Bill Title: Relating to permits for certain injection wells that transect a portion of the Edwards Aquifer.
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced - Dead) 2017-05-02 - Committee report sent to Calendars [HB3333 Detail]
Download: Texas-2017-HB3333-Comm_Sub.html
85R26748 SLB-F | |||
By: Isaac | H.B. No. 3333 | ||
Substitute the following for H.B. No. 3333: | |||
By: Larson | C.S.H.B. No. 3333 |
|
||
|
||
relating to permits for certain injection wells that transect a | ||
portion of the Edwards Aquifer. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Sections 27.0516(a)(1) and (3), Water Code, are | ||
amended to read as follows: | ||
(1) "Edwards Aquifer" means that portion of an arcuate | ||
belt of porous, waterbearing limestones composed of the Edwards | ||
Formation, Georgetown Formation, Comanche Peak Formation, Salmon | ||
Peak Limestone, McKnight Formation, West Nueces Formation, Devil's | ||
River Limestone, Person Formation, Kainer Formation, and Edwards | ||
Group, together with the Upper Glen Rose Formation where there is a | ||
significant hydrological connection to the overlying Edwards Group | ||
[ |
||
|
||
|
||
less-permeable Glen Rose Formation to the south[ |
||
|
||
|
||
regionally. | ||
(3) "Fresh water" means surface water or groundwater, | ||
without regard to whether the water has been physically, | ||
chemically, or biologically altered, that: | ||
(A) contains a total dissolved solids | ||
concentration of not more than 1,000 milligrams per liter; [ |
||
(B) meets the water quality standards for public | ||
drinking water established by commission rule; and | ||
(C) is otherwise suitable as a source of drinking | ||
water supply. | ||
SECTION 2. Sections 27.0516(b), (f), (h), (k), and (n), | ||
Water Code, are amended to read as follows: | ||
(b) This section applies only to the portion of the Edwards | ||
Aquifer that is within the geographic area circumscribed by the | ||
external boundaries of the Barton Springs-Edwards Aquifer | ||
Conservation District but is not in the jurisdiction [ |
||
|
||
Authority. | ||
(f) The commission by general permit may authorize: | ||
(1) an activity described by Subsection (e); | ||
(2) an injection well that transects and isolates the | ||
saline portion of the Edwards Aquifer and terminates in a lower | ||
aquifer for the purpose of injecting: | ||
(A) concentrate from a desalination facility; or | ||
(B) fresh water as part of an engineered aquifer | ||
storage and recovery facility; | ||
(3) an injection well that terminates in that part of | ||
the saline portion of the Edwards Aquifer that has a total dissolved | ||
solids concentration of more than 10,000 milligrams per liter for | ||
the purpose of injecting into the saline portion of the Edwards | ||
Aquifer: | ||
(A) concentrate from a desalination facility, | ||
provided that the injection well must be at least three miles from | ||
the closest outlet of Barton Springs; or | ||
(B) fresh water as part of an engineered aquifer | ||
and storage recovery facility, provided that each well used for | ||
injection or withdrawal from the facility must be at least three | ||
miles from the closest outlet of Barton Springs; [ |
||
(4) an injection well that transects or terminates in | ||
the Edwards Aquifer for: | ||
(A) aquifer remediation; | ||
(B) the injection of a nontoxic tracer dye as | ||
part of a hydrologic study; or | ||
(C) another beneficial activity that is designed | ||
and undertaken for the purpose of increasing protection of an | ||
underground source of drinking water from pollution or other | ||
deleterious effects; or | ||
(5) the injection of fresh water into a well that | ||
transects the Edwards Aquifer provided that: | ||
(A) the well isolates the Edwards Aquifer and | ||
meets the construction and completion standards adopted by the | ||
commission under Section 27.154; | ||
(B) the well is part of an engineered aquifer | ||
storage and recovery facility; | ||
(C) the injected water is sourced from a public | ||
water system, as defined by commission rule, that is permitted by | ||
the commission; and | ||
(D) the injection complies with the provisions of | ||
Subchapter G that are not in conflict with this section. | ||
(h) Rules adopted or a general permit issued under this | ||
section: | ||
(1) must require that an injection well authorized by | ||
the rules or permit be monitored by means of: | ||
(A) one or more [ |
||
operated by the injection well owner if the commission determines | ||
that there is an underground source of drinking water in the area of | ||
review that is potentially affected by the injection well; or | ||
(B) if Paragraph (A) does not apply, one or more | ||
[ |
||
injection well owner, provided that all results of monitoring are | ||
promptly made available to the injection well owner; | ||
(2) must ensure that an authorized activity will not | ||
result in the waste or pollution of native groundwater [ |
||
|
||
(3) may not authorize an injection well under | ||
Subsection (f)(2), [ |
||
associated with a small-scale research project designed to evaluate | ||
the long-term feasibility and safety of: | ||
(A) the injection of concentrate from a | ||
desalination facility; or | ||
(B) an aquifer storage and recovery project; | ||
(4) must require any authorization granted to be | ||
renewed at least as frequently as every 10 years; | ||
(5) must require that an injection well authorized | ||
under Subsection (f)(2)(A) or (3)(A) be monitored on an ongoing | ||
basis by or in coordination with the well owner and that the well | ||
owner file monitoring reports with the commission at least as | ||
frequently as every three months; [ |
||
(6) must ensure that any injection well authorized for | ||
the purpose of injecting concentrate from a desalination facility | ||
does not transect the fresh water portion of the Edwards Aquifer; | ||
and | ||
(7) must be consistent with the provisions of | ||
Subchapter G that are not in conflict with this section. | ||
(k) Notwithstanding Subsection (h)(3), a general permit may | ||
authorize the owner of an injection well authorized under | ||
Subsection (f)(2), [ |
||
for the purpose of implementing the desalination or engineered | ||
aquifer storage and recovery project following completion of the | ||
small-scale research project, provided that: | ||
(1) the injection well owner timely submits the | ||
information collected as part of the research project, including | ||
monitoring reports and information regarding the environmental | ||
impact of the well, to the commission; | ||
(2) the injection well owner, following the completion | ||
of studies and monitoring adequate to characterize risks to the | ||
fresh water portion of the Edwards Aquifer, the Trinity Aquifer, or | ||
[ |
||
continued operation of the well, and at least 90 days before the | ||
date the owner initiates commercial well operations, files with the | ||
commission a notice of intent to continue operation of the well | ||
after completion of the research project; and | ||
(3) the commission, based on the studies and | ||
monitoring, the report provided by Texas State University--San | ||
Marcos under Subsection (l)(2), and any other reasonably available | ||
information, determines that continued operation of the injection | ||
well as described in the notice of intent does not pose an | ||
unreasonable risk to the fresh water portion of the Edwards | ||
Aquifer, the Trinity Aquifer, or other native groundwater [ |
||
|
||
(n) If the commission preliminarily determines that | ||
continued operation of the injection well would pose an | ||
unreasonable risk to the fresh water portion of the Edwards | ||
Aquifer, the Trinity Aquifer, or other native groundwater [ |
||
|
||
commission shall notify the operator and specify, if possible, what | ||
well modifications or operational controls would be adequate to | ||
prevent that unreasonable risk. If the operator fails to modify the | ||
injection well as specified by the commission, the commission shall | ||
require the operator to cease operating the well. | ||
SECTION 3. This Act takes effect immediately if it receives | ||
a vote of two-thirds of all the members elected to each house, as | ||
provided by Section 39, Article III, Texas Constitution. If this | ||
Act does not receive the vote necessary for immediate effect, this | ||
Act takes effect September 1, 2017. |