Bill Text: TX HB5454 | 2025-2026 | 89th Legislature | Introduced
Bill Title: Relating to the authority of a county to regulate certain land uses.
Sponsorship: Partisan Bill (Republican 1)
Status: (Introduced - Dead) 2025-04-07 - Referred to Land & Resource Management [HB5454 Detail]
Download: Texas-2025-HB5454-Introduced.html
| By: Money | H.B. No. 5454 | |
|
|
||
|
|
||
| relating to the authority of a county to regulate certain land uses. | ||
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. Chapter 231, Local Government Code, is amended | ||
| by adding Subchapter N to read as follows: | ||
| SUBCHAPTER N. REGULATION OF CERTAIN INDUSTRIAL PROJECTS AND | ||
| OFFENSIVE LAND USES | ||
| Sec. 231.301. DEFINITIONS. In this subchapter: | ||
| (1) "Alternative energy facility" means: | ||
| (A) a wind power facility as defined by Section | ||
| 301.0001, Utilities Code; | ||
| (B) a solar power facility as defined by Section | ||
| 302.0001, Utilities Code; or | ||
| (C) a battery storage facility. | ||
| (2) "Industrial project" includes the construction or | ||
| operation of an electric generating facility, alternative energy | ||
| facility, or manufacturing facility. | ||
| (3) "Offensive land use" includes a concrete plant, | ||
| concrete crushing facility, landfill, solid waste transfer | ||
| station, or automotive wrecking and salvage yard. | ||
| Sec. 231.302. PERMIT REQUIRED. Notwithstanding any other | ||
| law, a person may not begin the construction or operation of an | ||
| industrial project or offensive land use in the unincorporated area | ||
| of a county unless the person obtains a permit from the | ||
| commissioners court of the county. | ||
| Sec. 231.303. COUNTY INDUSTRIAL PROJECT PERMITTING | ||
| PROCESS. (a) A commissioners court of a county shall by order | ||
| establish a procedure to review and approve an application for a | ||
| permit to build or operate an industrial project. | ||
| (b) If a commissioners court by order finds that a proposed | ||
| project requires substantial infrastructure or resources, the | ||
| commissioners court may by order determine that the project | ||
| constitutes an industrial project for purposes of the permit | ||
| requirement under this subchapter. | ||
| (c) A permitting procedure established by a county under | ||
| this subchapter must: | ||
| (1) require the permit be issued by order of the | ||
| commissioners court; and | ||
| (2) provide for at least two public hearings, held no | ||
| less than two weeks and no more than two months apart. | ||
| (d) In issuing a permit, a commissioners court must | ||
| consider: | ||
| (1) the compatibility of the proposed project with | ||
| existing land uses in the surrounding area; | ||
| (2) the potential impact of the proposed project on: | ||
| (A) public health and safety; | ||
| (B) air, water, and soil quality; and | ||
| (C) local infrastructure, including roads, | ||
| utilities, and emergency services; | ||
| (3) public comment and input from county residents and | ||
| other stakeholders; and | ||
| (4) other factors that the commissioners court | ||
| determines are relevant to balancing the interest in development | ||
| and the welfare of the community. | ||
| (e) A permit issued under this section may include | ||
| conditions and requirements that the commissioners court | ||
| determines are necessary to mitigate potential negative effects of | ||
| the project for which a permit is sought, including a requirement | ||
| that the applicant implement measures for: | ||
| (1) protecting public health and safety, including | ||
| providing necessary training and equipment for emergency services; | ||
| (2) local infrastructure improvement or maintenance; | ||
| (3) ensuring air, water, and soil quality; and | ||
| (4) noise reduction. | ||
| (f) A commissioners court may revoke, suspend, or deny | ||
| renewal of a permit issued under this subchapter if the | ||
| commissioners court by order finds that: | ||
| (1) the permit holder has violated the terms of the | ||
| permit; or | ||
| (2) the permitted project causes undue harm to the | ||
| surrounding area or community. | ||
| Sec. 231.304. ENFORCEMENT. The commissioners court of a | ||
| county may adopt orders to enforce this subchapter or an order | ||
| adopted under this subchapter. | ||
| SECTION 2. This Act takes effect September 1, 2025. | ||