Bill Text: TX HB3203 | 2013-2014 | 83rd Legislature | Introduced
Bill Title: Relating to design-build procedures for certain civil works projects.
Sponsorship: Partisan Bill (Republican 1)
Status: (Introduced - Dead) 2013-04-15 - Left pending in committee [HB3203 Detail]
Download: Texas-2013-HB3203-Introduced.html
| By: Creighton | H.B. No. 3203 | |
|
|
||
|
|
||
| relating to design-build procedures for certain civil works | ||
| projects. | ||
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. Section 2267.353, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended to read as follows: | ||
| Sec. 2267.353. CONTRACTS FOR CIVIL WORKS PROJECTS: | ||
| DESIGN-BUILD. [ |
||
| design-build method for the construction, rehabilitation, | ||
| alteration, or repair of a civil works project. In using this | ||
| method and in entering into a contract for the services of a | ||
| design-build firm, the contracting governmental entity and the | ||
| design-build firm shall follow the procedures provided by this | ||
| subchapter. | ||
| [ |
||
|
|
||
|
|
||
|
|
||
| [ |
||
|
|
||
|
|
||
|
|
||
|
|
||
| [ |
||
|
|
||
|
|
||
| [ |
||
|
|
||
|
|
||
| [ |
||
|
|
||
| [ |
||
|
|
||
| [ |
||
|
|
||
| [ |
||
|
|
||
|
|
||
|
|
||
| [ |
||
|
|
||
|
|
||
| SECTION 2. Section 2267.357, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended to read as follows: | ||
| Sec. 2267.357. REQUEST FOR PROPOSALS OR QUALIFICATIONS. | ||
| (a) The governmental entity shall select the design-build firm in a | ||
| one-step or two-step process. The governmental entity shall | ||
| prepare a single request for proposals, in the case of a one-step | ||
| process, or an initial request for qualifications, in the case of a | ||
| two-step process, that includes a statement of whether the | ||
| selection process is a one-step or two-step process and: | ||
| (1) information on the civil works project site; | ||
| (2) project scope; | ||
| (3) project budget; | ||
| (4) project schedule; | ||
| (5) criteria for selection under Section 2267.359 and | ||
| the weighting of the criteria; and | ||
| (6) other information that may assist potential | ||
| design-build firms in submitting proposals for the project. | ||
| (b) The governmental entity shall also prepare a design | ||
| criteria package as described by Section 2267.358. | ||
| (c) If a one-step process is used, the governmental entity | ||
| shall include the design criteria package in the request for | ||
| proposals. If a two-step process is used, the governmental entity | ||
| may not request, as part of the offeror's response to the request | ||
| for qualifications, the offeror's technical proposal or cost | ||
| proposal. | ||
| SECTION 3. Section 2267.359, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended by amending Subsections (a) and (c) to | ||
| read as follows: | ||
| (a) The governmental entity shall receive proposals, in the | ||
| case of a one-step process, or responses to a request for | ||
| qualifications, in the case of a two-step process, and shall | ||
| evaluate each offeror's experience, technical competence, and | ||
| capability to perform, the past performance of the offeror's team | ||
| and members of the team, project approach, cost methodology, and | ||
| other appropriate factors submitted by the team or firm in response | ||
| to the request for proposals or qualifications, except that the | ||
| governmental entity may not evaluate any cost-related or | ||
| price-related [ |
||
| methodology [ |
||
| process is used, the governmental entity shall also evaluate, for | ||
| each offeror, the results of each offeror's interview, if the | ||
| governmental entity included the results of an interview process in | ||
| the selection criteria. | ||
| (c) If a two-step process is used, the [ |
||
| entity shall, in accordance with the applicable evaluation criteria | ||
| established in Subsection (a), qualify five or fewer offerors to: | ||
| (1) submit additional information, including the | ||
| offeror's cost proposal and technical proposal as required by | ||
| Section 2267.361; and | ||
| (2) submit to an interview, if the governmental entity | ||
| included the results of an interview process in the selection | ||
| criteria [ |
||
| SECTION 4. Section 2267.360, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended to read as follows: | ||
| Sec. 2267.360. SELECTION OF DESIGN-BUILD FIRM. If a | ||
| one-step process is used, the governmental entity shall select the | ||
| design-build firm after evaluating the offeror's responses to the | ||
| request for proposals, in accordance with Section 2267.359(a) and | ||
| the governmental entity's selection criteria, as stated in the | ||
| request for proposals. If a two-step process is used, the [ |
||
| governmental entity shall select a design-build firm using a | ||
| combination of technical and cost proposals as provided by Section | ||
| 2267.361. | ||
| SECTION 5. The heading of Section 2267.361, Government | ||
| Code, as added by Chapter 1129 (H.B. 628), Acts of the 82nd | ||
| Legislature, Regular Session, 2011, is amended to read as follows: | ||
| Sec. 2267.361. PROCEDURES FOR SELECTION OF DESIGN-BUILD | ||
| FIRM UNDER TWO-STEP PROCESS [ |
||
|
|
||
| SECTION 6. Section 2267.361, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended by amending Subsections (a) and (e) to | ||
| read as follows: | ||
| (a) A governmental entity shall request proposals from | ||
| design-build firms identified under Section 2267.359(c). A firm | ||
| must submit a proposal not later than the 180th day after the date | ||
| the governmental entity makes a public request for the proposals | ||
| from the selected firms. The request for proposals must include: | ||
| (1) a design criteria package; | ||
| (2) if the project site is identified, a geotechnical | ||
| baseline report or other information that provides the design-build | ||
| firm minimum geotechnical design parameters to submit a proposal; | ||
| (3) detailed instructions for preparing both a cost | ||
| proposal and a [ |
||
| included, including a description of the form and level of | ||
| completeness of drawings expected; and | ||
| (4) the [ |
||
|
|
||
| and ranked. | ||
| (e) The governmental entity shall first open, evaluate, and | ||
| score each responsive technical proposal submitted on the basis of | ||
| the criteria described in the request for proposals and assign | ||
| points on the basis of the formula [ |
||
| request for proposals. The governmental entity may reject as | ||
| nonresponsive any firm that makes a significant change to the | ||
| composition of its firm as initially submitted. The governmental | ||
| entity shall subsequently open, evaluate, and score the cost | ||
| proposals from firms that submitted a responsive technical proposal | ||
| and assign points on the basis of the formula [ |
||
| in the request for proposals. The governmental entity shall select | ||
| the design-build firm in accordance with the formula provided in | ||
| the request for proposals. | ||
| SECTION 7. Section 2267.362, Government Code, as added by | ||
| Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended to read as follows: | ||
| Sec. 2267.362. NEGOTIATION. After selecting the | ||
| highest-ranked design-build firm under Section 2267.360, for a | ||
| one-step process, or Section 2267.361, for a two-step process, the | ||
| governmental entity shall first attempt to negotiate a contract | ||
| with the selected firm. If the governmental entity is unable to | ||
| negotiate a satisfactory contract with the selected firm, the | ||
| entity shall, formally and in writing, end all negotiations with | ||
| that firm and proceed to negotiate with the next firm in the order | ||
| of the selection ranking until a contract is reached or | ||
| negotiations with all ranked firms end. | ||
| SECTION 8. Section 2267.364(c), Government Code, as added | ||
| by Chapter 1129 (H.B. 628), Acts of the 82nd Legislature, Regular | ||
| Session, 2011, is amended to read as follows: | ||
| (c) The governmental entity may offer an unsuccessful | ||
| design-build firm that submits a response to the entity's request | ||
| for additional information under Section 2267.361 a stipend for | ||
| preliminary engineering costs associated with the development of | ||
| the proposal. The stipend must be [ |
||
|
|
||
| proposals. If the offer is accepted and paid, the governmental | ||
| entity may make use of any work product contained in the proposal, | ||
| including the techniques, methods, processes, and information | ||
| contained in the proposal. The use by the governmental entity of | ||
| any design element contained in an unsuccessful proposal is at the | ||
| sole risk and discretion of the entity and does not confer liability | ||
| on the recipient of the stipend under this subsection. | ||
| SECTION 9. Sections 2267.352 and and 2267.354, Government | ||
| Code, as added by Chapter 1129 (H.B. 628), Acts of the 82nd | ||
| Legislature, Regular Session, 2011, are repealed. | ||
| SECTION 10. This Act takes effect immediately if it | ||
| receives a vote of two-thirds of all the members elected to each | ||
| house, as provided by Section 39, Article III, Texas Constitution. | ||
| If this Act does not receive the vote necessary for immediate | ||
| effect, this Act takes effect September 1, 2013. | ||