Bill Text: NJ A4217 | 2012-2013 | Regular Session | Introduced


Bill Title: Permits contractor in certain construction contracts with State college to choose between a retainage deduction from monthly progress payments or depositing a bond; allows 2% retainage deduction of amount due on each partial payment.

Spectrum: Slight Partisan Bill (Republican 3-1)

Status: (Introduced - Dead) 2013-06-24 - Substituted by S2737 [A4217 Detail]

Download: New_Jersey-2012-A4217-Introduced.html

ASSEMBLY, No. 4217

STATE OF NEW JERSEY

215th LEGISLATURE

INTRODUCED JUNE 10, 2013

 


 

Sponsored by:

Assemblyman  LOUIS D. GREENWALD

District 6 (Burlington and Camden)

Assemblyman  DAVID P. RIBLE

District 30 (Monmouth and Ocean)

 

 

 

 

SYNOPSIS

     Permits contractor in certain construction contracts with State college to choose between a retainage deduction from monthly progress payments or depositing a bond; allows 2% retainage deduction of amount due on each partial payment.

 

CURRENT VERSION OF TEXT

     As introduced.

 


An Act concerning contracting by State colleges and supplementing P.L.1986, c.43 (C.18A:64-52 et seq.).

 

     Be It Enacted by the Senate and General Assembly of the State of New Jersey:

 

     1.    Whenever any contract, the total price of which exceeds $100,000, entered into by a State college, for the construction, reconstruction, alteration or repair of any building, structure, facility or other improvement to real property, requires the withholding of payment of a percentage of the amount of the contract, the contractor may agree to the withholding of payments in the manner prescribed in the contract, or may deposit with the State college registered book bonds, entry municipal bonds, State bonds or other appropriate bonds of the State of New Jersey, or negotiable bearer bonds or notes of any political subdivision of the State, the value of which is equal to the amount necessary to satisfy the amount that otherwise would be withheld pursuant to the terms of the contract.  The nature and amount of the bonds or notes to be deposited shall be subject to approval by the State college. For purposes of this section, "value" shall mean par value or current market value, whichever is lower.

     If the contractor agrees to the withholding of payments, the amount withheld shall be deposited, with a banking institution or savings and loan association insured by an agency of the Federal government, in an account bearing interest at the rate currently paid by such institutions or associations on time or savings deposits. The amount withheld, or the bonds or notes deposited, and any interest accruing on such bonds or notes, shall be returned to the contractor upon fulfillment of the terms of the contract relating to such withholding.  Any interest accruing on cash payments withheld shall be credited to the State college.

 

     2.    Any contract, the total price of which exceeds $100,000, entered into by a State college involving the construction, reconstruction, alteration, repair or maintenance of any building, structure, facility or other improvement to real property, shall provide for partial payments to be made at least once each month as the work progresses, unless the contractor shall agree to deposit bonds with the State college pursuant to section 1 of P.L.      , c.   (C.    ) (pending before the Legislature as this bill).

 

     3.    a. With respect to any contract entered into by a State college pursuant to section 2 of P.L.   , c.    (C.    ) (pending before the Legislature as this bill) for which the contractor shall agree to the withholding of payments pursuant to section 1 of P.L.    , c.    (C.    ) (pending before the Legislature as this bill), 2% of the amount due on each partial payment shall be withheld by the State college pending completion of the contract.

     b.    Upon acceptance of the work performed pursuant to the contract for which the contractor has agreed to the withholding of payments pursuant to subsection a. of this section, all amounts being withheld by the State college shall be released and paid in full to the contractor within 45 days of the final acceptance date agreed upon by the contractor and the State college, without further withholding of any amounts for any purpose whatsoever, provided that the contract has been completed as indicated.  If the State college requires maintenance security after acceptance of the work performed pursuant to the contract, such security shall be obtained in the form of a maintenance bond.  The maintenance bond shall be no longer than two years and shall be no more than 100% of the project costs.

 

     4.    This act shall take effect immediately.

 

 

STATEMENT

 

     This bill supplements the "State College Contracts Law," P.L.1986, c.43 (C.18A:64-52 et seq.), and applies to any State college contract for over $100,000 which involves the construction, reconstruction, alteration or repair of any building, structure, facility or other improvement to real property.  Under the provisions of this bill, whenever a contract of this type requires the withholding of payment of a percentage of the amount of the contract, the contractor would have the choice of either agreeing to a retainage deduction from each monthly progress payment, or the contractor could choose to deposit bonds in the amount necessary to satisfy the amount that otherwise would be withheld under the contract.  If a contractor chooses a retainage deduction from each monthly payment, then the retainage would be limited to 2% of the amount due on each partial payment.

     Upon acceptance of the work performed pursuant to the contract for which the contractor has agreed to a retainage deduction, all amounts being withheld by the State college must be paid in full to the contractor within 45 days of the final acceptance date agreed upon by the contractor and the State college.  The bill provides that if the State college requires maintenance security after acceptance of the work performed under the contract, the security must be obtained in the form of a maintenance bond, which is required to be no longer than two years and no more than 100% of the project costs.


     The provisions of this bill are similar to provisions in the "Local Public Contracts Law," P.L.1971, c.198 (C.40A:11-1 et seq.) and the "Public  School Contracts Law," P.L.1977, c.114 (C.18A:18A-1 et seq.).