Bill Text: CT HB07158 | 2017 | General Assembly | Comm Sub
Bill Title: An Act Concerning Authorization Of State Grant Commitments For School Building Projects.
Sponsorship: Committee Bill
Status: (Introduced - Dead) 2017-04-12 - File Number 547 [HB07158 Detail]
Download: Connecticut-2017-HB07158-Comm_Sub.html
General Assembly |
Raised Bill No. 7158 | ||
January Session, 2017 |
LCO No. 4215 | ||
*_____HB07158ED____032717____* | |||
Referred to Committee on EDUCATION |
|||
Introduced by: |
|||
(ED) |
|||
AN ACT CONCERNING AUTHORIZATION OF STATE GRANT COMMITMENTS FOR SCHOOL BUILDING PROJECTS.
Be it enacted by the Senate and House of Representatives in General Assembly convened:
Section 1. (Effective from passage) The Commissioner of Administrative Services, having reviewed applications for state grants for public school building projects in accordance with section 10-283 of the general statutes on the basis of priorities for such projects and standards for school construction established by the State Board of Education, and having prepared a listing of all such eligible projects ranked in order of priority, including a separate schedule of previously authorized projects which have changed substantially in scope or cost, as determined by said commissioner together with the amount of the estimated grant with respect to each eligible project, and having submitted such listing of eligible projects, prior to December 15, 2016, to a committee of the General Assembly established under section 10-283a of the general statutes for the purpose of reviewing such listing, is hereby authorized to enter into grant commitments on behalf of the state in accordance with said section 10-283 with respect to the priority listing of such projects and in such estimated amounts as approved by said committee prior to February 1, 2017, as follows:
(1) Estimated Grant Commitments.
T1 |
School District |
Estimated |
Estimated |
T2 |
School |
Project Costs |
Grant |
T3 |
Project Number |
||
T4 |
|||
T5 |
BRANFORD |
||
T6 |
Francis Walsh Intermediate School |
||
T7 |
014-0034 EA |
$85,933,000 |
$30,385,909 |
T8 |
|||
T9 |
FAIRFIELD |
||
T10 |
Stratfield School |
||
T11 |
051-0131 A |
$36,793 |
$9,592 |
T12 |
|||
T13 |
FAIRFIELD |
||
T14 |
North Stratfield School |
||
T15 |
051-0132 A |
$41,410 |
$10,796 |
T16 |
|||
T17 |
FAIRFIELD |
||
T18 |
Riverfield School |
||
T19 |
051-0133 A |
$48,970 |
$12,766 |
T20 |
|||
T21 |
FAIRFIELD |
||
T22 |
Jennings School |
||
T23 |
051-0134 A |
$55,639 |
$14,505 |
T24 |
|||
T25 |
FAIRFIELD |
||
T26 |
Tomlinson Middle School |
||
T27 |
051-0135 A |
$46,403 |
$12,097 |
T28 |
|||
T29 |
FAIRFIELD |
||
T30 |
Fairfield Woods Middle School |
||
T31 |
051-0136 A |
$86,168 |
$22,464 |
T32 |
|||
T33 |
FAIRFIELD |
||
T34 |
Sherman School |
||
T35 |
051-0137 A |
$30,394 |
$7,708 |
T36 |
|||
T37 |
FAIRFIELD |
||
T38 |
Osborn Hill School |
||
T39 |
051-0138 A |
$72,704 |
$18,438 |
T40 |
|||
T41 |
FAIRFIELD |
||
T42 |
Dwight Elementary School |
||
T43 |
051-0139 A |
$62,275 |
$15,793 |
T44 |
|||
T45 |
FAIRFIELD |
||
T46 |
McKinley Elementary School |
||
T47 |
051-0140 A |
$69,666 |
$17,667 |
T48 |
|||
T49 |
FAIRFIELD |
||
T50 |
Mill Hill School |
||
T51 |
051-0141 A |
$87,550 |
$22,203 |
T52 |
|||
T53 |
FAIRFIELD |
||
T54 |
Burr Elementary School |
||
T55 |
051-0142 A |
$133,776 |
$33,926 |
T56 |
|||
T57 |
FAIRFIELD |
||
T58 |
Roger Ludlowe Middle School |
||
T59 |
051-0143 A |
$171,640 |
$43,528 |
T60 |
|||
T61 |
GREENWICH |
||
T62 |
New Lebanon School |
||
T63 |
057-0112 DV/N |
$37,309,000 |
$29,847,200 |
T64 |
|||
T65 |
HAMDEN |
||
T66 |
West Woods Elementary School |
||
T67 |
062-0097 N |
$26,180,000 |
$15,147,748 |
T68 |
|||
T69 |
LEDYARD |
||
T70 |
Ledyard Middle School* |
||
T71 |
072-0090 RNV/EA |
$35,652,092 |
$22,410,905 |
T72 |
|||
T73 |
NEW BRITAIN |
||
T74 |
Smalley Academy |
||
T75 |
089-0168 EA/RR |
$53,000,000 |
$42,023,700 |
T76 |
|||
T77 |
NEW CANAAN |
||
T78 |
Saxe Middle School |
||
T79 |
090-0048 EA/CV |
$18,600,000 |
$3,786,960 |
T80 |
|||
T81 |
NEW LONDON |
||
T82 |
New London High School-South Campus* |
||
T83 |
095-0091 MAG/A |
$49,462,274 |
$39,569,819 |
T84 |
|||
T85 |
NORTH STONINGTON |
||
T86 |
Wheeler High School |
||
T87 |
102-0024 EA/RR |
$23,820,500 |
$10,974,104 |
T88 |
|||
T89 |
NORTH STONINGTON |
||
T90 |
North Stonington Elementary School |
||
T91 |
102-0025 EA/RR |
$14,207,500 |
$8,879,688 |
T92 |
|||
T93 |
WEST HARTFORD |
||
T94 |
Hall High School |
||
T95 |
155-0240 EA |
$12,800,000 |
$5,393,920 |
T96 |
|||
T97 |
REGIONAL DISTRICT 1 |
||
T98 |
Housatonic Valley Regional High School |
||
T99 |
201-0045 A/CV |
$4,255,856 |
$1,930,456 |
T100 |
|||
T101 |
REGIONAL DISTRICT 12 |
||
T102 |
Shepaug Valley Regional Agriscience STEM |
||
T103 |
212-0026 VA/N |
$29,957,408 |
$23,965,926 |
T104 |
|||
T105 |
GROTON |
||
T106 |
Cutler Elementary School (Carl C. Cutler Middle School) |
||
T107 |
059-0188 EA/RR |
$45,850,000 |
$26,363,750 |
T108 |
|||
T109 |
GROTON |
||
T110 |
Westside Elementary School (West Side Middle School) |
||
T111 |
059-0189 EA/RR |
$48,480,000 |
$27,876,000 |
T112 |
|||
T113 |
GROTON |
||
T114 |
Consolidated Middle School |
||
T115 |
059-0190 N/PS |
$90,090,000 |
$42,792,750 |
T116 |
|||
T117 |
HAMDEN |
||
T118 |
Shepherd Glen School |
||
T119 |
062-0098 EA/RR |
$27,665,000 |
$18,773,469 |
T120 |
|||
T121 |
KILLINGLY |
||
T122 |
Killingly High School (Vo-Ag) |
||
T123 |
069-0062 VE |
$123,000 |
$98,400 |
T124 |
|||
T125 |
LEDYARD |
||
T126 |
Gallup Hill School* |
||
T127 |
072-0091 RNV/EA |
$28,612,104 |
$17,985,569 |
T128 |
|||
T129 |
MANCHESTER |
||
T130 |
Verplanck School* |
||
T131 |
077-0235 EA/RR |
$29,172,000 |
$19,691,100 |
T132 |
|||
T133 |
NEWINGTON |
||
T134 |
John Wallace Middle School |
||
T135 |
094-0106 A |
$1,300,000 |
$742,820 |
T136 |
|||
T137 |
ROCKY HILL |
||
T138 |
Rocky Hill Intermediate School |
||
T139 |
119-0052 N |
$48,345,097 |
$16,577,534 |
T140 |
|||
T141 |
SHELTON |
||
T142 |
Long Hill School |
||
T143 |
126-0086 A |
$382,060 |
$150,111 |
T144 |
|||
T145 |
SHELTON |
||
T146 |
Elizabeth Shelton School |
||
T147 |
126-0087 A |
$280,620 |
$110,256 |
T148 |
|||
T149 |
SHELTON |
||
T150 |
Mohegan School |
||
T151 |
126-0088 A |
$280,620 |
$110,256 |
T152 |
|||
T153 |
SIMSBURY |
||
T154 |
Henry James Memorial School |
||
T155 |
128-0108 A/CV |
$2,465,000 |
$818,627 |
T156 |
|||
T157 |
WATERBURY |
||
T158 |
Wendell L. Cross School |
||
T159 |
151-0295 EA/RR |
$46,213,083 |
$36,309,619 |
T160 |
|||
T161 |
REGIONAL DISTRICT 12 |
||
T162 |
Shepaug Valley High School* |
||
T163 |
212-0025 A/EC |
$2,914,565 |
$957,726 |
T164 |
|||
T165 |
REGIONAL DISTRICT 14 |
||
T166 |
Nonnewaug High School (Vo-Ag)* |
||
T167 |
214-0094 VA/EA |
$662,000 |
$529,600 |
T168 |
|||
T169 |
REGIONAL DISTRICT 14 |
||
T170 |
Nonnewaug High School (Vo-Ag)* |
||
T171 |
214-0095 VE |
$587,568 |
$470,054 |
T172 |
|||
T173 |
BRANFORD |
||
T174 |
Central Administration (Francis Walsh Intermediate School) |
||
T175 |
014-0035 BE/EA |
$2,267,000 |
$400,806 |
T176 |
|||
T177 |
GUILFORD |
||
T178 |
A. Baldwin Middle School |
||
T179 |
060-0102 EC |
$2,351,115 |
$713,799 |
T180 |
|||
T181 |
MILFORD |
||
T182 |
Harborside Middle School |
||
T183 |
084-0195 EC |
$1,347,745 |
$683,441 |
T184 |
|||
T185 |
NORWALK |
||
T186 |
West Rocks Middle School |
||
T187 |
103-0244 EC |
$1,400,000 |
$455,000 |
T188 |
|||
T189 |
WATERBURY |
||
T190 |
Gilmartin School |
||
T191 |
151-0294 EC |
$432,893 |
$340,124 |
T192 |
|||
T193 |
WEST HAVEN |
||
T194 |
May V. Carrigan Middle School |
||
T195 |
156-0139 EC |
$3,354,815 |
$2,576,162 |
T196 |
|||
T197 |
REGIONAL DISTRICT 14 |
||
T198 |
Region 14 Central Office (Nonnewaug High School) |
||
T199 |
214-0096 BE/A/CV |
$1,609,535 |
$385,162 |
(2) Previously Authorized Projects That Have Changed Substantially in Scope or Cost which are Seeking Reauthorization.
T200 |
School District |
Authorized |
Requested |
T201 |
School |
||
T202 |
Project Number |
||
T203 |
|||
T204 |
FAIRFIELD |
||
T205 |
Fairfield Ludlowe High School |
||
T206 |
051-0127 EA/EC/RR |
||
T207 |
|||
T208 |
Estimated… |
||
T209 |
Total Project Costs |
$11,630,700 |
$15,537,674 |
T210 |
Total Grant |
$3,073,994 |
$4,106,607 |
T211 |
|||
T212 |
HARTFORD |
||
T213 |
West Middle School |
||
T214 |
064-0303 EA/RR |
||
T215 |
|||
T216 |
Estimated… |
||
T217 |
Total Project Costs |
$54,600,000 |
$54,600,000 |
T218 |
Total Grant |
$43,680,000 |
$43,680,000 |
T219 |
|||
T220 |
NEW FAIRFIELD |
||
T221 |
New Fairfield Middle/High School |
||
T222 |
091-0041 A/CV |
||
T223 |
|||
T224 |
Estimated… |
||
T225 |
Total Project Costs |
$378,000 |
$443,641 |
T226 |
Total Grant |
$132,300 |
$155,274 |
This act shall take effect as follows and shall amend the following sections: | ||
Section 1 |
from passage |
New section |
ED |
Joint Favorable |