| 1 | AMENDMENT TO SENATE BILL 321
| ||||||
| 2 | AMENDMENT NO. ______. Amend Senate Bill 321 by replacing | ||||||
| 3 | everything after the enacting clause with the following:
| ||||||
| 4 | "Section 5. The River Edge Redevelopment Zone Act is | ||||||
| 5 | amended by changing Section 10-10.1 as follows:
| ||||||
| 6 | (65 ILCS 115/10-10.1) | ||||||
| 7 | (Section scheduled to be repealed on July 29, 2017) | ||||||
| 8 | Sec. 10-10.1. Utility facilities. | ||||||
| 9 | (a) It is in the public interest that costs for | ||||||
| 10 | redevelopment in a River Edge Redevelopment Zone impacting a | ||||||
| 11 | public utility, as defined by Section 3-105 of the Public | ||||||
| 12 | Utilities Act, or a public utility's property, as described in | ||||||
| 13 | subsection (b) of this Section, should not be allocated solely | ||||||
| 14 | to the entity engaging in economic redevelopment because this | ||||||
| 15 | economic redevelopment benefits the utility service territory | ||||||
| 16 | as a whole and not just the particular area where the | ||||||
| |||||||
| |||||||
| 1 | redevelopment occurs. | ||||||
| 2 | (b) A public utility that has facilities or land affected | ||||||
| 3 | by the clean-up, remediation, and redevelopment of a River Edge | ||||||
| 4 | Redevelopment Zone and that incurs costs related to the | ||||||
| 5 | remediation or the removing or relocating of utility facilities | ||||||
| 6 | in the River Edge Redevelopment Zone may recover these costs | ||||||
| 7 | pursuant to subsections (c) and (d) of this Section. | ||||||
| 8 | (c) The reasonable and prudent costs incurred by a public | ||||||
| 9 | utility for facility removal or relocation described in | ||||||
| 10 | subsection (b) of this Section shall be shared equally among | ||||||
| 11 | the public utility, the municipality in which the facility is | ||||||
| 12 | located, and any landowner that is located within 100 feet of | ||||||
| 13 | the utility facility and that directly benefits from the | ||||||
| 14 | removal or relocation of the utility facility or the | ||||||
| 15 | redevelopment of the public utility's land. In no event shall | ||||||
| 16 | the costs incurred by each municipality or landowner for a | ||||||
| 17 | given project exceed an equal percentage of the total direct, | ||||||
| 18 | indirect, and overhead project costs, or $3,667,000 each, | ||||||
| 19 | whichever amount is less. The reasonable and prudent costs | ||||||
| 20 | incurred by the public utility for facility removal or | ||||||
| 21 | relocation that are not the responsibility of the municipality | ||||||
| 22 | or landowner under this subsection (c) shall be recovered by | ||||||
| 23 | the public utility from all retail customers located in the | ||||||
| 24 | municipality or municipalities in which the removal or | ||||||
| 25 | relocation occurs through an appropriate tariff mechanism, and | ||||||
| 26 | the public utility may record and defer such costs as a | ||||||
| |||||||
| |||||||
| 1 | regulatory asset until they are so recovered. | ||||||
| 2 | (d) The Illinois Commerce Commission shall allow a public | ||||||
| 3 | utility described in subsection (b) to fully recover from all | ||||||
| 4 | retail customers in its service territory all reasonable and | ||||||
| 5 | prudent costs that it incurs in conducting environmental | ||||||
| 6 | remediation in the River Edge Redevelopment Zone related to the | ||||||
| 7 | removal or relocation of utility facilities in the River Edge | ||||||
| 8 | Redevelopment Zone, including, but not limited to, | ||||||
| 9 | transmission and distribution lines, transformers, and poles. | ||||||
| 10 | These environmental remediation costs also include, but are not | ||||||
| 11 | limited to, direct, indirect, and overhead costs calculated by | ||||||
| 12 | the public utility for taxes or other charges, cost adjustments | ||||||
| 13 | made after the project has begun, and any other environmental | ||||||
| 14 | remediation-related charges. The public utility shall record | ||||||
| 15 | and defer such costs as a regulatory asset to be included in | ||||||
| 16 | the public utility's total rate base and amortized in the | ||||||
| 17 | public utility's next filing for a general increase in rates | ||||||
| 18 | over a reasonable period that is shorter than the life of the | ||||||
| 19 | affected facility or facilities. Such regulatory assets shall | ||||||
| 20 | be collected from all residential and commercial ratepayers | ||||||
| 21 | system-wide, and not only from ratepayers in the municipality's | ||||||
| 22 | corporate limits. In the event the River Edge Redevelopment | ||||||
| 23 | Zone is decertified, the public utility shall be permitted to | ||||||
| 24 | recover all reasonable and prudent costs incurred as of the | ||||||
| 25 | date of the decertification, as well as all reasonable and | ||||||
| 26 | prudent costs incurred subsequent to decertification that are | ||||||
| |||||||
| |||||||
| 1 | necessary to complete any projects commenced while the River | ||||||
| 2 | Edge Redevelopment Zone was certified, consistent with this | ||||||
| 3 | Section. | ||||||
| 4 | (e) This Section is repealed on August 1, 2020 7 years | ||||||
| 5 | after the effective date of this amendatory Act of the 96th | ||||||
| 6 | General Assembly.
| ||||||
| 7 | (Source: P.A. 96-1404, eff. 7-29-10.)".
| ||||||