Bill Text: HI HB1370 | 2018 | Regular Session | Introduced


Bill Title: Relating To Capital Improvement Projects For The Benefit Of The Thirty-sixth Representative District.

Spectrum: Partisan Bill (Republican 1-0)

Status: (Introduced - Dead) 2017-11-30 - Carried over to 2018 Regular Session. [HB1370 Detail]

Download: Hawaii-2018-HB1370-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

1370

TWENTY-NINTH LEGISLATURE, 2017

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE THIRTY-SIXTH REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of _____ or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2017-2018 for the purpose of capital improvement projects for the thirty-sixth representative district, as follows:

I.   To be expended by the department of education:

     1. Kipapa Elementary School, Oahu

          A. Design and construction for the renovation of the cafeteria stage.

             Design                        $50,000

             Construction             $400,000

                   Total funding      $450,000

          B. Design and construction for the stage lighting.

              Design                  $40,000

              Construction            $180,000

                   Total funding      $220,000

          C. Design and construction for air conditioning for buildings I, A, D, H, and L, and for the portables.

              Design                  $1,000

              Construction            $799,000

                   Total funding      $800,000

     2. Mililani High School, Oahu

          A. Plans, design, and construction to resurface back and side driveways.

              Design                  $90,000

              Construction            $350,000

                   Total funding      $440,000

          B. Design and construction for renovation of the boys and girls bathrooms.

              Design                  $60,000

              Construction            $200,000

                   Total funding      $260,000

          C. Design and construction to replace the fence at the back of the school.

              Design                  $15,000

              Construction            $70,000

                   Total funding      $85,000

          D. Design and construction to reroof building W.

              Design                  $23,000

              Construction            $80,000

                   Total funding      $103,000

          E. Design and construction to reroof building C.

              Design                  $65,000

              Construction            $263,000

                   Total funding      $328,000

          F. Design and construction B RPL book lockers

              Design                  $20,000

              Construction            $95,000

                   Total funding      $115,000

          G. Design and construction for R kitchen electrical improvements.

              Design                  $12,000

              Construction            $50,000

                   Total funding      $62,000

          H. Design and construction to reroof buildings F and G.

              Design                  $65,000

              Construction            $263,000

                   Total funding      $328,000

          I. Design and construction for classroom ceiling fans.

              Design                  $120,000

              Construction            $500,000

                   Total funding      $620,000

          J. Design and construction to replace gym bleachers for building E.

              Design                  $1,000

              Construction            $32,800

                   Total funding      $33,800

          K. Design and construction for fire alarm upgrades.

              Design                  $1,000

              Construction            $299,000

                   Total funding      $300,000

          L. Design and construction of a new auditorium.

              Design                  $1,000,000

              Construction            $29,000,000

.                  Total funding      $30,000,000

     3. Mililani Ike Elementary School, Oahu

          A. Design and construction of a new bell and PA system, and external speakers for the Oval.

              Design                  $75,000

               Construction            $250,000

                   Total funding      $325,000

     4. Mililani Mauka Elementary School, Oahu

          A. Plans, design, and construction to resurface parking lot.

              Plans                   $1,000

              Design                  $1,000

              Construction            $698,000

                   Total funding      $700,000

     5. Mililani Waena Elementary School, Oahu

          A. Design and construction to widen the driveway between the main parking lot and cafeteria parking lot.

              Design                  $1,000

              Construction            $749,000

                   Total funding      $750,000

          B. Design and construction for a covered walkway next to the parking lot.

              Design                  $1,000

              Construction            $149,000

                   Total funding      $150,000

          C. Design and construction for a covered walkway next to the driveway.

              Design                  $1,000

              Construction            $149,000

                   Total funding      $150,000

          D. Design and construction for a covered lanai between the administration building and the library.

              Design                  $1,000

              Construction            $299,000

                   Total funding      $300,000

          E. Design and construction for a covered lanai between the library and the cafeteria.

              Design                  $1,000

              Construction            $299,000

                   Total funding      $300,000

          F. Design and construction for additional classroom and learning space on the second floor of the library.

              Design                  $1,000

              Construction            $499,000

                   Total funding      $500,000

          G. Design and construction for air conditioning for D-building.

              Design                  $1,000

              Construction            $499,000

                   Total funding      $500,000

     6. Mililani Middle School, Oahu

              Design                  $500,000

              Construction            $13,000,000

                   Total funding      $13,500,000

II. To be expended by the department of transportation:

     1. H-2 Freeway, Oahu

          A. Plans, design, and construction for additional lane and double-loop on-ramp southbound from Mililani Mauka with pedestrian overpass; ground and site improvements; equipment and appurtenances.

              Plans                   $100,000

              Design                  $100,000

              Construction            $14,800,000

                   Total funding      $15,000,000

     SECTION 2.  The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended by the designed expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2017.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

Capital Improvement Projects for the Benefit of the Thirty-Sixth Representative District; CIP

 

Description:

Appropriates funds for capital improvement projects for the benefit of the 36th Representative District.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

 

feedback