HB 535-FN - AS INTRODUCED
2025 SESSION
25-0873
09/08
HOUSE BILL 535-FN
AN ACT relative to defining the role of the public utilities commission.
SPONSORS: Rep. Cormen, Graf. 15; Sen. Watters, Dist 4
COMMITTEE: Science, Technology and Energy
-----------------------------------------------------------------
ANALYSIS
This bill clarifies and eliminates certain grants of authority to the public utilities commission, and requires, in any contested case before the commission to which the department of energy and the office of the consumer advocate are parties, the commission to approve by order any settlement agreement to which all parties are a signatory, unless the commission determines after hearing that any settlement provision is contrary to law.
This bill is at the request of the office of the consumer advocate.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Explanation: Matter added to current law appears in bold italics.
Matter removed from current law appears [in brackets and struckthrough.]
Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.
25-0873
09/08
STATE OF NEW HAMPSHIRE
In the Year of Our Lord Two Thousand Twenty Five
AN ACT relative to defining the role of the public utilities commission.
Be it Enacted by the Senate and House of Representatives in General Court convened:
1 Findings. The general court finds that:
I. Pursuant to RSA 363:17-a, the public utilities commission plays a critical role in the regulation of the state’s electric, natural gas, and water service by serving as the neutral arbiter between the interests of utility customers and utility shareholders, and discharging that role effectively requires the commission to conduct its proceedings in a manner similar to that employed by a civil court.
II. When the general court established the department of energy via chapter 91 of the 2021 New Hampshire Laws, the general court transferred policymaking and investigative functions to the department so as to allow the public utilities commission to discharge its adjudicative responsibilities fully and fairly without being encumbered by duties that might conflict with or undermine the commission’s neutrality.
III. In light of ambiguities in the 2021 legislation, there has been confusion and uncertainty about the respective roles of the department of energy and the public utilities commission, which has increased the cost and complexity of utility regulation in a manner that does not serve the public interest.
IV. With respect to contested proceedings before the public utilities commission, when there is agreement among any participating utilities, the consumer advocate responsible for representing the interests of residential ratepayers pursuant to RSA 363:28, the department in its capacity as the state’s energy policymaker, and other parties, it is in the public interest for such proceedings to be resolved in a timely manner that reflects such consensus.
V. Therefore, to assure the continued provision of utility service to homes and businesses in the state at rates that are just and reasonable and on terms that promote reliability and affordability, it is necessary to clarify the role of the public utilities commission so as to eliminate authority that overlaps with that of the department of energy, and to encourage the swift resolution of contested proceedings before the commission by settlement.
2 The Public Utilities Commission; Commission; Term. Amend RSA 363:1 to read as follows:
363:1 Commission; Term.
I. There shall be a public utilities commission, which shall be an independent agency administratively attached to the department of energy pursuant to RSA 21-G:10. The chair of the commission shall have the powers and duties set forth in RSA 21-G:9. The commission shall be composed of 3 commissioners who shall be full-time employees and who shall engage in no other gainful employment during their terms as members. Their term of office shall be for 6 years. Of the 3 commissioners, one shall be an attorney and a member of the New Hampshire Bar and one shall have either background or experience or both in one or more of the following: engineering, economics, accounting or finance.
II. The authority of the commission shall consist of conducting contested adjudicative proceedings within the meaning of RSA 541-A:31 on matters concerning the rates, charges, tariffs, and services provided by public utilities as defined in RSA 362:2 and others as specifically authorized under this title, and to adopt administrative rules consistent with its authority as provided in this title.
3 Complaints to the Department of Energy and Proceedings Before the Commission; Inspection. Amend RSA 365:6 to read as follows:
365:6 Inspection. [Both the commission and] The department of energy may at any time personally, or by its experts or agents, inspect the property, works, system, plant, devices, appliances and methods used by any public utility, or its books, papers and records.
4 Complaints to the Department of Energy and Proceedings Before the Commission; Authority to Inspect. Amend RSA 365:7 to read as follows:
365:7 Authority to Inspect. Any expert or agent of the department of energy [or the commission], who shall make a demand on behalf of the commission or the department to be allowed to inspect as provided in RSA 365:6, shall produce written authority to make such inspection signed by [the chairperson of the commission or] the commissioner of the department of energy.
5 New Section; Proceedings Before the Commission; Settlement of Contested Cases. Amend RSA 365 by inserting after section 20 the following new section:
365:20-a Settlements. In any contested case before the commission to which the department of energy and the office of the consumer advocate are parties, the commission, in a timely manner, shall approve by order any settlement agreement to which all parties are a signatory, unless the commission determines after hearing that any settlement provision is contrary to law.
6 Supervisory Power of Department of Energy and Public Utilities Commission; Extent of Power. Amend RSA 374:3 to read as follows:
374:3 Extent of Power. The [public utilities commission and] department of energy shall have the general supervision of all public utilities and the plants owned, operated or controlled by the same so far as necessary to carry into effect the provisions of this title.
7 Supervisory Power of Department of Energy and Public Utilities Commission; Duty to Keep Informed. Amend RSA 374:4 to read as follows:
374:4 Duty to Keep Informed. The [commission and the] department of energy shall have power, and it shall be [their] its duty, to keep informed as to all public utilities in the state, their capitalization, franchises and the manner in which the lines and property controlled or operated by them are managed and operated, not only with respect to the safety, adequacy and accommodation offered by their service, but also with respect to their compliance with all provisions of law, orders of the commission and charter requirements. It shall further be the duty of the department of energy to petition the commission for appropriate relief through the means of RSA 365:41-44, RSA 374:41, or other appropriate action when the department reasonably believes that a public utility is failing to discharge its obligations pursuant to this title.
8 Supervisory Power of Department of Energy and Public Utilities Commission; Additions and Improvements. Amend RSA 374:5 to read as follows:
374:5 Additions and Improvements. For the purpose of enabling [the commission and] the department of energy to perform [their] its duty to keep informed as provided in RSA 374:4, every public utility, before making any addition, extension, or capital improvement to its fixed property in this state, except under emergency conditions, shall report to [the commission and] the department of energy the probable cost of such addition, extension, or capital improvement whenever the probable cost thereof exceeds a reasonable amount to be prescribed by general or special order of the commission. For this purpose, the commission may classify public utilities according to the amount of their respective fixed capital accounts, and prescribe a reasonable limitation for each such classification. In no case shall the minimum amount prescribed be less than 1/4 of one percent of such fixed capital account as of December 31 of the preceding year, or $10,000, whichever is the smaller amount. Reports shall be filed in writing within such reasonable time as may be prescribed by the [commission] department before starting actual construction on any addition, extension, or improvement. Upon petition by the department, the commission shall [have discretion to] exclude the cost of any such addition, extension, or capital improvement from the rate base of said utility [where] upon a finding that such written report thereof shall not have been filed in advance as herein provided.
9 Supervisory Power of Department of Energy and Public Utilities Commission; Investigation of Other Utilities; Orders. Amend RSA 374:7 to read as follows:
374:7 Investigation of Other Utilities; Orders. The [commission and the] department of energy shall have power to investigate and ascertain, from time to time, the quality of gas supplied by public utilities and the methods employed by public utilities in manufacturing, transmitting or supplying gas or electricity for light, heat or power, or in transmitting telephone and telegraph messages, or supplying water, and, after notice and hearing thereon, and upon petition of the department, the commission shall have power to order all reasonable and just improvements and extensions in service or methods.
10 Public Utilities; Production of Books, Etc. Amend RSA 374:18 to read as follows:
374:18 Production of Books, Etc. The [commission, by order, or the] department of energy[,] may require any public utility to produce within the state, at such time and place as it may designate, any accounts, records, memoranda, books, or papers kept in any office or place without the state, or verified copies thereof, in order that an examination thereof may be made by or under the direction of [the commission or] the department of energy.
11 Repeal. RSA 365:19, relative to investigations by the commission, is repealed.
12 Effective Date. This act shall take effect 60 days after its passage.
25-0873
1/9/25
HB 535-FN- FISCAL NOTE
AS INTRODUCED
AN ACT relative to defining the role of the public utilities commission.
FISCAL IMPACT:
The Office of Legislative Budget Assistant is unable to complete a fiscal note for this bill as it is awaiting information from Department of Energy. The Department was contacted on 12/26/24 for a fiscal note worksheet. When completed, the fiscal note will be forwarded to the House Clerk's Office.
AGENCIES CONTACTED:
Department of Energy, Public Utilities Commission, and Office of Consumer Advocate