existing agreement, or unless otherwise modified by mutual agreement of the parties. A wireless service provider may require the rates of this section for new small cells sites that are deployed after the operative date of this section in accordance with applicable change of law provisions in the existing agreements.
provisions. The operator of a small cell may accept the rates of this section for small cells that are the subject of an application submitted after the agreement is terminated pursuant to the terms of the agreement.
(i) Nothing in this section shall be construed to authorize or impose an obligation to charge a use fee different than that authorized by Part 2 (commencing with Section 9510) of Division 4.8 of the Public Utilities Code on a local publicly owned electric utility.
(j) This section does not change or remove any obligation by the owner or operator of a small cell to comply with a local publicly owned electric utility’s reasonable and feasible safety, reliability, and engineering policies.
(k) A city or county
shall consult with the utility director of a local publicly owned electric utility when adopting an ordinance or establishing permitting processes consistent with this section that impact the local publicly owned electric utility.
(l) Except as provided in subdivisions (a) and (b), nothing Nothing in this section shall be construed to modify the rules and compensation structure that have been adopted for an attachment to a utility pole owned by an electrical corporation or telephone corporation, as those terms are defined in Section 216 of the Public Utilities Code pursuant to state and federal law, including, but not limited to, decisions of the Public Utility
Utilities Commission adopting rules and a compensation structure for an attachment to a utility pole owned by an electrical corporation or telephone corporation, as those terms are defined in Section 216 of the Public Utilities Code.
(m) Nothing in this section shall be construed to modify any applicable rules adopted by the Public Utilities Commission, including General Order 95 requirements, regarding the attachment of wireless facilities to a utility pole owned by an electrical corporation or telephone corporation, as those terms are defined in Section 216 of the Public Utilities Code
(n) The Legislature finds and declares that small cells, as defined in this section, have a significant economic impact in California and are not a municipal affair as
that term is used in Section 5 of Article XI of the California Constitution, but are a matter of statewide concern.