Bill Text: TX HB2761 | 2023-2024 | 88th Legislature | Introduced
Bill Title: Relating to the issuance of a standard permit for the emission of air contaminants from a facility providing material for a public work project.
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced - Dead) 2023-03-13 - Referred to Environmental Regulation [HB2761 Detail]
Download: Texas-2023-HB2761-Introduced.html
88R10998 JXC-F | ||
By: Landgraf | H.B. No. 2761 |
|
||
|
||
relating to the issuance of a standard permit for the emission of | ||
air contaminants from a facility providing material for a public | ||
work project. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Subchapter C, Chapter 382, Health and Safety | ||
Code, is amended by adding Section 382.069 to read as follows: | ||
Sec. 382.069. STANDARD PERMIT FOR CERTAIN PUBLIC WORK | ||
PROJECTS. (a) In this section, "public work project" means a | ||
project to construct, alter, or repair a civil engineering project, | ||
including a road, street, bridge, underground utility, water supply | ||
project, water plant, wastewater plant, or airport runway or | ||
taxiway, under a contract entered into by a governmental entity | ||
under Chapter 2269, Government Code. | ||
(b) The commission shall issue a standard permit, if the | ||
commission finds that the permit is enforceable, for a facility | ||
that: | ||
(1) is dedicated solely to the provision of material | ||
for a public work project conducted under: | ||
(A) a single contract; or | ||
(B) one of multiple contracts for related project | ||
segments by the same contractor; | ||
(2) is not covered by an individual permit; | ||
(3) is located in or contiguous to the right-of-way of | ||
a public work project; | ||
(4) can adequately monitor compliance with the terms | ||
of the standard permit; and | ||
(5) will use control technology at least as effective | ||
as that described in Section 382.0518(b). | ||
(c) The commission shall publish notice of a standard permit | ||
proposed under this section in the Texas Register and in one or more | ||
statewide or regional newspapers designated by the commission that | ||
will, in the commission's judgment, provide reasonable notice | ||
throughout the state. The notice must include an invitation for | ||
written comments by the public to the commission regarding the | ||
proposed standard permit and must be published not later than the | ||
30th day before the date the commission issues the standard permit. | ||
(d) The commission may hold a public meeting to provide an | ||
additional opportunity for public comment. The commission shall | ||
give notice of a public meeting under this subsection as part of the | ||
notice described in Subsection (c) not later than the 30th day | ||
before the date of the meeting. | ||
(e) The commission by rule shall establish procedures for | ||
the amendment of a standard permit and for the issuance and | ||
revocation of an authorization to use a standard permit. The | ||
procedures must: | ||
(1) provide that an applicant may obtain an | ||
authorization to use the standard permit issued under this section | ||
for a facility by submitting to the commission a written notice of | ||
intent to use the permit; | ||
(2) specify the deadline for submitting and the | ||
information required to be included in a notice of intent under | ||
Subdivision (1); and | ||
(3) authorize an applicant to specify a date or period | ||
of time after the commission receives the notice of intent under | ||
Subdivision (1) on which the emission of air contaminants from the | ||
facility may begin unless the executive director notifies the | ||
applicant that the facility is not authorized to use the standard | ||
permit. | ||
(f) A facility authorized to use a standard permit issued | ||
under this section shall comply with an amendment to the standard | ||
permit beginning on the date the facility's authorization to use | ||
the permit is renewed or the date the commission otherwise | ||
provides. Before the date the facility is required to comply with | ||
the amendment, the standard permit, as it read before the | ||
amendment, applies to the facility. | ||
(g) A standard permit issued under this section must: | ||
(1) provide that an operator of a facility authorized | ||
to use the standard permit may use the standard permit for the | ||
duration of the public work project, unless the executive director | ||
notifies the operator that the facility is not authorized to use the | ||
standard permit; | ||
(2) require an authorization to use a standard permit | ||
issued under this section to terminate on the date the public work | ||
project is completed; | ||
(3) require an operator of a facility authorized to | ||
use a standard permit issued under this section to notify the | ||
commission of the operator's intent to cease operations by | ||
submitting a written notice of termination to the commission; and | ||
(4) specify the deadline for submitting and the | ||
information to be included in a notice of termination under | ||
Subdivision (3). | ||
(h) Sections 382.0516 and 382.056 do not apply to an | ||
application for an authorization to use a standard permit issued | ||
under this section. | ||
(i) The issuance or amendment of a standard permit or the | ||
issuance, renewal, or revocation of an authorization to use a | ||
standard permit is not subject to Chapter 2001, Government Code. | ||
SECTION 2. This Act takes effect September 1, 2023. |