Bill Text: VA HB576 | 2020 | Regular Session | Chaptered
Bill Title: Undergrounding electric transmission lines; pilot program.
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Passed) 2020-03-04 - Governor: Acts of Assembly Chapter text (CHAP0164) [HB576 Detail]
Download: Virginia-2020-HB576-Chaptered.html
Be it enacted by the General Assembly of Virginia:
1. That §56-585.1:5 of the Code of Virginia is amended and reenacted as follows:
§56-585.1:5. Pilot program for underground transmission lines.
A. There is hereby established a pilot program to further the
understanding of underground electric transmission lines in regard to electric
reliability, construction methods and related cost and timeline estimating,
and the probability of meeting such projections, and the benefits of
undergrounding existing electric transmission lines to promote economic
development within the Commonwealth. The pilot program shall consist of the
approval to construct qualifying electrical transmission lines of 230 kilovolts
or less (but greater than 69 kilovolts) in whole or in part underground. Such
pilot program shall consist of a total of two qualifying electrical
transmission line projects, constructed in whole or in part underground, as
specified and set forth in this section.
B. Notwithstanding any other law to the contrary, as a part of the pilot program established pursuant to this section, the Commission shall approve as a qualifying project a transmission line of 230 kilovolts or less that is pending final approval of a certificate of public convenience and necessity from the Commission as of December 31, 2017, for the construction of an electrical transmission line approximately 5.3 miles in length utilizing both overhead and underground transmission facilities, of which the underground portion shall be approximately 3.1 miles in length, which has been previously proposed for construction within or immediately adjacent to the right-of-way of an interstate highway. Once the Commission has affirmed the project need through an order, the project shall be constructed in part underground, and the underground portion shall consist of a double circuit.
The Commission shall approve such underground construction
within 30 days of receipt of the written request of the public utility to
participate in the pilot program pursuant to this subsection section.
The Commission shall not require the submission of additional technical and
cost analyses as a condition of its approval but may request such analyses for
its review. The Commission shall approve the underground construction of one
contiguous segment of the transmission line that is approximately 3.1 miles in
length that was previously proposed for construction within or immediately
adjacent to the right-of-way of the interstate highway, for which, by
resolution, the locality has indicated general community support. The remainder
of the construction for the transmission line shall be aboveground. The
Commission shall not be required to perform any further analysis as to the
impacts of this route, including environmental impacts or impacts upon
historical resources.
The electric utility may proceed to acquire right-of-way and take such other actions as it deems appropriate in furtherance of the construction of the approved transmission line, including acquiring the cables necessary for the underground installation.
C. In reviewing applications submitted by public utilities for
certificates of public convenience and necessity for the construction of
electrical transmission lines of 230 kilovolts or less filed between July 1,
2018, and July October 1, 2020, the Commission shall approve,
consistent with the requirements of subsection D, one additional application as
a qualifying project to be constructed in whole or in part underground, as a
part of this pilot program. The one qualifying project shall be in addition to
the qualifying project described in subsection B and shall be the relocation
or conversion of an existing 230-kilovolt overhead line to an underground line.
D. For purposes of subsection C, a project shall be qualified
to be placed underground, in whole or in part, if it meets all of the following
criteria: (i) an engineering analysis demonstrates that it is technically
feasible to place the proposed line, in whole or in part, underground; (ii) the
governing body of each locality in which a portion of the proposed line will be
placed underground indicates, by resolution, general community support for the
project and that it supports the transmission line to be placed underground;
(iii) a project has been filed with the Commission or is pending issuance of a
certificate of public convenience and necessity by July October
1, 2020; (iv) the estimated additional cost of placing the proposed line, in
whole or in part, underground does not exceed $40 million or, if greater
than $40 million, the cost does not exceed 2.5 times the cost of placing
the same line overhead, assuming accepted industry standards for undergrounding
to ensure safety and reliability; if the public utility, the affected
localities, and the Commission agree, a proposed underground line whose cost
exceeds 2.5 times the cost of placing the line overhead may also be accepted
into the pilot program; (v) the public utility requests that the project be
considered as a qualifying project under this section; and (vi) the primary
need of the project shall be for purposes of grid reliability, grid resiliency,
or to support economic development priorities of the Commonwealth, including
the economic development priorities and the comprehensive plan of the governing
body of the locality in which at least a portion of line will be placed,
and shall not be to address aging assets that would have otherwise been
replaced in due course.
E. A transmission line project that is found to meet the criteria of subsection D shall be deemed to satisfy the requirements of subsection B of §56-46.1 with respect to a finding of the Commission that the line is needed.
F. Approval of a transmission line pursuant to this section for inclusion in the pilot program shall be deemed to satisfy the requirements of §15.2-2232 and local zoning ordinances with respect to such transmission line and any associated facilities, such as stations, substations, transition stations and locations, and switchyards or stations, that may be required.
F. G. The Commission shall report annually to
the Commission on Electric Utility Restructuring, the Joint Commission on
Technology and Science, and the Governor on the progress of the pilot program
by no later than December 1 of each year that this section is in effect. The
Commission shall submit a final report to the Commission on Electric Utility
Restructuring, the Joint Commission on Technology and Science, and the Governor
no later than December 1, 2024, analyzing the entire program and making
recommendations about the continued placement of transmission lines underground
in the Commonwealth. The Commission's final report shall include, but not be
limited to, analysis and findings of the costs of underground construction
and historical and future consumer rate effects of such costs, effect of
underground transmission lines on grid reliability, operability (including
operating voltage), probability of meeting cost and construction timeline
estimates of such underground transmission lines, and economic development,
aesthetic or other benefits attendant to the placement of transmission lines
underground.
G. H. For the qualifying projects chosen
pursuant to this section and not fully recoverable as charges for new
transmission facilities pursuant to subdivision A 4 of §56-585.1, the
Commission shall approve a rate adjustment clause. The rate adjustment clause
shall provide for the full and timely recovery of any portion of the cost of
such project not recoverable under applicable rates, terms, and conditions
approved by the Federal Energy Regulatory Commission and shall include the use
of the fair return on common equity most recently approved in a State
Corporation Commission proceeding for such utility. Such costs shall be
entirely assigned to the utility's Virginia jurisdictional customers. The
Commission's final order regarding any petition filed pursuant to this
subsection shall be entered not more than three months after the filing of such
petition.
H. I. The provisions of this section shall not
be construed to limit the ability of the Commission to approve additional
applications for placement of transmission lines underground.
I. J. If two applications are not submitted to
the Commission that meet the requirements of this section, the Commission shall
document the failure of the projects to qualify for the pilot program in order
to justify approving fewer than two projects to be placed underground, in whole
or in part.
J. K. Insofar as the provisions of this section
are inconsistent with the provisions of any other law or local ordinance, the
provisions of this section shall be controlling.