Bill Text: NY S03445 | 2009-2010 | General Assembly | Amended


Bill Title: Relates to the prompt payment of employees and contractors engaged in private construction projects.

Sponsorship: Partisan Bill (Democrat 1)

Status: (Introduced - Dead) 2010-01-06 - REFERRED TO LABOR [S03445 Detail]

Download: New_York-2009-S03445-Amended.html
                           S T A T E   O F   N E W   Y O R K
       ________________________________________________________________________
                                        3445--C
           Cal. No. 143
                              2009-2010 Regular Sessions
                                   I N  S E N A T E
                                    March 19, 2009
                                      ___________
       Introduced  by  Sen.  SAVINO -- read twice and ordered printed, and when
         printed to be  committed  to  the  Committee  on  Labor  --  committee
         discharged, bill amended, ordered reprinted as amended and recommitted
         to  said  committee -- reported favorably from said committee, ordered
         to first and second report, ordered to a third  reading,  amended  and
         ordered  reprinted,  retaining its place in the order of third reading
         -- again amended and ordered reprinted, retaining  its  place  in  the
         order of third reading
       AN ACT to amend the labor law and the general business law, in  relation
         to  the prompt payment of employees and contractors engaged in private
         construction projects
         THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND  ASSEM-
       BLY, DO ENACT AS FOLLOWS:
    1    Section  1. Section 196-a of the labor law, as added by chapter 605 of
    2  the laws of 1997, is amended to read as follows:
    3    S 196-a. Complaints by employees to commissioner.   (A) Any  employee,
    4  or  the  recognized  and certified collective bargaining agent acting on
    5  the employee's behalf,  may  file  with  the  commissioner  a  complaint
    6  regarding  a violation of THIS article [six], article nineteen, or arti-
    7  cle nineteen-A of this chapter for an investigation  of  such  complaint
    8  and  statement  setting  the  appropriate remedy, if any.  Failure of an
    9  employer to keep adequate records, in addition to exposing such employer
   10  to penalties authorized under subdivision one  of  section  two  hundred
   11  eighteen  of  this  chapter,  shall  not operate as a bar to filing of a
   12  complaint by an employee. In such a case the employer in violation shall
   13  bear the burden of proving that the complaining employee was paid wages,
   14  benefits and wage supplements.
   15    (B) ANY EMPLOYEE, OR THE RECOGNIZED AND CERTIFIED COLLECTIVE  BARGAIN-
   16  ING AGENT ACTING ON THE EMPLOYEE'S BEHALF, CONTRACTOR, OR THE RECOGNIZED
   17  AND  CERTIFIED LABOR ORGANIZATION WITH WHICH THE CONTRACTOR HAS EXECUTED
   18  A COLLECTIVE BARGAINING AGREEMENT COVERING WAGES, BENEFITS  AND  SUPPLE-
        EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
                             [ ] is old law to be omitted.
                                                                  LBD10170-11-9
       S. 3445--C                          2
    1  MENTS,  MAY FILE WITH THE COMMISSIONER A COMPLAINT REGARDING A VIOLATION
    2  OF OR THE POTENTIAL FOR THE IMMINENT VIOLATION OF THIS ARTICLE OR  ARTI-
    3  CLE  NINETEEN OF THIS CHAPTER OCCASIONED BY ANOTHER PERSON, CORPORATION,
    4  EMPLOYER OR ENTITIES IN VIOLATION OF ARTICLE THIRTY-FIVE-E OF THE GENER-
    5  AL  BUSINESS  LAW  FOR  AN INVESTIGATION OF SUCH COMPLAINT AND STATEMENT
    6  SETTING THE APPROPRIATE REMEDY, IF ANY.
    7    S 2. Subdivision 1 of section 756 of  the  general  business  law,  as
    8  added by chapter 127 of the laws of 2002, is amended to read as follows:
    9    1.  "Construction  contract" means a written or oral agreement for the
   10  construction, reconstruction, alteration, maintenance, moving or demoli-
   11  tion of any building, structure or improvement, or relating to the exca-
   12  vation of or other development or improvement to  land,  and  where  the
   13  aggregate   cost  of  the  construction  project  including  all  labor,
   14  services, materials and equipment to be  furnished,  equals  or  exceeds
   15  [two hundred fifty thousand dollars] ONE HUNDRED FIFTY THOUSAND DOLLARS.
   16  For  the  purposes  of  this  article  a construction contract shall not
   17  include any such contract made and awarded  by  the  state,  any  public
   18  department,  any  public  benefit corporation, any public corporation or
   19  official thereof, or a municipal corporation  or  official  thereof  for
   20  construction, reconstruction, alteration, repair, maintenance, moving or
   21  demolition  of any public works project nor any contract with a contrac-
   22  tor or subcontractor which is part of such project; or any such contract
   23  the purpose of which is the  construction,  reconstruction,  alteration,
   24  repair,  maintenance,  moving or demolition of an individual one, two or
   25  three family residential dwelling or a residential tract development  of
   26  one hundred [fifty] or less one or two family dwellings, or any residen-
   27  tial  construction  project  where the aggregate size of such project is
   28  [nine thousand] FOUR THOUSAND FIVE HUNDRED square feet or less,  or  any
   29  residential project of fewer than [one hundred fifty] SEVENTY-FIVE units
   30  which  receives  financial  assistance  from the federal government, the
   31  state or a municipal entity designed for households earning  an  average
   32  of  one hundred twenty-five percent of the housing and urban development
   33  agency area median income.
   34    S 3. Section 756-a of the general business law, as  added  by  chapter
   35  127 of the laws of 2002, is amended to read as follows:
   36    S  756-a. Obligations. IT IS THE POLICY AND PURPOSE OF THIS ARTICLE TO
   37  EXPEDITE PAYMENT OF ALL MONIES OWED TO  THOSE  WHO  PERFORM  CONTRACTING
   38  SERVICES   PURSUANT  TO  CONSTRUCTION  CONTRACTS.  Except  as  otherwise
   39  provided in this article, the terms and  conditions  of  a  construction
   40  contract  shall  supersede the provisions of this article and govern the
   41  conduct of the parties thereto.
   42    1. Billing cycle. The parties to a construction contract may, by mutu-
   43  al agreement, establish a billing cycle for the submission  of  invoices
   44  requesting  payment  for  work  performed  pursuant  to  a  construction
   45  contract. In the absence of an agreement by the parties as to the  bill-
   46  ing  cycle,  the  billing cycle shall be the calendar month within which
   47  the work is performed.
   48    2. Invoices. (a) A contractor shall be entitled to invoice  the  owner
   49  for interim payments at the end of the billing cycle. A contractor shall
   50  be  entitled  to  submit  a  final  invoice for payment in full upon the
   51  performance of all the contractor's obligation under the contract.
   52    (i) Upon  delivery  of  an  invoice  and  all  contractually  required
   53  documentation,  an owner shall approve or disapprove all or a portion of
   54  such invoice within twelve business days.  Owner  approval  of  invoices
   55  shall  not  be  unreasonably  withheld  nor shall an owner, in bad faith
   56  disapprove all or a portion of an  invoice.  If  an  owner  declines  to
       S. 3445--C                          3
    1  approve  an  invoice  or  a portion thereof, it must prepare and issue a
    2  written statement describing those items in the  invoice  that  are  not
    3  approved.  An  owner  may decline to approve an invoice or portion of an
    4  invoice for:
    5    (1) Unsatisfactory or disputed job progress;
    6    (2) Defective construction work or material not remedied;
    7    (3) Disputed work materials;
    8    (4)   Failure   to  comply  with  other  material  provisions  of  the
    9  construction contract;
   10    (5) Failure of the  contractor  to  make  timely  payments  for  labor
   11  including  collectively  bargained fringe benefit contributions, payroll
   12  taxes and insurance, equipment and materials, damage to  the  owner,  or
   13  reasonable  evidence  that the construction contract cannot be completed
   14  for the unpaid balance of the construction contract sum; or
   15    (6) Failure of the owner's architect to certify payment for any or all
   16  of the reasons set forth in this section so  long  as  the  reasons  are
   17  included in the owner's written statement of disapproval.
   18    (ii)  Upon  delivery  of  an  invoice  and  all contractually required
   19  documentation, a contractor or subcontractor shall approve or disapprove
   20  all or a portion of such invoice within twelve business days. Contractor
   21  and subcontractor approval of invoices shall not be  unreasonably  with-
   22  held  nor  shall a contractor or subcontractor, in bad faith, disapprove
   23  all or a portion of an invoice. Nothing in this section  shall  prohibit
   24  the contractor or subcontractor, at the time of application to the owner
   25  or  contractor,  from  withholding  such  application  to  the  owner or
   26  contractor for payment to the subcontractor or material supplier for:
   27    (1) Unsatisfactory or disputed job progress;
   28    (2) Defective construction work or material not remedied;
   29    (3) Disputed work;
   30    (4)  Failure  to  comply  with  other  material  provisions   of   the
   31  construction contract; or
   32    (5)  Failure  of  the  subcontractor to make timely payments for labor
   33  including collectively bargained fringe benefit  contributions;  payroll
   34  taxes  and  insurance,  equipment and materials, damage to contractor or
   35  another subcontractor or material supplier, or reasonable evidence  that
   36  the  subcontract  cannot  be  completed  for  the  unpaid balance of the
   37  subcontract sum.
   38    (b) Nothing in this subdivision shall authorize the withholding of  an
   39  application  to the owner or contractor for the payment to a subcontrac-
   40  tor or material supplier when due to a delay  in  job  progress  by  the
   41  owner,  contractor  or  another subcontractor or material supplier other
   42  than the applicant or applicant's subcontractor or material supplier.
   43    3. Payment. (a) The owner's payment  of  a  contractor's  interim  and
   44  final  invoices shall be made on the basis of a duly approved invoice of
   45  work performed and the material supplied during the billing cycle.
   46    (i) Unless the provisions of this article provide otherwise, the owner
   47  shall pay the contractor strictly in accordance with the  terms  of  the
   48  construction contract.
   49    (ii)  [Unless  otherwise agreed to by the parties, payment] PAYMENT of
   50  an interim or final invoice shall be due from the owner not  later  than
   51  thirty days after approval of the invoice.
   52    (iii)  If  payment  by  the  owner is contingent upon lender approval,
   53  payment of a contractor's interim or final invoice or the amount of loan
   54  proceeds disbursed by the lender for payment of the contractor's interim
   55  or final invoice shall be due from the owner seven days after receipt by
       S. 3445--C                          4
    1  the owner of good funds except where the  provisions  of  section  seven
    2  hundred fifty-six-d of this article applies.
    3    (iv) An owner may withhold from an interim payment only an amount that
    4  is sufficient to pay the costs and expenses the owner reasonably expects
    5  to  incur  in order to cure the defect or correct any items set forth in
    6  writing pursuant to subparagraph (i) of paragraph (a) of subdivision two
    7  of this section, or in the alternative, to withhold  an  amount  not  to
    8  exceed  the  line item amount appearing in the agreed schedule of values
    9  together with any change orders, additions  and/or  deletions,  if  such
   10  schedule  has  been previously submitted, and/or an amount sufficient to
   11  cover liquidated damages as established in an agreed  upon  schedule  in
   12  the construction contract.
   13    (b)  The  contractor  or  subcontractor's  payment of subcontractor or
   14  material supplier's interim or final invoice shall be made on the  basis
   15  of  a duly approved invoice of the work performed and materials supplied
   16  during the billing cycle.
   17    (i) Unless the provisions  of  this  article  provide  otherwise,  the
   18  contractor  or  subcontractor  shall  pay  the subcontractor strictly in
   19  accordance with the terms of the construction contract. Performance by a
   20  subcontractor in accordance with the provisions of  its  contract  shall
   21  entitle  it to payment from the party with which it contracts.  Notwith-
   22  standing this article, where a contractor  enters  into  a  construction
   23  contract  with  a  subcontractor  as  agent  for  a disclosed owner, the
   24  payment obligation shall flow directly from the disclosed owner as prin-
   25  cipal to the subcontractor and through the agent.
   26    (ii) When  a  subcontractor  has  performed  in  accordance  with  the
   27  provisions of its construction contract, the contractor shall pay to the
   28  subcontractor,  and  each subcontractor shall in turn pay to its subcon-
   29  tractors, the full or proportionate amount of funds  received  from  the
   30  owner  for  each  subcontractor's  work  and  materials based on work or
   31  services provided under the  construction  contract,  seven  days  after
   32  receipt  of  good  funds for each interim or final payment, provided all
   33  contractually required documentation and waivers are received.
   34    (iii) A contractor or subcontractor may withhold amounts received from
   35  an owner in connection with an interim payment due to a subcontractor or
   36  material supplier only such sums that are sufficient to pay  the  direct
   37  expenses  as  are reasonable to correct deficiencies identified pursuant
   38  to subparagraph (ii)  of  paragraph  (a)  of  subdivision  two  of  this
   39  section,  or in the alternative, to withhold an amount not to exceed the
   40  line item amount appearing in the agreed schedule  of  values,  together
   41  with any change order, additions or deletions, if such schedule has been
   42  previously  submitted[,  and/or an amount sufficient to cover liquidated
   43  damages as established in an agreed upon schedule  in  the  construction
   44  contract].
   45    (iv)  If a contractor, after submitting an invoice to an owner under a
   46  construction contract, but before making a payment to a subcontractor or
   47  material  supplier  for  the  subcontractor's  or  material   supplier's
   48  performance  covered by such invoice, discovers that all or a portion of
   49  the payment otherwise due to the subcontractor or material  supplier  is
   50  subject  to  withholding  from the subcontractor or material supplier in
   51  accordance with the construction contract and the conditions  set  forth
   52  in  subparagraph  (ii)  of  paragraph  (a)  of  subdivision  two of this
   53  section, then the contractor shall:
   54    (1) As soon as practicable upon ascertaining the cause giving rise  to
   55  a withholding, but prior to the due date for a subcontractor or material
   56  supplier  payment, furnish to the subcontractor or material supplier and
       S. 3445--C                          5
    1  the owner written notice of withholding specifying conditions for  with-
    2  holding payment and identifying the amount to be withheld;
    3    (2)  Reduce the subcontractor's or material supplier's interim payment
    4  by an amount not to exceed the amount specified in the notice  of  with-
    5  holding; and
    6    (3) Pay the subcontractor or material supplier amounts withheld within
    7  seven  days after correction of the identified subcontractor or material
    8  supplier performance deficiency and receipt of all  required  documenta-
    9  tion and waivers, unless the funds [therefore] THEREFOR must be obtained
   10  from the owner's next interim payment due to a reduction in the contrac-
   11  tor's  billing  directly  resulting from the subcontractor's or material
   12  supplier's performance deficiency identified in the notice of  withhold-
   13  ing.
   14    (c)  A  written notice of any withholding under this subdivision shall
   15  be issued to a subcontractor or material supplier specifying:
   16    (i) The amount to be withheld;
   17    (ii) The specific causes  for  withholding  under  the  terms  of  the
   18  construction contract and pursuant to this subdivision;
   19    (iii)  The remedial actions necessary to be taken by the subcontractor
   20  or material supplier in order to receive payments of the  amounts  with-
   21  held; and
   22    (iv) The documentation and waivers required.
   23    4.  Notice.  A contractor or subcontractor shall disclose to a subcon-
   24  tractor, at the time the construction subcontract is entered  into,  the
   25  due date for receipt of payments to the contractor or subcontractor from
   26  the  owner  or  the  contractor  as  the case may be. If a contractor or
   27  subcontractor fails to accurately disclose the due date to a subcontrac-
   28  tor, the contractor or subcontractor  shall  be  obligated  to  pay  the
   29  subcontractor  as  though  the due dates established in paragraph (a) of
   30  subdivision three of this section were met by the  owner.  In  addition,
   31  upon  written request of a subcontractor, the owner shall provide notice
   32  to such subcontractor within five days of making any  interim  or  final
   33  payment  to  the contractor. The subcontractor's request shall remain in
   34  effect for the duration of the subcontractor's work on the project.
   35    S 4.  Section 756-b of the general business law, as added  by  chapter
   36  127 of the laws of 2002, is amended to read as follows:
   37    S  756-b.  Remedies.  1.  (a)  If  any  interim  or final payment to a
   38  contractor is delayed beyond the due date established in  paragraph  (a)
   39  of  subdivision three of section seven hundred fifty-six-a of this arti-
   40  cle, the owner shall pay the contractor interest beginning on  the  next
   41  day  at  the rate of one percent per month or fraction of a month on the
   42  unpaid balance, or at a higher rate  consistent  with  the  construction
   43  contract.
   44    (b)  Notwithstanding  any  contrary agreement, if any interim or final
   45  payment to a subcontractor is delayed beyond the due date established in
   46  paragraph (b) of subdivision three of section seven hundred  fifty-six-a
   47  of  this  article  the contractor or subcontractor shall pay its subcon-
   48  tractor interest, beginning on the next day, at the rate of one  percent
   49  a  month  or  fraction  of a month on the unpaid balance, or at a higher
   50  rate consistent with the construction contract.
   51    2. (a) (i) If an owner fails to approve or disapprove an invoice with-
   52  in the time limits established in subparagraph (i) of paragraph  (a)  of
   53  subdivision two of section seven hundred fifty-six-a of this article, or
   54  to  pay  the  contractor  the  undisputed invoice amount within the time
   55  limits provided by paragraph (a) of subdivision three of  section  seven
   56  hundred fifty-six-a of this article, the contractor may suspend contrac-
       S. 3445--C                          6
    1  tually  required  performance,  only  after  providing the owner written
    2  notice and an opportunity to cure consistent with subparagraph  (ii)  of
    3  this paragraph.
    4    (ii) A contractor intending to suspend performance on the construction
    5  contract  for  failure of the owner to make timely payments or approvals
    6  within the time limits provided by this article must provide  the  owner
    7  written  notice  at  least  ten  calendar  days  before the contractor's
    8  intended suspension. Such notice shall:
    9    (A) inform the owner that payment for undisputed invoice amounts  have
   10  not been received; and
   11    (B)  state  the  intent  of  the contractor to suspend performance for
   12  non-payment.
   13  If after the tenth calendar day following written notice the  owner  has
   14  not cured the deficiency, the contractor may suspend performance.
   15    (iii)  A  contractor shall not be deemed in breach of the construction
   16  contract for suspending performance pursuant to this section.
   17    (b)(i) A subcontractor may suspend contractually required  performance
   18  if any or all of the occurrences outlined in clauses (A), (B) and (C) of
   19  this  subparagraph  occur and only after providing written notice and an
   20  opportunity to cure consistent with subparagraph (ii) of this paragraph:
   21    (A) If an owner fails to make timely payments for undisputed  invoices
   22  within the time limits established by subdivision three of section seven
   23  hundred fifty-six-a of this article for the subcontractor's work and the
   24  contractor also fails to pay the subcontractor for the approved work;
   25    (B) If an owner pays the contractor within the time limits established
   26  by  subdivision three of section seven hundred fifty-six-a of this arti-
   27  cle for undisputed invoices for work performed by the subcontractor  but
   28  the  contractor  fails  to  make payment to the subcontractor within the
   29  time frames established by this article for the subcontractor's work;
   30    (C) If an owner fails to approve or disapprove a portion  of  contrac-
   31  tor's  invoice  for  work performed by the subcontractor within the time
   32  limits established in paragraph (a) of subdivision two of section  seven
   33  hundred fifty-six-a of this article;
   34    (D)  If a contractor or subcontractor fails to approve or disapprove a
   35  subcontractor's invoice within the time limits established in  paragraph
   36  (b)  of  subdivision  three of section seven hundred fifty-six-a of this
   37  article; or
   38    (E) If an owner fails to approve portions of the contractors'  billing
   39  for  work  performed  by the subcontractor within the time limits estab-
   40  lished by this article and the reasons for  such  failure  are  not  the
   41  fault of or directly related to the subcontractor's work.
   42    (ii)  A  subcontractor intending to suspend performance for failure to
   43  receive timely payments within the time limits established  pursuant  to
   44  this  article  must  provide  both  the owner and the contractor written
   45  notice at least ten calendar days before  the  subcontractor's  intended
   46  suspension. Such notice shall:
   47    (A)  inform  the  owner and the contractor that payment for undisputed
   48  billing amounts have not been received; and
   49    (B) state the intent of the  contractor  to  suspend  performance  for
   50  non-payment.
   51    If  after  the  tenth calendar day following written notice either the
   52  owner or the contractor has not cured the deficiency, the  subcontractor
   53  may  suspend  performance  AND/OR  ATTEMPT TO RESOLVE IN COMPLIANCE WITH
   54  SUBDIVISION THREE OF THIS SECTION.
       S. 3445--C                          7
    1    (iii)  A  subcontractor  shall  not  be  deemed  in  breach   of   the
    2  construction  contract  for  suspending  performance  pursuant  to  this
    3  section.
    4    (iv)  (A)  A  contractor or subcontractor that suspends performance as
    5  provided in this section shall not be required to furnish further labor,
    6  materials or services until the contractor or subcontractor is paid  the
    7  undisputed  invoice amount at the time period for completion as provided
    8  in the construction contract, OR A FINAL DETERMINATION HAS BEEN MADE  IN
    9  COMPLIANCE  WITH  SUBDIVISION  THREE  OF THIS SECTION AND COMPLIED WITH.
   10  All of the time frames established within [the construction contract  of
   11  a  contractor  or  subcontractor] THIS SECTION shall be extended for the
   12  length of time performance was suspended. Payment of  documented  actual
   13  costs  incurred  for  re-mobilization resulting from suspension shall be
   14  negotiated between the parties.
   15    (B) In the event of suspension of a construction contract, as provided
   16  in this article, all materials, equipment, tools, construction equipment
   17  and machinery located at the job site shall remain the sole  and  exclu-
   18  sive  property  of  the contractor or subcontractor and shall be removed
   19  from the job site, if necessary, within a  reasonable  period  of  time.
   20  Access  to  the  contractor's  or  subcontractor's property shall not be
   21  unreasonably withheld.
   22    3.  (A) UPON RECEIPT OF WRITTEN NOTICE OF  A  COMPLAINT  (I)  THAT  AN
   23  OWNER  HAS VIOLATED THE PROVISIONS OF THIS ARTICLE; (II) THAT A CONTRAC-
   24  TOR HAS VIOLATED THE PROVISIONS OF THIS ARTICLE; (III) WHERE A  CONTRAC-
   25  TOR ALLEGES A SUBCONTRACTOR HAS VIOLATED THE PROVISIONS OF THIS ARTICLE;
   26  (IV)  WHERE  A  SUBCONTRACTOR  ALLEGES  A  CONTRACTOR  HAS  VIOLATED THE
   27  PROVISIONS OF THIS ARTICLE;  (V)  WHERE  A  SUBCONTRACTOR  ALLEGES  THAT
   28  ANOTHER  SUBCONTRACTOR HAS VIOLATED THE PROVISIONS OF THIS ARTICLE; (VI)
   29  WHERE A CONTRACTOR OR SUBCONTRACTOR  ALLEGES  A  MATERIAL  SUPPLIER  HAS
   30  VIOLATED  THE  PROVISIONS  OF  THIS  ARTICLE;  OR (VII) WHERE A MATERIAL
   31  SUPPLIER  ALLEGES  A  CONTRACTOR  OR  SUBCONTRACTOR  HAS  VIOLATED   THE
   32  PROVISIONS  OF  THIS  ARTICLE;  THE PARTIES SHALL ATTEMPT TO RESOLVE THE
   33  MATTER GIVING RISE TO SUCH COMPLAINT.
   34    (B) THE WRITTEN NOTICE REQUIRED UNDER THIS SECTION SHALL BE  DELIVERED
   35  AT  OR SENT BY ANY MEANS THAT PROVIDES WRITTEN, THIRD-PARTY VERIFICATION
   36  OF DELIVERY TO THE LAST BUSINESS  ADDRESS  KNOWN  TO  THE  PARTY  GIVING
   37  NOTICE.
   38    (C)  IF  EFFORTS  TO  RESOLVE  SUCH  MATTER TO THE SATISFACTION OF ALL
   39  PARTIES ARE UNSUCCESSFUL, THE AGGRIEVED PARTY MAY REFER THE MATTER,  NOT
   40  LESS  THAN  FIFTEEN  DAYS  OF THE RECEIPT OF THIRD PARTY VERIFICATION OF
   41  DELIVERY OF THE COMPLAINT, TO THE AMERICAN ARBITRATION  ASSOCIATION  FOR
   42  AN  EXPEDITED  ARBITRATION  PURSUANT  TO THE RULES OF THE AMERICAN ARBI-
   43  TRATION ASSOCIATION.
   44    (D) UPON CONCLUSION OF THE  ARBITRATION  PROCEEDINGS,  THE  ARBITRATOR
   45  SHALL  SUBMIT  TO THE PARTIES HIS OR HER OPINION AND AWARD REGARDING THE
   46  ALLEGED VIOLATION.
   47    (E) THE AWARD OF THE ARBITRATOR SHALL BE FINAL AND MAY ONLY BE VACATED
   48  OR MODIFIED AS PROVIDED IN ARTICLE SEVENTY-FIVE OF  THE  CIVIL  PRACTICE
   49  LAW  AND  RULES  UPON  AN  APPLICATION  MADE WITHIN THE TIME PROVIDED BY
   50  SECTION SEVENTY-FIVE HUNDRED TWO OF THE CIVIL PRACTICE LAW AND RULES.
   51    S 5. Section 757 of the general business law is amended by adding  two
   52  new subdivisions 3 and 4 to read as follows:
   53    3. A PROVISION, COVENANT, CLAUSE OR UNDERSTANDING IN, COLLATERAL TO OR
   54  AFFECTING  A CONSTRUCTION CONTRACT STATING THAT EXPEDITED ARBITRATION AS
   55  EXPRESSLY PROVIDED FOR AND IN THE MANNER ESTABLISHED  BY  SECTION  SEVEN
       S. 3445--C                          8
    1  HUNDRED  FIFTY-SIX-B  OF  THIS  ARTICLE  IS  UNAVAILABLE  TO ONE OR BOTH
    2  PARTIES.
    3    4.  A PROVISION, COVENANT, CLAUSE OR UNDERSTANDING IN COLLATERAL TO OR
    4  AFFECTING A CONSTRUCTION CONTRACT ESTABLISHING PAYMENT PROVISIONS  WHICH
    5  DIFFER  FROM  THOSE  ESTABLISHED  IN  SUBDIVISION THREE OF SECTION SEVEN
    6  HUNDRED FIFTY-SIX-A AND SECTION SEVEN HUNDRED FIFTY-SIX-B AS APPLICABLE.
    7    S 6. This act  shall  take  effect  immediately  and  shall  apply  to
    8  construction  contracts  entered  into  after  such  date,  except those
    9  contracts entered into as part of a construction  project  for  which  a
   10  permit  or  permits have been issued and work has begun on such projects
   11  prior to the effective date of this act.