S.B. No. 1281 |
|
||
relating to a reliability assessment of the ERCOT power grid and | ||
certificates of public convenience and necessity for certain | ||
transmission projects. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 37.052, Utilities Code, is amended by | ||
adding Subsection (c) to read as follows: | ||
(c) An electric utility is not required to amend the | ||
utility's certificate of public convenience and necessity to | ||
construct a transmission line that connects the utility's existing | ||
transmission facilities to a substation or metering point if: | ||
(1) the transmission line does not exceed: | ||
(A) three miles in length, if the line connects | ||
to a load-serving substation or metering point; or | ||
(B) two miles in length, if the line connects to a | ||
generation substation or metering point; | ||
(2) each landowner whose property would be directly | ||
affected by the transmission line, as provided by commission rules, | ||
provides written consent for the transmission line; and | ||
(3) all rights-of-way necessary for construction of | ||
the transmission line have been purchased. | ||
SECTION 2. Section 37.056, Utilities Code, is amended by | ||
adding Subsection (c-1) and amending Subsection (d) to read as | ||
follows: | ||
(c-1) In considering the need for additional service under | ||
Subsection (c)(2) for a reliability transmission project that | ||
serves the ERCOT power region, the commission must consider the | ||
historical load, forecasted load growth, and additional load | ||
currently seeking interconnection. | ||
(d) The commission by rule shall establish criteria, in | ||
addition to the criteria described by Subsection (c), for granting | ||
a certificate for a transmission project that serves the ERCOT | ||
power region, that is not necessary to meet state or federal | ||
reliability standards, and that is not included in a plan developed | ||
under Section 39.904(g) [ |
||
estimated cost of the transmission project for consumers and the | ||
estimated congestion cost savings for consumers that may result | ||
from the transmission project, considering both current and future | ||
expected congestion levels and the transmission project's ability | ||
to reduce those congestion levels. The commission shall include | ||
with its decision on an application for a certificate to which this | ||
subsection applies findings on the criteria. | ||
SECTION 3. Subchapter D, Chapter 39, Utilities Code, is | ||
amended by adding Section 39.159 to read as follows: | ||
Sec. 39.159. GRID RELIABILITY ASSESSMENT. (a) The | ||
independent organization certified under Section 39.151 for the | ||
ERCOT power region shall conduct a biennial assessment of the ERCOT | ||
power grid to assess the grid's reliability in extreme weather | ||
scenarios. | ||
(b) Each assessment must: | ||
(1) consider the impact of different levels of thermal | ||
and renewable generation availability; and | ||
(2) recommend transmission projects that may increase | ||
the grid's reliability in extreme weather scenarios. | ||
SECTION 4. The changes in law made by this Act apply only to | ||
a proceeding affecting a certificate of public convenience and | ||
necessity that commences on or after the effective date of this Act. | ||
A proceeding affecting a certificate of public convenience and | ||
necessity that commenced before the effective date of this Act is | ||
governed by the law in effect on the date the proceeding is | ||
commenced, and that law is continued in effect for that purpose. | ||
SECTION 5. This Act takes effect September 1, 2021. | ||
______________________________ | ______________________________ | |
President of the Senate | Speaker of the House | |
I hereby certify that S.B. No. 1281 passed the Senate on | ||
April 19, 2021, by the following vote: Yeas 31, Nays 0; | ||
May 28, 2021, Senate refused to concur in House amendments and | ||
requested appointment of Conference Committee; May 28, 2021, House | ||
granted request of the Senate; May 30, 2021, Senate adopted | ||
Conference Committee Report by the following vote: Yeas 31, | ||
Nays 0. | ||
______________________________ | ||
Secretary of the Senate | ||
I hereby certify that S.B. No. 1281 passed the House, with | ||
amendments, on May 26, 2021, by the following vote: Yeas 142, | ||
Nays 1, two present not voting; May 28, 2021, House granted request | ||
of the Senate for appointment of Conference Committee; | ||
May 30, 2021, House adopted Conference Committee Report by the | ||
following vote: Yeas 137, Nays 0, two present not voting. | ||
______________________________ | ||
Chief Clerk of the House | ||
Approved: | ||
______________________________ | ||
Date | ||
______________________________ | ||
Governor |