Bill Text: TX SB1503 | 2019-2020 | 86th Legislature | Introduced
Bill Title: Relating to civil works projects and other construction projects of governmental entities.
Spectrum: Bipartisan Bill
Status: (Introduced - Dead) 2019-03-14 - Referred to Business & Commerce [SB1503 Detail]
Download: Texas-2019-SB1503-Introduced.html
86R10900 SRA-F | ||
By: Zaffirini, Paxton | S.B. No. 1503 |
|
||
|
||
relating to civil works projects and other construction projects of | ||
governmental entities. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Subchapter B, Chapter 2269, Government Code, is | ||
amended by adding Section 2269.0525 to read as follows: | ||
Sec. 2269.0525. PREQUALIFICATION PROCESS FOR CIVIL WORKS | ||
PROJECTS. (a) In this section, "civil works project" has the | ||
meaning assigned by Section 2269.351. | ||
(b) A governmental entity may implement a prequalification | ||
process to eliminate unqualified offerors from consideration for a | ||
civil works project under a competitive bidding method authorized | ||
by this chapter. A governmental entity that implements a | ||
prequalification process under this section shall advertise or | ||
publish notice of the prequalification process along with a request | ||
for qualifications 30 days before the invitation for bids is issued | ||
in a manner prescribed by law. In addition, the governmental entity | ||
may directly solicit qualifications from potential offerors if the | ||
competitive requirements of this chapter and other applicable law | ||
are followed. | ||
(c) If a governmental entity considers a contract for a | ||
civil works project using competitive bidding under this chapter, | ||
in implementing a prequalification process under Subsection (b), | ||
the governmental entity: | ||
(1) may not rank potential offerors; and | ||
(2) shall determine if any potential offerors meet | ||
minimum qualification requirements for completing the civil works | ||
project, including meeting any requirements related to an | ||
experience modification rate for workers' compensation insurance | ||
premiums that the governmental entity will allow without additional | ||
information and actions taken to prevent future incidents. | ||
(d) A governmental entity may consider the following | ||
factors during the prequalification process: | ||
(1) the potential offeror's experience with other | ||
construction projects of similar size and scope; | ||
(2) the potential offeror's commercial and financial | ||
history and stability; | ||
(3) the potential offeror's ability to self-perform | ||
the construction project services; | ||
(4) the potential offeror's familiarity and experience | ||
with subcontractors and suppliers in the area served by the | ||
governmental entity; | ||
(5) whether the potential offeror has been involved in | ||
litigation or arbitration with a governmental entity related to a | ||
construction project during the preceding five years; | ||
(6) the potential offeror's ability and capacity to | ||
provide performance and payment bonds; | ||
(7) whether the potential offeror has ever failed to | ||
complete a project for a governmental entity; | ||
(8) the qualifications and experience of the potential | ||
offeror's management or project team; and | ||
(9) the potential offeror's safety record for the | ||
previous three years. | ||
(e) If a potential offeror has been involved in litigation | ||
or arbitration as described by Subsection (d)(5), the potential | ||
offeror shall provide to the governmental entity the name of the | ||
parties involved and a brief description of the nature and outcome | ||
of the litigation or arbitration. | ||
SECTION 2. Section 2269.056(b), Government Code, is amended | ||
to read as follows: | ||
(b) The governmental entity shall base its selection among | ||
offerors on applicable criteria listed for the particular method | ||
used. The governmental entity shall publish in the request for | ||
proposals or qualifications: | ||
(1) the criteria that will be used to evaluate the | ||
offerors; | ||
(2) the applicable weighted value for each criterion; | ||
and | ||
(3) [ |
||
scoring each criterion. | ||
SECTION 3. Subchapter B, Chapter 2269, Government Code, is | ||
amended by adding Section 2269.060 to read as follows: | ||
Sec. 2269.060. EXPLANATION OF EVALUATION AND RANKING. (a) | ||
An offeror who submits a bid, proposal, or response to a request for | ||
qualifications for a construction contract under this chapter may, | ||
after the contract is awarded, make a request in writing to the | ||
governmental entity to provide an explanation of its evaluation of | ||
the offeror's submission. | ||
(b) Not later than the 30th day after the date a request is | ||
made under Subsection (a), the governmental entity shall deliver to | ||
the offeror a written explanation of or grant the offeror an | ||
interview with a representative of the selection team regarding its | ||
evaluation of the submission including, if applicable, its ranking | ||
of the submission. | ||
SECTION 4. Section 2269.103, Government Code, is amended to | ||
read as follows: | ||
Sec. 2269.103. PREPARATION OF REQUEST. (a) The | ||
governmental entity shall prepare a request for competitive bids | ||
that includes construction documents, estimated budget, project | ||
scope, estimated project completion date, and other information | ||
that a contractor may require to submit a bid. | ||
(b) For civil works projects, before preparing a request for | ||
competitive bids under Subsection (a), a governmental entity may | ||
use the prequalification process for civil works projects described | ||
by Section 2269.0525. | ||
SECTION 5. Section 2269.153, Government Code, is amended to | ||
read as follows: | ||
Sec. 2269.153. PREPARATION OF REQUEST. (a) The | ||
governmental entity shall prepare a request for competitive sealed | ||
proposals that includes construction documents, selection criteria | ||
and the weighted value for each criterion, estimated budget, | ||
project scope, estimated project completion date, and other | ||
information that a contractor may require to respond to the | ||
request. | ||
(b) For civil works projects, the weighted value assigned to | ||
price must be at least 50 percent of the total weighted value of all | ||
selection criteria. | ||
SECTION 6. Section 2269.155, Government Code, is amended by | ||
adding Subsection (d) to read as follows: | ||
(d) Not later than the seventh business day after the date | ||
the contract is awarded, the governmental entity shall document the | ||
basis of its selection and shall make the evaluations public. | ||
SECTION 7. Section 2269.452(a), Government Code, is amended | ||
to read as follows: | ||
(a) This chapter may be enforced through an action for | ||
declaratory or injunctive relief filed not later than the 15th | ||
[ |
||
SECTION 8. The change in law made by this Act applies only | ||
to a contract for which a governmental entity first advertises or | ||
otherwise solicits bids, proposals, offers, or qualifications or | ||
makes a similar solicitation on or after the effective date of this | ||
Act. A contract for which a governmental entity first advertises or | ||
otherwise solicits bids, proposals, offers, or qualifications or | ||
makes a similar solicitation before the effective date of this Act | ||
is governed by the law in effect on the date the advertisement or | ||
solicitation is made, and that law is continued in effect for that | ||
purpose. | ||
SECTION 9. This Act takes effect September 1, 2019. |