Bill Text: TX HB5066 | 2023-2024 | 88th Legislature | Comm Sub
NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Relating to electricity service in areas of this state with a need for transmission projects.
Spectrum: Slight Partisan Bill (Republican 2-1)
Status: (Passed) 2023-06-13 - Effective immediately [HB5066 Detail]
Download: Texas-2023-HB5066-Comm_Sub.html
Bill Title: Relating to electricity service in areas of this state with a need for transmission projects.
Spectrum: Slight Partisan Bill (Republican 2-1)
Status: (Passed) 2023-06-13 - Effective immediately [HB5066 Detail]
Download: Texas-2023-HB5066-Comm_Sub.html
By: Geren (Senate Sponsor - Schwertner) | H.B. No. 5066 | |
(In the Senate - Received from the House May 8, 2023; | ||
May 9, 2023, read first time and referred to Committee on Business & | ||
Commerce; May 18, 2023, reported adversely, with favorable | ||
Committee Substitute by the following vote: Yeas 9, Nays 0; | ||
May 18, 2023, sent to printer.) | ||
COMMITTEE SUBSTITUTE FOR H.B. No. 5066 | By: Nichols |
|
||
|
||
relating to electricity service in areas of this state with a need | ||
for transmission projects. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Sections 37.056(c) and (c-1), Utilities Code, | ||
are amended to read as follows: | ||
(c) The commission shall grant each certificate on a | ||
nondiscriminatory basis after considering: | ||
(1) the adequacy of existing service; | ||
(2) the need for additional service; | ||
(3) the effect of granting the certificate on the | ||
recipient of the certificate and any electric utility serving the | ||
proximate area; and | ||
(4) other factors, such as: | ||
(A) community values; | ||
(B) recreational and park areas; | ||
(C) historical and aesthetic values; | ||
(D) environmental integrity; | ||
(E) the probable improvement of service or | ||
lowering of cost to consumers in the area if the certificate is | ||
granted, including any potential economic or reliability benefits | ||
associated with dual fuel and fuel storage capabilities in areas | ||
outside the ERCOT power region; and | ||
(F) the need for extending transmission service | ||
where existing or projected electrical loads will be underserved, | ||
including where: | ||
(i) the existing transmission service is | ||
unreasonably remote; | ||
(ii) the available capacity is unreasonably | ||
limited at transmission or distribution voltage level; or | ||
(iii) the electrical load cannot be | ||
interconnected in a timely manner [ |
||
(c-1) In considering the need for additional service under | ||
Subsection (c)(2) for a reliability transmission project that | ||
serves the ERCOT power region or under Subsection (c)(4)(F), the | ||
commission must consider the historical load, forecasted load | ||
growth, and additional load currently seeking interconnection, | ||
including load for which the electric utility has yet to sign an | ||
interconnection agreement, as determined by the electric utility | ||
with the responsibility for serving the load. | ||
SECTION 2. Section 37.057, Utilities Code, is amended to | ||
read as follows: | ||
Sec. 37.057. DEADLINE FOR APPLICATION FOR NEW TRANSMISSION | ||
FACILITY. The commission must approve or deny an application for a | ||
certificate for a new transmission facility not later than the | ||
180th day after [ |
||
is filed. If the commission does not approve or deny the | ||
application on or before that date, a party may seek a writ of | ||
mandamus in a district court of Travis County to compel the | ||
commission to decide on the application. | ||
SECTION 3. Subchapter D, Chapter 39, Utilities Code, is | ||
amended by adding Sections 39.166 and 39.167 to read as follows: | ||
Sec. 39.166. RELIABILITY PLAN FOR REGIONS WITH RAPID | ||
ELECTRICAL LOAD GROWTH. (a) The commission shall direct the | ||
independent organization certified under Section 39.151 for the | ||
ERCOT power region to: | ||
(1) identify each region in which transmission | ||
capacity is insufficient to meet the region's existing and | ||
forecasted electrical load, as reasonably determined by the | ||
certificated transmission service provider; and | ||
(2) develop a reliability plan to serve existing and | ||
forecasted electrical load in the identified region. | ||
(b) The commission shall develop a plan to implement each | ||
reliability plan adopted under Subsection (a) to ensure timely | ||
development and approval of necessary transmission service | ||
improvements. | ||
Sec. 39.167. RELIABILITY PLAN FOR PERMIAN BASIN. (a) Not | ||
later than January 30, 2024, the commission shall direct the | ||
independent organization certified under Section 39.151 for the | ||
ERCOT power region to develop a reliability plan under Section | ||
39.166 for the Permian Basin region. | ||
(b) The plan must: | ||
(1) address extending transmission service to areas | ||
where mineral resources have been found; | ||
(2) address increasing available capacity to meet | ||
forecasted load; and | ||
(3) provide available infrastructure to reduce | ||
interconnection times in areas without access to transmission | ||
service. | ||
(c) This section expires September 1, 2025. | ||
SECTION 4. The changes in law made by this Act apply only to | ||
a proceeding affecting a certificate of public convenience and | ||
necessity that commences on or after the effective date of this Act. | ||
A proceeding affecting a certificate of public convenience and | ||
necessity that commenced before the effective date of this Act is | ||
governed by the law in effect on the date the proceeding is | ||
commenced, and that law is continued in effect for that purpose. | ||
SECTION 5. This Act takes effect immediately if it receives | ||
a vote of two-thirds of all the members elected to each house, as | ||
provided by Section 39, Article III, Texas Constitution. If this | ||
Act does not receive the vote necessary for immediate effect, this | ||
Act takes effect September 1, 2023. | ||
* * * * * |