Bill Text: TX SB1283 | 2021-2022 | 87th Legislature | Introduced
Bill Title: Relating to attachments for broadband service on utility poles owned by an electric cooperative.
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced - Dead) 2021-03-18 - Referred to Transportation [SB1283 Detail]
Download: Texas-2021-SB1283-Introduced.html
87R8812 BRG-F | ||
By: Hancock | S.B. No. 1283 |
|
||
|
||
relating to attachments for broadband service on utility poles | ||
owned by an electric cooperative. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. The heading to Chapter 252, Utilities Code, is | ||
amended to read as follows: | ||
CHAPTER 252. CABLE ATTACHMENTS TO ELECTRIC COOPERATIVE'S | ||
DISTRIBUTION POLES | ||
SECTION 2. Title 5, Utilities Code, is amended by adding | ||
Chapter 253 to read as follows: | ||
CHAPTER 253. BROADBAND ATTACHMENTS TO ELECTRIC COOPERATIVE'S | ||
DISTRIBUTION POLES | ||
SUBCHAPTER A. GENERAL PROVISIONS | ||
Sec. 253.0001. DEFINITIONS. In this chapter: | ||
(1) "Broadband provider" means an entity that provides | ||
broadband service either directly or through an affiliate that uses | ||
the entity's communications facilities, regardless of whether the | ||
entity: | ||
(A) provides additional services in addition to | ||
broadband service; or | ||
(B) uses its facilities in whole or in part to | ||
provide broadband service. | ||
(2) "Broadband service" means Internet service with | ||
the capability of providing: | ||
(A) a download speed of 25 megabits per second or | ||
faster; and | ||
(B) an upload speed of three megabits per second | ||
or faster. | ||
(3) "Communications space" means the lower usable | ||
space on a pole that is typically reserved for low-voltage | ||
communications equipment. | ||
(4) "Large order application" means an application | ||
submitted by a broadband provider under this subchapter requesting | ||
access to attach pole attachments to a number of poles: | ||
(A) that exceeds the lesser of 300 poles or a | ||
number equal to 0.5 percent of the electric cooperative's poles; | ||
and | ||
(B) that is not more than the lesser of 3,000 | ||
poles or a number equal to five percent of the electric | ||
cooperative's poles. | ||
(5) "Pole" has the meaning assigned by Section | ||
252.001. | ||
(6) "Pole attachment" means an affixture of cables, | ||
strands, wires, and associated equipment used in the provision of a | ||
broadband provider's services attached to a pole directly or | ||
indirectly or placed in a right-of-way owned or controlled by an | ||
electric cooperative. | ||
(7) "Simple make-ready activities" means work to | ||
accommodate a new pole attachment on a pole and includes work where | ||
existing attachments in the communications space are moved without | ||
any reasonable expectation of: | ||
(A) service outage or facility damage; | ||
(B) a need to splice an existing communications | ||
attachment; or | ||
(C) a need to relocate an existing wireless | ||
attachment. | ||
Sec. 253.0002. APPLICABILITY AND CONSTRUCTION OF CHAPTER. | ||
(a) This chapter applies to a pole attachment affixed by a | ||
broadband provider to a pole owned and controlled by an electric | ||
cooperative. This chapter does not apply to a pole attachment | ||
regulated by the Federal Communications Commission under 47 U.S.C. | ||
Section 224. | ||
(b) This chapter does not abrogate or affect a right or | ||
obligation of a party to a pole attachment contract entered into by | ||
a broadband provider and an electric cooperative before September | ||
1, 2021. | ||
(c) A broadband provider that attaches a pole attachment to | ||
a pole owned by an electric cooperative under the terms of this | ||
chapter is subject to Sections 252.006, 252.007, and 252.008 in the | ||
same manner as if the broadband provider were a cable operator. | ||
(d) This chapter does not limit a right of a party to a pole | ||
attachment contract to request modification, amendment, or renewal | ||
of such contract to conform it to the provisions of this chapter. | ||
Sec. 253.0003. NO STATE CERTIFICATION; NO REGULATORY | ||
AUTHORITY. (a) This chapter does not constitute state | ||
certification under 47 U.S.C. Section 224. If a court determines | ||
that this chapter constitutes certification under that section, | ||
this chapter is not enforceable and has no effect. | ||
(b) This chapter may not be construed to subject an electric | ||
cooperative to regulation by the Federal Communications Commission | ||
under 47 U.S.C. Section 224. | ||
(c) This chapter does not authorize a department, agency, or | ||
political subdivision of this state to exercise enforcement or | ||
regulatory authority over attachments to electric cooperative | ||
poles. | ||
Sec. 253.0004. CONSTRUCTION OF TERMS AND PHRASES. | ||
Technical terms and phrases in this chapter, other than those | ||
defined by Section 253.0001, shall be construed using the term's or | ||
phrase's usual and customary meanings in the electric and broadband | ||
industries. | ||
Sec. 253.0005. COST-BASED NON-RECURRING CHARGES. | ||
Non-recurring charges authorized by this chapter must be | ||
cost-based. | ||
SUBCHAPTER B. APPLICATION FOR ACCESS TO POLES | ||
Sec. 253.0101. APPLICATION FOR POLE ACCESS. (a) A | ||
broadband provider may not access a pole owned by an electric | ||
cooperative for the purpose of placing a pole attachment unless the | ||
provider applies for that access in accordance with this | ||
subchapter. | ||
(b) An electric cooperative shall: | ||
(1) establish a timeline for a broadband provider to | ||
apply for and obtain access to poles for placing a pole attachment | ||
under this chapter; and | ||
(2) make available an explanation of the information | ||
reasonably required for an application for access to poles for | ||
placing a pole attachment under this chapter to be considered | ||
complete. | ||
Sec. 253.0102. REVIEW OF APPLICATION FOR COMPLETENESS. (a) | ||
An electric cooperative shall review an application for | ||
completeness before the cooperative reviews the application on the | ||
merits. | ||
(b) An electric cooperative shall notify an applicant | ||
whether an application is complete not later than: | ||
(1) the 10th business day after the date the | ||
cooperative receives the application; | ||
(2) the 25th business day after the date the | ||
cooperative receives a large order application; | ||
(3) the fifth business day after the date the | ||
cooperative receives a resubmitted application; or | ||
(4) the 20th business day after the date the | ||
cooperative receives a resubmitted large order application. | ||
Sec. 253.0103. TREATMENT OF MULTIPLE APPLICATIONS BY SAME | ||
APPLICANT. For purposes of this chapter, an electric cooperative | ||
may treat as a single application for pole access an application the | ||
cooperative receives from the same applicant before the 31st day | ||
after the cooperative receives that applicant's most recent | ||
previous application. | ||
Sec. 253.0104. GRANT OR DENIAL OF APPLICATION. (a) Except | ||
as provided by Sections 253.0204 and 253.0302, an electric | ||
cooperative shall grant or deny an application for pole access | ||
under this chapter and provide to the applicant a survey of the | ||
poles affected by the application not later than: | ||
(1) the 45th day after the date the cooperative | ||
receives a complete application; or | ||
(2) the 60th day after the date the cooperative | ||
receives a complete large order application. | ||
(b) An electric cooperative may deny an application for | ||
access to a pole under this chapter if: | ||
(1) generally applicable safety, reliability, or | ||
engineering requirements established for the protection of public | ||
health, safety, or welfare prevent granting access; or | ||
(2) the pole lacks sufficient capacity. | ||
(c) Notwithstanding Subsection (b)(1), an electric | ||
cooperative may not deny access to a pole if the capacity, safety, | ||
reliability, or engineering consideration may be remedied by | ||
rearranging, expanding, replacing, or otherwise safely | ||
reengineering the pole or pole attachments through make-ready | ||
activities. | ||
(d) An electric cooperative's denial of an application to | ||
access a pole under this chapter must: | ||
(1) be specific; | ||
(2) include all relevant evidence and information that | ||
supports the denial; and | ||
(3) explain how the evidence and information relate to | ||
the denial. | ||
Sec. 253.0105. DEADLINES NOT APPLICABLE TO CERTAIN | ||
APPLICATIONS. (a) An electric cooperative is not required to meet | ||
the deadlines under this subchapter for an application for pole | ||
access to place pole attachments on more than 3,000 poles or more | ||
than 5 percent of the electric cooperative's poles. | ||
(b) An electric cooperative may not act under Subsection (a) | ||
to delay an application unreasonably and shall negotiate in good | ||
faith with the applicant regarding the time required to fulfill the | ||
cooperative's duties. | ||
SUBCHAPTER C. MAKE-READY ACTIVITIES | ||
Sec. 253.0201. DEADLINES FOR MAKE-READY ACTIVITIES. (a) | ||
Not later than the 15th day after the date an electric cooperative | ||
grants an application, the electric cooperative shall provide to | ||
the broadband provider a detailed and itemized estimate of the | ||
expected costs of all necessary make-ready activities. | ||
(b) An electric cooperative shall complete all make-ready | ||
activities in the communications space and send a detailed, | ||
itemized final invoice to the broadband provider not later than: | ||
(1) the 30th day after the date the electric | ||
cooperative receives payment of the estimated make-ready cost from | ||
the broadband provider; or | ||
(2) for a large order application, the 75th day after | ||
the date the electric cooperative receives payment of the estimated | ||
make-ready cost from the broadband provider. | ||
(c) An electric cooperative shall complete all make-ready | ||
activities above the communications space, including pole | ||
replacements, and send a detailed, itemized final invoice to the | ||
broadband provider not later than: | ||
(1) the 90th day after the date the electric | ||
cooperative receives payment of the estimated make-ready cost from | ||
the broadband provider; or | ||
(2) for a large order application, the 135th day after | ||
the date the electric cooperative receives payment of the estimated | ||
make-ready cost from the broadband provider. | ||
Sec. 253.0202. EXTENSION OF MAKE-READY ACTIVITIES | ||
DEADLINE. (a) An electric cooperative may extend a deadline under | ||
Section 253.0201(b) or (c) for a cause that renders the deadline | ||
infeasible. A cooperative that chooses to extend a deadline shall: | ||
(1) immediately and in writing notify the broadband | ||
provider and each person with an affected existing pole attachment | ||
about the delay; and | ||
(2) identify the affected poles and provide a detailed | ||
explanation of the reason for the delay and an estimated new | ||
completion date to the broadband provider and each person with an | ||
affected existing pole attachment. | ||
(b) An electric cooperative may not extend a deadline under | ||
this section for a period longer than is necessary to complete | ||
make-ready activities on affected poles. | ||
(c) An electric cooperative may not extend a deadline under | ||
this section because of a preexisting violation on an affected pole | ||
caused by a person other than the broadband provider. The | ||
cooperative shall correct a preexisting violation as part of the | ||
make-ready process and before the applicable deadline at the cost | ||
of the responsible person. | ||
(d) An electric cooperative shall resume make-ready | ||
activities without discrimination when the cooperative returns to | ||
routine operations. | ||
Sec. 253.0203. DEADLINES NOT APPLICABLE TO CERTAIN | ||
APPLICATIONS. (a) An electric cooperative is not required to meet | ||
the deadlines under this subchapter for an application to place | ||
pole attachments on more than 3,000 poles or more than five percent | ||
of the electric cooperative's poles. | ||
(b) An electric cooperative may not act under Subsection (a) | ||
to delay an application unreasonably and shall negotiate in good | ||
faith with the applicant regarding the time required to fulfill the | ||
cooperative's duties. | ||
Sec. 253.0204. CONTRACTORS FOR MAKE-READY ACTIVITIES. (a) | ||
A broadband provider may hire a contractor approved by the electric | ||
cooperative to complete a survey under Section 253.0104 or perform | ||
a make-ready activity under this subchapter that is not timely | ||
completed by the electric cooperative or a person with an existing | ||
pole attachment. | ||
(b) The broadband provider shall provide reasonably timely | ||
notice to the electric cooperative and each person with an existing | ||
pole attachment on an affected pole that the provider intends to | ||
hire a contractor as authorized by Subsection (a). | ||
(c) The broadband provider shall provide reasonably timely | ||
notice to the electric cooperative and each person with an existing | ||
pole attachment on an affected pole of the contractor's completion | ||
of the make-ready activities. | ||
(d) An electric cooperative may not act under Subsection (a) | ||
unreasonably to withhold approval of a contractor for purposes of | ||
this section. | ||
(e) Not later than the 90th day after the date a broadband | ||
provider provides notice as provided by Subsection (c), the | ||
cooperative or person may inspect the make-ready work. | ||
(f) Not later than the 14th day after the date that an | ||
electric cooperative or person completes an inspection under | ||
Subsection (e), the cooperative or person may notify the broadband | ||
provider of any damage or code violations caused by such work. The | ||
notice must include specific documentation. | ||
(g) The electric cooperative or person that completes an | ||
inspection may: | ||
(1) remedy any defective make-ready work at the cost | ||
of the broadband provider; or | ||
(2) require the provider to remedy the defect not | ||
later than the 14th day after the provider receives the notice under | ||
Subsection (f). | ||
Sec. 253.0205. LIST OF APPROVED CONTRACTORS. (a) An | ||
electric cooperative shall maintain and make available a list of | ||
approved contractors for work above the communications space and | ||
pole replacements. An electric cooperative may require any work | ||
above the communications space and pole replacements to be | ||
performed by contractors on this list, including work performed by | ||
a contractor hired under Section 253.0204. | ||
(b) An electric cooperative may not act unreasonably to | ||
withhold consent for a requested addition of a qualified contractor | ||
to the list described by Subsection (a). | ||
SUBCHAPTER D. OPTION FOR SIMPLE MAKE-READY ACTIVITIES | ||
Sec. 253.0301. OPTION: SIMPLE MAKE-READY. A broadband | ||
provider may choose to perform simple make-ready activities using | ||
one-touch make-ready procedures in place of the process outlined | ||
under Subchapter C. | ||
Sec. 253.0302. GRANT OR DENIAL OF APPLICATION: SIMPLE | ||
MAKE-READY. (a) A broadband provider that chooses to perform | ||
simple make-ready activities as described by Section 253.0301 must | ||
indicate that choice and describe the work to be performed as part | ||
of the provider's initial application under Subchapter B. | ||
(b) An electric cooperative shall grant or deny an | ||
application for simple make-ready activities under this section not | ||
later than: | ||
(1) the 15th day after the date the cooperative | ||
receives a complete application; or | ||
(2) the 30th day after the date the cooperative | ||
receives a complete large order application. | ||
Sec. 253.0303. SIMPLE MAKE-READY ACTIVITIES PERFORMED BY | ||
CONTRACTOR. (a) If an application for activities under Section | ||
253.0302 is granted, a contractor hired by the broadband provider | ||
shall perform all necessary surveys. | ||
(b) The broadband provider and contractor shall provide a | ||
reasonable opportunity for the electric cooperative and a person | ||
with an existing pole attachment on an affected pole to be present | ||
for any field inspections. | ||
(c) A contractor hired by the broadband provider may perform | ||
all simple make-ready activities. Not later than the 15th day | ||
before the date the contractor begins performing simple make-ready | ||
activities, the contractor shall provide to the electric | ||
cooperative and a person with an existing pole attachment on an | ||
affected pole written notice that: | ||
(1) identifies the contractor performing the | ||
activities; and | ||
(2) sets out reasonable opportunities for the | ||
cooperative and person to be present for the activities. | ||
Sec. 253.0304. INSPECTION OF WORK AND REMEDIATION OF | ||
DAMAGES. (a) A broadband provider immediately shall notify the | ||
electric cooperative and a person with an existing pole attachment | ||
on an affected pole of any damage to the cooperative's or person's | ||
facilities reasonably likely to interrupt the entity's service. | ||
(b) An electric cooperative or person that receives notice | ||
under Subsection (a) may: | ||
(1) complete any remedial work at a reasonable cost to | ||
the broadband provider; or | ||
(2) require the broadband provider immediately to | ||
remedy the damage at the provider's own expense. | ||
(c) Not later than the 15th day after the date a broadband | ||
provider or contractor hired by the provider completes simple | ||
make-ready activities on a pole, the provider shall notify the | ||
electric cooperative and a person with an existing pole attachment | ||
on the pole of the completed work. | ||
(d) Not later than the 90th day after the date an electric | ||
cooperative or person receives notice under Subsection (c), the | ||
cooperative or person may inspect the work. Not later than the 14th | ||
day after the date of the inspection, the cooperative or person may | ||
provide notice to the broadband provider, with specific | ||
documentation, of any damage or code violations caused by the work. | ||
(e) An electric cooperative or person that provides notice | ||
under Subsection (d) may: | ||
(1) remedy any defective make-ready work at the cost | ||
of the broadband provider; or | ||
(2) require the provider to remedy the defect not | ||
later than the 14th day after the date the provider received the | ||
notice under Subsection (d). | ||
SUBCHAPTER E. POLES AND POLE ATTACHMENTS | ||
Sec. 253.0401. DUTIES OF ELECTRIC COOPERATIVE. An electric | ||
cooperative shall rearrange, expand, replace, or otherwise safely | ||
reengineer any pole at the request of a broadband provider whose | ||
application for access to a pole is granted if the change is: | ||
(1) consistent with the National Electrical Safety | ||
Code; and | ||
(2) reasonably necessary to safely accommodate a pole | ||
attachment. | ||
Sec. 253.0402. RECOVERY OF COSTS FOR REPLACING POLES. (a) | ||
If an electric cooperative is required under Section 253.0401 to | ||
replace a pole that has been in service for longer than 75 percent | ||
and less than 100 percent of the average service life of a pole | ||
owned by the cooperative, the cooperative may not require | ||
reimbursement of costs associated with replacing the pole from the | ||
broadband provider that exceed the cooperative's reasonable costs | ||
of advancing the retirement of the existing pole. | ||
(b) The costs under Subsection (a) shall be determined by | ||
adding: | ||
(1) the remaining undepreciated value of the existing | ||
pole; | ||
(2) any interest expense of advancing the replacement | ||
of the pole relative to replacing the pole at the end of the average | ||
service life of a pole owned by the electric cooperative; and | ||
(3) any reasonable incremental cost of increasing the | ||
capacity of the replacement pole relative to the installation cost | ||
of the average new pole installed by the electric cooperative. | ||
(c) If an electric cooperative is required under Section | ||
253.0401 to replace a pole that has been in service for the average | ||
service life of a pole owned by the electric cooperative or longer, | ||
the cooperative may not require reimbursement of costs associated | ||
with replacing the pole from the broadband provider that exceed any | ||
reasonable incremental cost of increasing the capacity of the | ||
replacement pole relative to the installation cost of the average | ||
new pole installed by the electric cooperative. | ||
(d) An electric cooperative shall determine the average | ||
service life of a pole as the period of time during which an | ||
electric cooperative's books maintained for tax and accounting | ||
purposes consider an average pole to have positive value, after | ||
depreciation. | ||
Sec. 253.0403. SHARING COSTS OF MODIFICATION TO POLE. (a) | ||
The following entities must share proportionately in the costs of | ||
modifying a pole under Section 253.0401: | ||
(1) the broadband provider who obtains access to a | ||
pole through a modification to the pole; and | ||
(2) a person who directly benefits from a | ||
modification, including: | ||
(A) the electric cooperative; | ||
(B) a person with an existing attachment on the | ||
pole who adds to or modifies the person's attachment after | ||
receiving notice of the modification; and | ||
(C) a party that makes an attachment to a pole | ||
after the completion of a modification that made the attachment | ||
possible. | ||
(b) This section does not affect the responsibility of the | ||
electric cooperative under Sections 253.0401 and 253.0402. | ||
Sec. 253.0404. EXTENSION ARMS AND TEMPORARY POLE | ||
ATTACHMENTS. (a) A broadband provider may use extension arms and | ||
temporary attachments pending the completion of make-ready | ||
activities if use of extension arms and temporary attachments | ||
complies with the National Electrical Safety Code or other | ||
applicable safety codes. | ||
(b) An electric cooperative may require a broadband | ||
provider to convert a temporary attachment to a permanent | ||
attachment not later than the 60th day after the date of the | ||
completion of make-ready activities and may require the provider to | ||
comply with the National Electrical Safety Code or other | ||
applicable safety codes. | ||
Sec. 253.0405. POLE ATTACHMENT SPECIFICATIONS. (a) A | ||
broadband provider may not be required to meet pole attachment | ||
specifications that exceed the specifications in the National | ||
Electrical Safety Code, applicable fire safety codes, and any | ||
building code or similar code of general applicability for the | ||
protection of public health, safety, or welfare a political | ||
subdivision adopted before the provider submitted an application to | ||
the cooperative. | ||
(b) This section may not be construed to expand the power of | ||
any local government jurisdiction. | ||
Sec. 253.0406. OVERLASHING. (a) A broadband provider with | ||
an existing pole attachment may not be required to obtain advance | ||
approval from an electric cooperative to overlash or permit a third | ||
party to overlash the provider's existing wires. | ||
(b) An electric cooperative may require a broadband | ||
provider to provide notice before and after overlashing. The | ||
cooperative may not require notice before overlashing to be | ||
provided before the 15th day before the date of the overlashing | ||
activities. | ||
(c) An electric cooperative may require a broadband | ||
provider to modify an overlashing proposal to address specific and | ||
identified capacity, safety, reliability, or engineering issues. | ||
The cooperative may not prohibit the provider from overlashing | ||
because of a preexisting violation caused by another person. | ||
(d) An electric cooperative may require a broadband | ||
provider to remedy damage or code violations caused by overlashing | ||
if the electric cooperative: | ||
(1) inspects the overlash not later than the 90th day | ||
after the date the cooperative receives notice that an overlash is | ||
complete; and | ||
(2) informs the provider of the damage or violation | ||
not later than the 14th day after the date of the inspection. | ||
Sec. 253.0407. USE OF POLE ATTACHMENTS FOR MULTIPLE | ||
SERVICES. A broadband provider that attaches a pole attachment | ||
under this chapter may use the attachment for any service delivered | ||
over the provider's facilities, including cable service. | ||
SUBCHAPTER F. POLE ATTACHMENT CONTRACTS | ||
Sec. 253.0501. POLE ATTACHMENT CONTRACTS WITH BROADBAND | ||
PROVIDERS. (a) A broadband provider and an electric cooperative | ||
shall establish the rates, terms, and conditions for pole | ||
attachments by a written pole attachment contract executed by both | ||
parties. The rates, terms, and conditions for attachments by a | ||
broadband provider on an electric cooperative's poles must be just, | ||
reasonable, and nondiscriminatory. | ||
(b) In determining whether rates, terms, and conditions are | ||
just and reasonable, the following factors must be considered: | ||
(1) the interests of and benefits to the consumers and | ||
potential consumers of the electric cooperative's services; | ||
(2) the interests of and benefits to the subscribers | ||
and potential subscribers to broadband services offered through the | ||
pole attachments; | ||
(3) the interests of and benefits to third parties | ||
from the availability of broadband services offered through the | ||
pole attachments; | ||
(4) compliance with the specifications in the National | ||
Electrical Safety Code, applicable fire safety codes, and any | ||
building code or similar code of general applicability for the | ||
protection of public health, safety, or welfare applicable to the | ||
pole attachments; and | ||
(5) the maintenance and reliability of both electric | ||
distribution and broadband services. | ||
(c) A broadband provider and an electric cooperative shall | ||
negotiate a pole attachment contract and any amendment, | ||
modification, or renewal thereof in good faith. | ||
(d) A request to negotiate a new pole attachment contract or | ||
to amend, modify, or renew a contract pertaining to pole | ||
attachments by a broadband provider or an electric cooperative must | ||
be made in writing. | ||
Sec. 253.0502. CONTRACT NEGOTIATIONS AND MEDIATION. (a) | ||
If a broadband provider and an electric cooperative are unable to | ||
agree to a new pole attachment contract before the expiration date | ||
of an existing contract, the rates, terms, and conditions of the | ||
existing contract and the terms and conditions of the electric | ||
cooperative's application and permitting processes remain in | ||
force: | ||
(1) during the 90-day negotiation period described by | ||
Subsection (b) and during the period of any agreed extension; | ||
(2) during the 60-day mediation period described by | ||
Subsection (b) and during the period of any agreed extension; and | ||
(3) pending final disposition of any litigation | ||
commenced under Subsection (c). | ||
(b) If a broadband provider and an electric cooperative are | ||
unable to agree to a new pole attachment contract before the 91st | ||
day after the expiration date of an existing contract, and are | ||
unable to agree to an extension of the negotiation period for a | ||
certain number of days, the broadband provider and electric | ||
cooperative shall attempt to resolve any disagreement over the | ||
rates, terms, or conditions by submitting the contract negotiations | ||
to a mediation process. The mediation process may not extend later | ||
than the 60th day after the end of the initial 90-day negotiation | ||
period and any agreed extension of that period unless the broadband | ||
provider and electric cooperative agree to an extension of the | ||
mediation period for a certain number of days. The mediation | ||
process must be conducted in a county in which the electric | ||
cooperative has distribution poles. The broadband provider and | ||
electric cooperative must share equally the expenses for the | ||
mediator. | ||
(c) If the mediation process under Subsection (b) does not | ||
resolve the disagreement over the rates, terms, or conditions of a | ||
new pole attachment agreement, or if a dispute arises under the | ||
terms of an existing agreement or the requirements of this chapter, | ||
the broadband provider or electric cooperative may file suit in a | ||
district court to resolve the disagreement or dispute, including to | ||
enforce the terms of the agreement or of this chapter. | ||
SECTION 3. This Act takes effect September 1, 2021. |