Bill Title: Authorizes certain energy projects involving installation of transmission and distribution wires that cross preserved farmland.

Sponsorship: Partisan Bill (Democrat 4)

Status: (Passed) 2026-01-20 - Approved P.L.2025, c.390. [A5901 Detail]

Download: New_Jersey-2024-A5901-Amended.html

[Second Reprint]

ASSEMBLY, No. 5901

STATE OF NEW JERSEY

221st LEGISLATURE

 

INTRODUCED JUNE 27, 2025

 


 

Sponsored by:

Assemblyman  DAVID BAILEY, JR.

District 3 (Cumberland, Gloucester and Salem)

Assemblyman  ROBERT J. KARABINCHAK

District 18 (Middlesex)

Assemblyman  WAYNE P. DEANGELO

District 14 (Mercer and Middlesex)

 

 

 

 

SYNOPSIS

     Authorizes certain energy projects involving installation of transmission and distribution wires that cross preserved farmland.

 

CURRENT VERSION OF TEXT

     As reported by the Assembly Appropriations Committee on December 18, 2025, with amendments.

  


An Act concerning the 1[construction, installation, and operation of certain energy project components on] installation of transmission and distribution wires that cross1 preserved farmland and supplementing Title 4 of the Revised Statutes.

 

     Be It Enacted by the Senate and General Assembly of the State of New Jersey:

 

     1.  a.  As used in this section:

     1"Board" means the Board of Public Utilities.1

     "Committee" means the State Agriculture Development Committee established pursuant to section 4 of P.L.1983, c.31 (C.4:1C-4).

     "Preserved farmland" means land on which a development easement was conveyed to, or retained by, the committee, a board, or a qualifying tax exempt nonprofit organization pursuant to the provisions of section 24 of P.L.1983, c.32 (C.4:1C-31), section 5 of P.L.1988, c.4 (C.4:1C-31.1), section 1 of P.L.1989, c.28 (C.4:1C-38), section 1 of P.L.1999, c.180 (C.4:1C-43.1), sections 37 through 40 of P.L.1999, c.152 (C.13:8C-37 through C.13:8C-40), or any other State law enacted for farmland preservation purposes.

     1"Secretary" means the Secretary of Agriculture.

     "Transmission and distribution wires" or "wires" means wires used to interconnect an energy generation facility to an electric distribution or transmission system, as well as any associated components that are necessary for the wires' installation, functionality, and access.1

     b.  1[Notwithstanding the provisions of any law, rule, or regulation to the contrary, a person or entity may construct, install, and operate energy project transmission and distribution components, facilities, structures, equipment, and improvements on preserved farmland, including improvements associated with access to such components, whether on the preserved portion of the farm or on any exception area or other portion excluded from preservation and regardless of whether the energy generating from the project is used on the farm, and may make improvements to any agricultural, horticultural, residential, or other building or structure on the land for that purpose, so long as:

     (1) the owner of the preserved farmland has granted rights or otherwise approved such components, facilities, equipment, and improvements;

     (2) generating facilities are not located on the farm pursuant to this section and the facilities authorized by this subsection shall be limited to those associated with the transmission and distribution of energy, along with access to such facilities;

     (3) the components, facilities, structures, and equipment for any single project are located within a right-of-way not to exceed fifty feet in width located as close as reasonably practical, based on applicable constraints, to the edge of the preserved portion of the farm and are installed by any of the following methods and subject to the following limitations:

     (a) overhead lines shall be located within the right-of-way, with any disturbance around associated poles and in the work area to be returned as close as reasonably practical to existing conditions after completion of the work;

     (b) open cut trenches shall be located within the right-of-way with the components to be installed at a depth of greater than three feet below grade, with the trench to be backfilled and with any disturbance in the work area to be returned as close as reasonably practical to existing conditions after completion of the work;

     (c) the use of a cable plow to cut a narrow trench into the ground and simultaneously lay the cable shall be located within the right-of-way with the components to be installed at a depth of greater than three feet below grade, with any open areas to be backfilled and with any disturbance in the work area to be returned as close as reasonably practical to existing conditions after completion of the work; and

     (d) the underground bore shall be located within the right-of-way at a depth of greater than three feet below grade; and

     (4) any improvements or use, including roadway improvements, that require access outside of the right-of-way shall be limited to an additional right-of-way not to exceed fifty feet in width and shall be allowed only when no other access route is reasonably practical.  The additional right-of-way shall be located either:

     (a) as close as reasonably practical based on applicable constraints to the edge of the preserved portion of the farm; or

     (b) in and around any existing driveway that is adjacent to, or that leads to, the energy project facilities.

     c.  Any use of preserved farmland that is consistent with the provisions of subsection b. of this section shall be automatically allowed without approval required from the committee.

     d.  For any use of preserved farmland that is associated with energy project transmission or distribution, but that is not consistent with the provisions of subsection b. of this section, the person or entity shall submit an application to the committee to seek approval before constructing, installing, and operating any energy project components, facilities, structures, or equipment on the farm, with such approval not to be unreasonably withheld, conditioned, or delayed.  The committee shall provide the holder of any development easement on the farm with a copy of the application submitted pursuant to this subsection, and the holder of the development easement shall have 30 days within which to provide comments to the committee on the application.  The committee shall, within 90 days of receipt, approve, disapprove, or approve with conditions an application submitted pursuant to this subsection.  The committee shall base application decisions solely upon whether the proposed installations will interfere significantly with the use of the land for agricultural or horticultural production, considering comments received from the holder of the development easement, and balancing against the energy needs of the State.

     e.  No fee shall be charged of the applicant for review of an application submitted to, or issuance of any decision by, the committee pursuant to this section.

     f.  The committee may suspend or revoke an approval issued pursuant to this section for a violation of any term or condition of the approval or any provision of this section.

     g.  Notwithstanding any provision of this section to the contrary, the construction, installation, or operation of any energy project transmission or distribution component, facility, structure, or equipment in the pinelands area, as defined and regulated by the "Pinelands Protection Act," P.L.1979, c.111 (C.13:18A-1 et seq.), shall comply with the standards of P.L.1979, c.111 (C.13:18A-1 et seq.) and the comprehensive management plan for the pinelands area adopted pursuant to P.L.1979, c.111 (C.13:18A-1 et seq.).

     h.  In making any decisions pursuant to this section, the committee shall balance the need for land for suitable agricultural or horticultural production with the energy needs of the State.] If transmission and distribution wires are required to be connected to, or from, an energy generation facility located in the State to allow the facility to interconnect to an electric distribution or transmission system, such that the wires would cross preserved farmland, the owner of the facility may submit an application to the committee for approval of a proposed project to install the transmission and distribution wires.  The application shall contain, at minimum, the following information:

     (1) the name, address, and telephone number of the company or organization that owns or operates the proposed project and the name of a contact person for the proposed project;

     (2) information related to the location and land use of the proposed project, as follows:

     (a) the municipality or municipalities, block, and lot number or numbers, as applicable, that would be impacted by the proposed project;

     (b) a key map adequately locating the proposed route of wires to, and from, the proposed project; and

     (c) the land use of areas adjacent to the project site, including the block and lot number of any surrounding parcels of preserved farmland that would be impacted by the proposed project;

     (3) a description of the proposed project, including:

     (a) the type and purpose of the proposed project;

     (b) the phases of the proposed project; and

     (c) the site plan for the proposed project;

     (4) an analysis of alternatives to the installation of wires across preserved farmland, including:

     (a) a description of why there is no practical alternative to installing transmission and distribution wires across preserved farmland; and

     (b) an explanation of other alternatives that were considered and why those alternatives were rejected; and

     (5) written approval from the owner of the preserved farmland on which the transmission and distribution wires would be installed.

     c.  Except as provided in subsection d. of this section, the committee, in consultation with the County Agriculture Development Board or organization that retains the development rights pursuant to the easement in place on each parcel of preserved farmland impacted by the proposed project, as applicable, shall render a decision on an application submitted pursuant to subsection b. of this section within 60 days.

     d.  If the Board of Public Utilities determines that a proposed project is necessary to serve the State's energy needs, 2[the]2 board 2staff2 may file a letter with the committee explaining the public need for the proposed project, and the determination shall be given deference by the committee.  2If the board has issued a board order designating the proposed project as eligible to receive incentives in one of the State's incentive programs, the board may file the order with the committee in place of a letter.2  The Secretary of Agriculture, in the secretary's capacity as chair of the committee, and in consultation with the committee, shall grant approval of the application within 30 days of receiving the 2[board's]2 letter 2or board order, as applicable2.  If the secretary finds that there will be a substantial disruption to preserved farmland resulting from the proposed project as described in the application, the secretary, in consultation with the committee, shall require modifications to the proposed project as a condition of granting approval of the application, as may be necessary and reasonably achievable to allow the proposed project to proceed without undue disruption to the preserved farmland.

     e. An application for a proposed project that has been approved pursuant to this section shall comply with any other applicable laws, regulations, or permit requirements.1

 

     2.  This act shall take effect immediately.