Bill Text: TX HB587 | 2027-2028 | 90th Legislature Regular Session | Introduced
Bill Title: Relating to the authority of a county to regulate the construction of certain industrial and offensive land use facilities.
Sponsorship: Partisan Bill (Republican 1)
Status: (Introduced) 2026-11-09 - Filed [HB587 Detail]
Download: Texas-2027-HB587-Introduced.html
| 90R3766 DRS-F | ||
| By: Money | H.B. No. 587 | |
|
|
||
|
|
||
| relating to the authority of a county to regulate the construction | ||
| of certain industrial and offensive land use facilities. | ||
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. Chapter 240, Local Government Code, is amended | ||
| by adding Subchapter F to read as follows: | ||
| SUBCHAPTER F. REGULATION OF CERTAIN INDUSTRIAL AND OFFENSIVE LAND | ||
| USE FACILITIES | ||
| Sec. 240.101. DEFINITIONS. In this subchapter: | ||
| (1) "Alternative energy facility" means: | ||
| (A) a wind power facility as defined by Section | ||
| 301.0001, Utilities Code; | ||
| (B) a solar power facility as defined by Section | ||
| 302.0001, Utilities Code; or | ||
| (C) a battery storage facility. | ||
| (2) "Industrial facility" includes: | ||
| (A) an electric generation facility; | ||
| (B) an alternative energy facility; | ||
| (C) a manufacturing or production facility; | ||
| (D) a distribution or logistics center; | ||
| (E) a data center; | ||
| (F) a water or wastewater treatment plant; and | ||
| (G) another heavy industrial or large-scale | ||
| commercial facility. | ||
| (3) "Offensive land use facility" includes a concrete | ||
| plant, concrete crushing facility, landfill, solid waste transfer | ||
| station, or automotive wrecking and salvage yard. | ||
| Sec. 240.102. PERMIT REQUIRED. Notwithstanding any other | ||
| law, a person may not construct an industrial facility or offensive | ||
| land use facility in the unincorporated area of a county unless the | ||
| person obtains a permit from the commissioners court of the county. | ||
| Sec. 240.103. PERMITTING PROCEDURE. (a) A commissioners | ||
| court of a county shall by order establish a procedure to review and | ||
| approve an application for a permit to construct an industrial | ||
| facility or offensive land use facility. | ||
| (b) A permitting procedure established under this section | ||
| must require: | ||
| (1) a permit be issued by order of the commissioners | ||
| court; and | ||
| (2) the commissioners court to hold at least two | ||
| public hearings on the application for the permit not less than two | ||
| weeks and not more than two months apart. | ||
| Sec. 240.104. DETERMINATION OF INDUSTRIAL OR OFFENSIVE LAND | ||
| USE FACILITY. A commissioners court by order may determine that a | ||
| facility proposed to be constructed is: | ||
| (1) an offensive land use facility; or | ||
| (2) an industrial facility, if the commissioners court | ||
| by order determines that the proposed facility: | ||
| (A) will require substantial infrastructure or | ||
| resources when operational; or | ||
| (B) by its nature, scale, or type of operations | ||
| constitutes a facility that would be suited for location in a | ||
| municipal zoning district that allows industrial use, if the | ||
| project were proposed to be located in an area subject to municipal | ||
| zoning regulation. | ||
| Sec. 240.105. ISSUANCE OF PERMIT. (a) In issuing a permit | ||
| required by this subchapter, a commissioners court must consider: | ||
| (1) the compatibility of the proposed facility that is | ||
| the subject of the permit with existing land uses in the surrounding | ||
| area; | ||
| (2) the potential impact of the facility on: | ||
| (A) public health and safety; | ||
| (B) air, water, and soil quality; and | ||
| (C) local infrastructure, including roads, | ||
| utilities, and emergency services; | ||
| (3) public comment and input from county residents and | ||
| other stakeholders; and | ||
| (4) other factors that the commissioners court | ||
| determines are relevant to balancing the interest in development | ||
| and the welfare of the community. | ||
| (b) A permit issued under this section may include | ||
| conditions and requirements that the commissioners court | ||
| determines are necessary to mitigate potential negative effects of | ||
| the proposed facility that is the subject of the permit, including a | ||
| requirement that the applicant implement measures for: | ||
| (1) the protection of public health and safety, | ||
| including providing necessary training and equipment for emergency | ||
| services; | ||
| (2) the improvement or maintenance of local | ||
| infrastructure; | ||
| (3) the protection of air, water, and soil quality; | ||
| and | ||
| (4) noise reduction. | ||
| Sec. 240.106. REVOCATION OR SUSPENSION OF PERMIT. A | ||
| commissioners court may revoke or suspend a permit issued under | ||
| this subchapter if the commissioners court by order finds that: | ||
| (1) the permit holder has violated the terms of the | ||
| permit; or | ||
| (2) the permitted project causes undue harm to the | ||
| surrounding area or community. | ||
| Sec. 240.107. ENFORCEMENT. The commissioners court of a | ||
| county may adopt orders to enforce this subchapter or an order | ||
| adopted under this subchapter. | ||
| SECTION 2. This Act takes effect September 1, 2027. | ||