Bill Title: Amends the Environmental Protection Act. Provides that, before an owner or operator may initiate demolition of a thermal power plant via implosion, the owner or operator must satisfy specified notification requirements and obtain an Agency-approved air quality plan. Provides that, at least 30 days after providing notice, an owner or operator must hold at least one public meeting within the municipality in which the site is located to discuss the proposed demolition. Contains requirements for the public meeting and the air quality plan. Requires the air quality plan to include a dust mitigation plan, contingency plan, and site cleanup plan with specified requirements. Contains other provisions. Repeals a provision regarding the notice of power plant demolition. In provisions regarding civil penalties, provides that any person who engages in demolition of a thermal power plant via implosion in violation of the Act shall be liable for a civil penalty of up to $50,000 for the first violation and up to $250,000 for a second or subsequent violation. Effective immediately.
Spectrum: Partisan Bill (Democrat 16-0)
Status: (Introduced - Dead) 2022-03-08 - Added Co-Sponsor Rep. Sam Yingling [HB2767 Detail]
Download: Illinois-2021-HB2767-Introduced.html
| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
1 | AN ACT concerning safety.
| |||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| |||||||||||||||||||
3 | represented in the General Assembly:
| |||||||||||||||||||
4 | Section 5. The Environmental Protection Act is amended by | |||||||||||||||||||
5 | adding Section 40.4 as follows:
| |||||||||||||||||||
6 | (415 ILCS 5/40.4 new) | |||||||||||||||||||
7 | Sec. 40.4. Environmental justice communities; community | |||||||||||||||||||
8 | and environmental impact assessment; notification of | |||||||||||||||||||
9 | applicants; community benefits agreements. | |||||||||||||||||||
10 | (a) The Agency shall ensure that possible adverse | |||||||||||||||||||
11 | economic, social, and environmental effects on environmental | |||||||||||||||||||
12 | justice communities relating to any permit or permit renewal | |||||||||||||||||||
13 | have been fully considered prior to publishing a draft permit | |||||||||||||||||||
14 | or permit renewal for public comment, and that the final | |||||||||||||||||||
15 | decision on the permit or permit renewal is made in the best | |||||||||||||||||||
16 | overall public interest. | |||||||||||||||||||
17 | Any person seeking a permit or permit renewal shall first | |||||||||||||||||||
18 | submit to the Agency information necessary for the Agency to | |||||||||||||||||||
19 | determine if the permitted activity will adversely impact an | |||||||||||||||||||
20 | environmental justice community. | |||||||||||||||||||
21 | (b) Any person or entity seeking a permit or permit | |||||||||||||||||||
22 | renewal in an environmental justice community shall give | |||||||||||||||||||
23 | public notice to the residents of the community of the |
| |||||||
| |||||||
1 | following: | ||||||
2 | (1) The person or entity's permit or permit renewal | ||||||
3 | application. | ||||||
4 | (2) The procedures allowing residents to file comments | ||||||
5 | on the application with the Agency. | ||||||
6 | (3) The date, time, and place of a community meeting | ||||||
7 | for the purpose of informing the surrounding community of | ||||||
8 | the permit application and for taking comments and | ||||||
9 | questions. The meeting shall not be held less than 30 days | ||||||
10 | following publication of the notice. | ||||||
11 | Community residents shall have 90 days following the | ||||||
12 | community meeting to submit comments to the Agency. | ||||||
13 | (c) A permit applicant for permitted activity sited in an | ||||||
14 | environmental justice community shall enter into a community | ||||||
15 | benefits agreement with the unit of local government in whose | ||||||
16 | jurisdiction the permit applicant has applied. The community | ||||||
17 | benefits agreement must, at a minimum, contain provisions | ||||||
18 | requiring the permit applicant to mitigate the environmental | ||||||
19 | and public health impact of the permitted activity in the | ||||||
20 | environmental justice community. | ||||||
21 | (d) For purposes of this Section, "permit" means a permit | ||||||
22 | issued by the Illinois Environmental Protection Agency through | ||||||
23 | the Clean Air Act Permit Program or the National Pollutant | ||||||
24 | Discharge Elimination System.
| ||||||
25 | Section 99. Effective date. This Act takes effect upon | ||||||
26 | becoming law.
|