By: Rosenthal | H.B. No. 228 |
|
||
|
||
relating to electricity supply chain risk mitigation planning. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Sections 86.044(d) and (e), Natural Resources | ||
Code, as added by S.B. No. 3, Acts of the 87th Legislature, Regular | ||
Session, 2021, are amended to read as follows: | ||
(d) The commission by rule shall require an operator of a | ||
gas supply chain facility to provide to the commission: | ||
(1) a summary report of a criticality analysis of the | ||
facility; | ||
(2) a plan to mitigate risk factors identified in the | ||
criticality analysis; and | ||
(3) proof that the operator has implemented the plan | ||
described by Subdivision (2) over a reasonable period, in a form | ||
satisfactory to the commission, which may be in the form of | ||
inspections or documents[ |
||
[ |
||
[ |
||
[ |
||
(e) The commission shall report to the attorney general any | ||
violation of a rule adopted under Subsection (c) that is not | ||
remedied in a reasonable period of time [ |
||
SECTION 2. Section 35.0021(c), Utilities Code, as added by | ||
S.B. No. 3, Acts of the 87th Legislature, Regular Session, 2021, is | ||
amended to read as follows: | ||
(c) The commission by rule shall require a provider of | ||
electric generation service described by Subsection (a) to provide | ||
to the commission: | ||
(1) a summary report of a criticality analysis of the | ||
provider's generation assets; | ||
(2) a plan to mitigate risk factors identified in the | ||
criticality analysis; and | ||
(3) proof that the provider has implemented the plan | ||
described by Subdivision (2) over a reasonable period, in a form | ||
satisfactory to the commission, which may be in the form of | ||
inspections or documents [ |
||
[ |
||
[ |
||
[ |
||
SECTION 3. Section 38.075(b), Utilities Code, as added by | ||
S.B. No. 3, Acts of the 87th Legislature, Regular Session, 2021, is | ||
amended to read as follows: | ||
(b) The commission by rule shall require each electric | ||
cooperative, municipally owned utility, and transmission and | ||
distribution utility providing transmission service in the ERCOT | ||
power region to provide to the commission: | ||
(1) a summary report of a criticality analysis of the | ||
cooperative's or utility's facilities; | ||
(2) a plan to mitigate risk factors identified in the | ||
criticality analysis; and | ||
(3) proof that the cooperative or utility has | ||
implemented the plan described by Subdivision (2) over a reasonable | ||
period, in a form satisfactory to the commission, which may be in | ||
the form of inspections or documents [ |
||
[ |
||
[ |
||
[ |
||
SECTION 4. Sections 121.2015(c-1) and (c-2), Utilities | ||
Code, as added by S.B. No. 3, Acts of the 87th Legislature, Regular | ||
Session, 2021, are amended to read as follows: | ||
(c-1) The railroad commission by rule shall require an | ||
operator of a gas pipeline facility described by Subsection (a)(3) | ||
to provide to the railroad commission: | ||
(1) a summary report of a criticality analysis of the | ||
facility; | ||
(2) a plan to mitigate risk factors identified in the | ||
criticality analysis; and | ||
(3) proof that the operator has implemented the plan | ||
described by Subdivision (2) over a reasonable period, in a form | ||
satisfactory to the commission, which may be in the form of | ||
inspections or documents [ |
||
[ |
||
[ |
||
[ |
||
(c-2) The railroad commission shall report to the attorney | ||
general any violation of a rule adopted under Subsection (a)(3) | ||
that is not remedied in a reasonable period of time [ |
||
SECTION 5. Sections 35.0021(c-1) and 38.075(c), Utilities | ||
Code, as added by S.B. No. 3, Acts of the 87th Legislature, Regular | ||
Session, 2021, are repealed. | ||
SECTION 6. This Act takes effect on the 91st day after the | ||
last day of the legislative session. |