Bill Text: TX HB1261 | 2027-2028 | 90th Legislature Regular Session | Introduced
Bill Title: Relating to the exercise of eminent domain for a demonstrated public necessity; limiting certain condemnation powers; requiring independent review, public hearings and county elections, enhanced compensation, repurchase rights, and revenue accounting; providing court review, injunctive relief, recovery of costs, and enforcement; contingent in part on a constitutional amendment.
Sponsorship: Partisan Bill (Republican 1)
Status: (Introduced) 2026-11-20 - Filed [HB1261 Detail]
Download: Texas-2027-HB1261-Introduced.html
| By: Spencer | H.B. No. 1261 | |
|
|
||
|
|
||
| relating to the exercise of eminent domain for a demonstrated | ||
| public necessity; limiting certain condemnation powers; requiring | ||
| independent review, public hearings and county elections, enhanced | ||
| compensation, repurchase rights, and revenue accounting; providing | ||
| court review, injunctive relief, recovery of costs, and | ||
| enforcement; contingent in part on a constitutional amendment. | ||
| BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
| SECTION 1. SHORT TITLE. This Act may be cited as the Texas | ||
| Private Property and Public Necessity Protection Act. | ||
| SECTION 2. LEGISLATIVE PURPOSE. The legislature finds that | ||
| involuntary acquisition of private property is an extraordinary | ||
| governmental act, that a public benefit is not by itself proof of an | ||
| indispensable need for a particular parcel, and that the public and | ||
| landowners require transparent findings, genuine alternatives, | ||
| meaningful local participation, adequate compensation, and | ||
| judicial review before property is taken. | ||
| SECTION 3. Chapter 2206, Government Code, is amended by | ||
| adding Subchapter E to read as follows: | ||
| SUBCHAPTER E. STATEWIDE PUBLIC NECESSITY STANDARDS | ||
| Sec. 2206.201. DEFINITIONS. In this subchapter: | ||
| (1) "Condemning authority" means any governmental or | ||
| private person or entity asserting eminent-domain power under a | ||
| general, local, or special law, including an agency, municipality, | ||
| county, special district, water supply corporation, public | ||
| utility, railway, common carrier, corporation created or | ||
| controlled by a governmental entity, or agent acting on behalf of | ||
| another entity. | ||
| (2) "Covered project" means the entire undertaking for | ||
| which property acquisition by eminent domain is proposed, including | ||
| related reservoirs, roads, pipelines, power facilities, | ||
| transmission lines, mitigation areas, access facilities, storage, | ||
| development phases, and improvements under common control or | ||
| coordinated funding. A connected project may not be artificially | ||
| divided to avoid a statutory requirement. | ||
| (3) "Public necessity" means an objectively | ||
| demonstrated, immediate and critical need for essential public | ||
| infrastructure or services directly benefiting the general public, | ||
| including the local population where a taking occurs, that cannot | ||
| reasonably be supplied by a feasible, less intrusive alternative. | ||
| "Immediate" requires a presently established need and an | ||
| objectively justified implementation schedule; speculative growth | ||
| projections alone are insufficient. This definition does not limit | ||
| a more protective standard in the Texas Constitution. | ||
| (4) "Feasible alternative" means a lawful, | ||
| technically capable option reasonably implementable within an | ||
| objectively justified period, including a combination of options, | ||
| even if not the condemnor's least expensive or preferred option. | ||
| Substantiated disproportionate cost and infeasibility may be | ||
| considered; an avoidable or self-created deadline is not proof of | ||
| necessity. | ||
| (5) "Protected land" means prime farmland identified | ||
| under United States Department of Agriculture soil | ||
| classifications, active timberland, watershed or recharge land, | ||
| bottomland hardwood forest, a multigenerational ranch held | ||
| continuously in family ownership for at least 25 years, or a | ||
| homestead occupied or qualified for homestead treatment under | ||
| applicable law. The claimant may supply reasonable records; | ||
| absence of a tax exemption does not defeat otherwise qualifying | ||
| land. | ||
| (6) "Affected owner" means a record title owner, | ||
| including a cotenant group treated as one ownership unit for a | ||
| particular parcel, whose land is sought through eminent domain for | ||
| the covered project. Affiliates may not fabricate or consolidate | ||
| owners to evade a threshold. A person owning multiple parcels is | ||
| counted once for the separate-owner threshold. | ||
| (7) "Taking" includes acquiring fee title, easements, | ||
| options secured by threatened condemnation, long-term exclusive | ||
| occupancy, or another compensable property interest; the | ||
| imposition of project-related restrictions may be examined under | ||
| applicable takings law. | ||
| Sec. 2206.202. STATEWIDE APPLICATION; PREEMPTION OF STATE | ||
| EXCEPTIONS. (a) This subchapter governs every proposed | ||
| condemnation under state law by a public or private condemnor, | ||
| regardless of size or location, and supplements Chapter 21, | ||
| Property Code. | ||
| (b) Notwithstanding Section 2206.001(c), Section | ||
| 2206.053(f) or (g), or a conflicting general, special, or local | ||
| law, a permit, franchise, common-carrier designation, certificate | ||
| of convenience, water plan, declaration of public use, funding | ||
| award, or vote of an appointed board does not dispense with this | ||
| subchapter. | ||
| (c) The subchapter applies to transportation, water, | ||
| wastewater, drainage, ports, public buildings, schools, parks, | ||
| utilities, transmission, pipelines, storage facilities, and other | ||
| undertakings alike, but confers no new condemnation authority. No | ||
| private contract, joint venture, subsidiary, proxy, affiliate, | ||
| interlocal agreement, route change, condemnation threat, or staged | ||
| acquisition may evade the requirements. | ||
| (d) A federal agency's exercise of independent federal | ||
| eminent-domain authority is not regulated by this state Act. Its | ||
| application to a federally certificated or preempted project is | ||
| limited to the extent consistent with controlling federal law; a | ||
| condemnor invoking preemption shall identify the specific federal | ||
| authority in a verified public filing before asserting the | ||
| exception. No broader exception is implied. | ||
| Sec. 2206.203. PROHIBITED PURPOSES AND NONDELEGATION. (a) | ||
| A taking is prohibited if its primary purpose is speculative | ||
| population or tax-base growth, private development, private | ||
| commerce, increased private profit, assembly for resale, or a | ||
| public-private venture principally supplying private economic | ||
| return. A subsequent private lease or transfer is evidence to be | ||
| considered, but the economic substance controls. | ||
| (b) An entity created to profit from acquiring condemned | ||
| property, a private for-profit company, or an unelected governing | ||
| board may not hold or exercise a new state-law delegation of | ||
| eminent-domain power after the effective date. Only the state or an | ||
| elected political-subdivision governing body may authorize a | ||
| taking; an elected authorizing body must consider each affected | ||
| project and issue written parcel-specific findings. A ministerial | ||
| filing by staff does not replace its vote. | ||
| (c) An entity with a preexisting claim of private | ||
| condemnation authority is subject to the transition provisions of | ||
| this Act, applicable constitutional law, and the express limits in | ||
| this section. This section shall be administered consistently with | ||
| Section 2206.215 and the Constitutions of Texas and the United | ||
| States. | ||
| Sec. 2206.204. BURDEN OF PROOF; NECESSITY; ALTERNATIVES. | ||
| (a) Before filing a condemnation petition or threatening | ||
| involuntary possession, a condemnor shall prove by clear and | ||
| convincing evidence for each tract and each interest sought that | ||
| (1) the project meets a present public necessity; (2) the exact | ||
| parcel and interest are indispensable to that necessity; (3) no | ||
| feasible combination of conservation, design changes, routes, | ||
| sites, technology, existing property, demand reduction, voluntary | ||
| acquisition, or a lesser estate can meet the demonstrated need; and | ||
| (4) the taking is the least intrusive reasonably feasible means. | ||
| (b) The purpose must be defined without reference to the | ||
| preferred site or sponsor. Greater population, forecast taxes, | ||
| grants, economic development, or the convenience of the sponsor | ||
| does not create a presumption. An offer refused by an owner is not | ||
| evidence of public necessity. | ||
| (c) The assessment shall quantify actual local, downstream, | ||
| and surrounding economic, agricultural, ecological, environmental, | ||
| access, drainage, cultural, community, and cumulative effects. | ||
| Project-specific mitigation shall be evaluated but cannot excuse a | ||
| prohibited taking or replace the necessity proof. | ||
| (d) A landowner is not required to retain an expert or | ||
| design an alternative. Unresolved material uncertainty or | ||
| unsupported assumptions are insufficient to satisfy the | ||
| condemnor's burden. | ||
| Sec. 2206.205. INDEPENDENT REVIEW PANEL. (a) Before the | ||
| public hearing required by Section 2206.206, the condemnor shall | ||
| submit the complete project and parcel-specific necessity record to | ||
| an independent three-member review panel appointed by the district | ||
| court in the county where the property lies from an approved public | ||
| roster of qualified independent professionals. | ||
| (b) One member must possess relevant engineering or | ||
| infrastructure expertise; one must possess land valuation, | ||
| agricultural, or environmental expertise appropriate to the | ||
| affected property; and one must be an attorney experienced in | ||
| property or administrative law or a qualified neutral with judicial | ||
| experience. No member may have represented or received | ||
| project-related compensation from the condemnor, its affiliates, | ||
| or the acquiring beneficiary during the preceding five years. | ||
| (c) The panel shall review alternatives, demand and supply | ||
| assumptions, local benefits, impacts, and the proposed | ||
| acquisition. It shall conduct a publicly noticed evidentiary | ||
| meeting, accept written and oral objections, and publish an | ||
| independently reasoned recommendation with its data and dissenting | ||
| conclusions, if any, within 90 days of a complete submission. | ||
| (d) The panel's recommendation is evidence but is not | ||
| conclusive, creates no presumption, and does not replace judicial | ||
| findings. The condemnor pays reasonable approved costs into a | ||
| court-administered fund; affected owners pay no panel costs. The | ||
| court may replace a conflicted member and may order supplementation | ||
| of an inadequate record. | ||
| Sec. 2206.206. FULL DISCLOSURE; PUBLIC HEARINGS. (a) At | ||
| least 90 days before filing a condemnation petition, the condemnor | ||
| shall provide each affected owner, county commissioners court, and | ||
| affected municipality a complete project description, each route or | ||
| site alternative, demand evidence, land map and ownership list, | ||
| independent-review report, environmental and economic impact | ||
| assessments, parcel-specific necessity findings, survey limits, | ||
| acquisition instrument, and written notice of rights. | ||
| (b) The documents shall be available without charge online | ||
| and in a physical public location in each affected county. Notice | ||
| shall be mailed to affected owners; published in an appropriate | ||
| newspaper; and posted publicly at least 30 days before a recorded | ||
| hearing in each affected county. The hearing must allow reasonable | ||
| oral and written comment and address material objections in a | ||
| written response before a vote. | ||
| (c) A confidentiality agreement, trade-secret designation, | ||
| contract with an intermediary, or nondisclosure clause may not | ||
| conceal information material to condemnation necessity from an | ||
| owner or court. Information lawfully protected from the general | ||
| public may be examined under a judicial protective order; it may not | ||
| be relied on to establish necessity if withheld from the affected | ||
| owner and judge. | ||
| Sec. 2206.207. COUNTYWIDE REFERENDUM. (a) Before a | ||
| condemnor files the first petition for a covered project that | ||
| proposes, in aggregate, to acquire through eminent domain more than | ||
| 100 acres or property of more than 10 separate owners, the project | ||
| must receive an affirmative majority vote at a project-specific | ||
| election in each county in which a project taking would occur. | ||
| (b) An affirmative vote is required in every affected | ||
| county; approval in another county cannot substitute. A county | ||
| commissioners court shall order the election when it receives a | ||
| complete, verified application and a deposit of the reasonable | ||
| election costs from the condemnor. An elected statewide entity is | ||
| subject to the same county elections for projects under state | ||
| authority. | ||
| (c) The proposition shall identify the project, maximum | ||
| condemned acreage, general route or footprint, necessity claimed, | ||
| beneficiaries, and maximum proposed interest to be taken, and shall | ||
| ask whether the project may use eminent domain in that county. It | ||
| may not package unrelated projects. Material expansion requires a | ||
| new vote. | ||
| (d) Elections shall be administered under the Election | ||
| Code, including Chapter 41 and applicable notice and canvassing | ||
| laws. An election may not be held until after the independent panel | ||
| report and county hearing. The condemnor shall bear documented | ||
| election costs. Failure to hold an election is denial, not deemed | ||
| approval. | ||
| (e) For determining thresholds, all reasonably foreseeable | ||
| project phases, connected parcels, threatened condemnation | ||
| acquisitions, common owners, affiliates, and substantially related | ||
| routes or sites must be aggregated. An initial voluntary purchase | ||
| that does not involve threatened condemnation is not itself | ||
| condemned acreage, but a sham acquisition to evade this section | ||
| shall be counted. | ||
| Sec. 2206.208. PROTECTED AGRICULTURAL AND NATURAL LANDS. | ||
| (a) Land meeting Section 2206.201(5) may be condemned only on a | ||
| showing by clear and convincing evidence of unavoidable immediate | ||
| public necessity for that protected tract, as independently | ||
| reviewed and judicially determined, and only after at least | ||
| two-thirds of votes cast on the question by the qualified voters in | ||
| each county containing affected protected land are in favor. | ||
| (b) This special election is required regardless of project | ||
| acreage or number of affected owners. When both Sections 2206.207 | ||
| and 2206.208 apply, one ballot may be used only if it clearly states | ||
| the heightened two-thirds threshold. No approval in one county | ||
| overrules a no vote in another. | ||
| (c) A project sponsor must evaluate farmland, timberland, | ||
| homestead, and watershed avoidance and demonstrate why an | ||
| alternative route or site outside protected lands is infeasible. | ||
| Future mitigation or payments to unrelated parties do not satisfy | ||
| the prohibition. | ||
| Sec. 2206.209. PRIOR JUDICIAL HEARING; NO EARLY POSSESSION. | ||
| (a) The district court where the tract is located has original | ||
| jurisdiction, before appointment of special commissioners under | ||
| Chapter 21, Property Code, to decide lawful authority, public | ||
| necessity, independent panel compliance, elections, protected | ||
| status, the validity of a proposed interest, and the absence of | ||
| feasible alternatives. | ||
| (b) The condemnor must produce all evidence and establish | ||
| each element by clear and convincing evidence. The court shall | ||
| conduct an evidentiary hearing with reasonable discovery and | ||
| opportunity for the owner to examine witnesses, make independent | ||
| findings as to each parcel, and deny or dismiss a proceeding that | ||
| fails the burden. | ||
| (c) Neither a permit nor a condemnor's own determination | ||
| receives deference. No court or special commissioner may permit | ||
| possession, entry for construction, site disturbance, or transfer | ||
| of ownership pending a final favorable necessity determination and | ||
| completion of timely review. Lawful preliminary surveys remain | ||
| governed by existing law and do not authorize intrusive | ||
| construction or a permanent property right. | ||
| (d) Either party may take an interlocutory appeal from the | ||
| necessity ruling. The filing of a timely appeal stays all | ||
| condemnation and possession activity for the affected parcel | ||
| through resolution of that appeal. A deposit, bond, emergency | ||
| declaration, or commissioners' award does not waive the stay. | ||
| (e) An owner who obtains dismissal or an injunction for | ||
| noncompliance, or whose condemnor voluntarily dismisses after a | ||
| substantial contest to necessity, shall receive reasonable | ||
| attorney, expert, appraisal, and court costs. An unsuccessful | ||
| owner shall not owe the condemnor's professional fees solely for | ||
| raising a good-faith challenge. | ||
| Sec. 2206.210. COMPENSATION; DAMAGES AND COSTS. (a) The | ||
| minimum amount for a taking permitted by this subchapter is 200 | ||
| percent of the fair market value of the interest condemned as of the | ||
| valuation date immediately preceding any project-caused | ||
| diminution, plus independently established severance damages to | ||
| the remainder and reasonable actual relocation, loss-of-access | ||
| mitigation, restoration, fencing, drainage, | ||
| business-interruption, moving, and necessary appraisal, legal, and | ||
| professional expenses caused by the taking. | ||
| (b) The 200 percent value floor applies separately to the | ||
| interest taken. Additional categories may not be used to reduce | ||
| that floor, and an item of actual loss may be recovered only once. | ||
| This section provides an enhancement beyond ordinary | ||
| constitutional compensation and does not reduce another remedy or | ||
| federal minimum. | ||
| (c) The condemnor shall pay or secure the required amount | ||
| before possession. If any owner contests valuation, the undisputed | ||
| amount shall be tendered, but tender alone does not authorize | ||
| possession while necessity remains in litigation. The court shall | ||
| authorize independently obtained appraisals and allow evidence of | ||
| long-term agricultural and timber use insofar as relevant under the | ||
| appraisal law. | ||
| (d) For an easement, the acquired interest must be narrowly | ||
| described by area, duration, permissible uses, access, future | ||
| expansion, restoration duty, and termination; a condemnor may not | ||
| treat a limited corridor award as blanket authority for unrelated | ||
| future facilities. | ||
| Sec. 2206.211. 10-YEAR RETURN; NO SHAM PROGRESS. (a) In | ||
| addition to all rights under Subchapter E, Chapter 21, Property | ||
| Code, a former owner or the owner's heirs, successors, or assigns | ||
| has an enforceable right to repurchase an interest condemned under | ||
| this subchapter if the property is not actually placed into the | ||
| original specifically stated public-necessity use within 10 years | ||
| after acquisition, even if surveying, planning, procurement, | ||
| financing, permitting, or another preliminary act occurred. | ||
| (b) The right also arises earlier upon cancellation, | ||
| abandonment, disposal, or change to a substantially different use. | ||
| A redevelopment label, partial nonproductive use, transfer to an | ||
| affiliate, or lease may not constitute use unless the condemned | ||
| parcel is materially serving the authorized public necessity. | ||
| (c) The condemnor shall notify the former owner and known | ||
| heirs promptly upon an event in Subsection (b) and not later than 30 | ||
| days after the 10-year deadline. The person has at least 180 days | ||
| after actual notice to accept an offer of repurchase, and 180 days | ||
| after acceptance to close. Failure to deliver notice does not | ||
| extinguish the right. | ||
| (d) The repurchase price is the original compensation | ||
| attributable to the interest reacquired, adjusted by the change in | ||
| the United States Consumer Price Index for All Urban Consumers from | ||
| acquisition through repurchase; the amount may not be increased for | ||
| improvements installed solely for an abandoned purpose. The seller | ||
| shall convey the same estate or interest reasonably capable of | ||
| reconveyance, free of liens created by the condemnor. | ||
| (e) The district court may compel conveyance, rescind an | ||
| unlawful transfer, and award costs and reasonable fees to a | ||
| prevailing former owner. The stronger of this section and | ||
| otherwise applicable repurchase law governs a new covered | ||
| acquisition. Existing lawful repurchase rights are not diminished. | ||
| Sec. 2206.212. DIRECT PROPERTY REVENUE RETURN. (a) If | ||
| receipts or revenue are obtained directly from property | ||
| involuntarily acquired for a covered project, including leases, | ||
| license fees, royalties, rents, sales, commercial access charges, | ||
| concessions, or consideration for later transfer or commercial use, | ||
| the condemnor shall annually account for and remit the attributable | ||
| revenue in proportion to the real property interests acquired from | ||
| the affected former owners and successors. | ||
| (b) Revenue from a specific parcel must first be attributed | ||
| to that parcel. Revenue inseparable among several condemned | ||
| parcels shall be allocated using independently appraised | ||
| contribution to the revenue-generating use, or acreage if | ||
| contribution cannot reasonably be distinguished. No contractual | ||
| affiliate, successor, governmental corporation, or project sponsor | ||
| may evade payment through internal transfers or noncash | ||
| consideration. | ||
| (c) Public taxes and general utility tariffs collected for | ||
| services that cannot reasonably be attributed to the affected | ||
| parcel are not deemed property-generated receipts merely because a | ||
| public facility crosses the parcel. This narrow identification | ||
| rule does not exempt site-specific commercial revenue and shall be | ||
| reviewed by legislative counsel for conformity with the proposed | ||
| constitutional amendment and adopted legislative priority. | ||
| (d) The condemnor shall maintain an audited annual | ||
| property-revenue ledger and send statements and distributions to | ||
| known former owners. An affected owner may audit the records, seek | ||
| an accounting and injunction, and recover wrongfully withheld | ||
| amounts, interest, and reasonable fees. A compensation award under | ||
| Section 2206.210 may not be used as an offset to revenue due under | ||
| this section. | ||
| Sec. 2206.213. TRANSPARENCY; OVERSIGHT; ENFORCEMENT. (a) | ||
| The comptroller shall maintain a free statewide registry of covered | ||
| projects and the condemning authority; requested parcels and | ||
| acreage; number of owners; purpose and underlying legal authority; | ||
| assessments and alternatives; panel reports; elections; court | ||
| rulings; use-commencement dates; disposition, repurchase, and | ||
| revenue remittances; and compliance and enforcement actions. | ||
| (b) The attorney general may seek injunctive or declaratory | ||
| relief to prevent an unauthorized taking. An affected owner may | ||
| bring an action for declaratory or injunctive relief and | ||
| enforcement of a mandatory duty in a district court of the county | ||
| where the land lies. Jurisdiction and a limited waiver of | ||
| governmental and sovereign immunity to suit and liability are | ||
| provided to the extent necessary for the prospective relief and | ||
| specific fee and repurchase remedies expressly conferred by this | ||
| subchapter; this subsection creates no general tort damages remedy. | ||
| (c) Materially false verification, evasion by project | ||
| segmentation, concealment of beneficial ownership, or retaliation | ||
| for participation disqualifies the defective application until | ||
| corrected and is subject to court-ordered injunctive relief. | ||
| Additional criminal or civil penalties require independent | ||
| Legislative Council review before inclusion. | ||
| Sec. 2206.214. NARROW TEMPORARY LIFE-SAFETY RELIEF. A | ||
| district court may authorize only temporary, reasonably necessary | ||
| access or a nonpermanent property interest for a documented | ||
| imminent threat to human life when no feasible response exists | ||
| without immediate access. The order must specify maximum duration, | ||
| safeguards, payment, restoration, and a hearing within 10 days. It | ||
| does not authorize a permanent taking, ordinary growth project, | ||
| speculative capacity expansion, or evasion of the necessity | ||
| requirement. | ||
| Sec. 2206.215. PROTECTED RIGHTS; FEDERAL LAW. (a) This | ||
| subchapter applies prospectively to petitions filed on or after its | ||
| effective date, subject to the constitutional protection of final | ||
| judgments, interests already acquired, and legally protected | ||
| contracts. A pending route designation, project plan, preliminary | ||
| expenditure, or unfiled proposal alone is not a vested condemnation | ||
| of a particular parcel. | ||
| (b) This subchapter does not authorize the state to regulate | ||
| direct federal condemnation or diminish rights under the | ||
| Constitution of the United States. Any federally preempted | ||
| application is severed only to the minimum degree required by | ||
| controlling law; the remaining state-law duties continue where | ||
| lawful. | ||
| Sec. 2206.216. RULES; NO WAIVER. The comptroller, the | ||
| attorney general, the Texas Department of Transportation, the | ||
| Public Utility Commission, the Railroad Commission, and the Texas | ||
| Commission on Environmental Quality may coordinate published | ||
| implementation guidance within their lawful jurisdictions, but may | ||
| not create exceptions or substitute implied approval for a | ||
| statutory or constitutional protection. | ||
| SECTION 4. Section 2206.001, Government Code, is amended by | ||
| adding Subsection (f) to read as follows: | ||
| (f) An exception recognized in Subsection (c) preserves | ||
| only the underlying authority otherwise granted by law; it does not | ||
| exempt a condemnor from the public necessity, election, independent | ||
| review, compensation, and other requirements of Subchapter E, | ||
| subject to controlling federal law. | ||
| SECTION 5. Section 2206.053, Government Code, is amended by | ||
| adding Subsection (h) to read as follows: | ||
| (h) Notwithstanding Subsection (f) or (g), an ordinance, | ||
| resolution, or delegation that does not identify a parcel or that | ||
| authorizes condemnation without compliance with Subchapter E may | ||
| not substitute for the parcel-specific public necessity findings, | ||
| independent review, or county election required by that subchapter. | ||
| SECTION 6. Chapter 21, Property Code, is amended by adding | ||
| Section 21.0125 to read as follows: | ||
| Sec. 21.0125. PRIOR PUBLIC NECESSITY DETERMINATION. (a) | ||
| Notwithstanding Sections 21.001, 21.011, 21.014, and 21.021, | ||
| before special commissioners are appointed or possession granted, | ||
| the district court in the county containing the property shall make | ||
| the findings required by Subchapter E, Chapter 2206, Government | ||
| Code, when applicable. | ||
| (b) No compensation award, deposit, temporary injunction | ||
| bond, or waiver of commissioners' objections dispenses with the | ||
| prior judicial determination and any timely interlocutory appeal. | ||
| This section supplements Section 21.003. | ||
| SECTION 7. Chapter 21, Property Code, is amended by adding | ||
| Section 21.0431 to read as follows: | ||
| Sec. 21.0431. MINIMUM COMPENSATION FOR CERTAIN TAKINGS. | ||
| For a taking covered by Subchapter E, Chapter 2206, Government | ||
| Code, special commissioners and courts shall award no less than the | ||
| compensation required by Section 2206.210 of that code. A written | ||
| settlement made with independently represented owners may | ||
| establish different payment terms only if it does not purport to | ||
| waive any required constitutional minimum or entitlement of another | ||
| owner. | ||
| SECTION 8. Section 21.101, Property Code, is amended by | ||
| adding Subsection (d) to read as follows: | ||
| (d) For property acquired under Subchapter E, Chapter 2206, | ||
| Government Code, the additional triggers, ten-year actual-use | ||
| test, notice protections, and remedies in Section 2206.211, | ||
| Government Code, apply in addition to this subchapter; an existing | ||
| stronger repurchase right is preserved. | ||
| SECTION 9. Section 21.103, Property Code, is amended by | ||
| adding Subsection (c) to read as follows: | ||
| (c) The repurchase price for a property interest acquired | ||
| under Subchapter E, Chapter 2206, Government Code, is governed by | ||
| Section 2206.211, Government Code, rather than the unadjusted | ||
| resale price in Subsection (b), without limiting another repurchase | ||
| entitlement available for acquisitions not covered by that | ||
| subchapter. | ||
| SECTION 10. CONFORMING EFFECT ON OTHER CODES. The | ||
| requirements of Subchapter E, Chapter 2206, Government Code, and | ||
| Section 21.0125, Property Code, apply notwithstanding a | ||
| conflicting condemnation grant or procedure in Transportation Code | ||
| Chapter 203; Utilities Code Chapter 181 or 186; Water Code Chapter | ||
| 49; Natural Resources Code Chapter 111; Local Government Code | ||
| Chapter 251; Education Code Section 11.155; or a special enabling | ||
| law, subject to the supremacy of controlling federal law. An | ||
| authorizing law that conflicts with this Act shall be read together | ||
| with this Act to give effect to the stronger lawful protection | ||
| against an involuntary taking. | ||
| SECTION 11. IMPLEMENTATION; LEGISLATIVE REVIEW. (a) | ||
| Within 180 days after this Act takes effect, the comptroller shall | ||
| publish a consolidated list of existing state-law entities claiming | ||
| condemnation authority and the statutes that confer it, flag | ||
| private or unelected bodies, and submit to the legislature proposed | ||
| conforming repeals or limitations. | ||
| (b) No new prohibited taking may proceed solely because | ||
| implementing rules have not yet been adopted. This Act does not | ||
| appropriate funds. The fiscal effect of panels, elections, | ||
| enhanced compensation, reporting, and revenue remittance must be | ||
| addressed through the legislative appropriations process. | ||
| SECTION 12. TRANSITION. This Act governs condemnation | ||
| petitions filed, and new acquisitions by express threat of | ||
| condemnation initiated, on or after the effective date. It does not | ||
| reopen final judgments or undo an interest actually and lawfully | ||
| acquired before that date. A preexisting permit, certificate, | ||
| plan, or contract does not by itself grandfather a future unfiled | ||
| condemnation proceeding. Any application to a legally protected | ||
| preexisting right shall be resolved under the Texas and United | ||
| States Constitutions. | ||
| SECTION 13. SEVERABILITY. If a provision or application of | ||
| this Act is held invalid, remaining provisions capable of | ||
| independent application remain effective. A finding invalidating a | ||
| referendum procedure, reimbursement formula, or delegation limit | ||
| does not by itself authorize a taking prohibited by another | ||
| effective provision. | ||
| SECTION 14. EFFECTIVE DATE AND CONTINGENCY. This Act takes | ||
| effect January 1, 2028, but only if the constitutional amendment | ||
| proposed by the 90th Legislature, Regular Session, 2027, concerning | ||
| the public-necessity standard for eminent domain is approved by the | ||
| voters at the November 2, 2027 election. If that amendment is not | ||
| approved, this Act has no effect. | ||