Bill Amendment: IL HB4803 | 2025-2026 | 104th General Assembly
NOTE: For additional amemendments please see the Bill Drafting List
Bill Title: ELECTRIC TRANSMISSION SITING
Status: 2026-04-17 - House Floor Amendment No. 2 Rule 19(c) / Re-referred to Rules Committee [HB4803 Detail]
Download: Illinois-2025-HB4803-House_Amendment_002.html
Bill Title: ELECTRIC TRANSMISSION SITING
Status: 2026-04-17 - House Floor Amendment No. 2 Rule 19(c) / Re-referred to Rules Committee [HB4803 Detail]
Download: Illinois-2025-HB4803-House_Amendment_002.html
| |||||||
| |||||||
| 1 | AMENDMENT TO HOUSE BILL 4803 | ||||||
| 2 | AMENDMENT NO. ______. Amend House Bill 4803, AS AMENDED, | ||||||
| 3 | by replacing everything after the enacting clause with the | ||||||
| 4 | following: | ||||||
| 5 | "Section 1. Short title. This Act may be cited as the | ||||||
| 6 | Electric Transmission Highway Colocation Act. | ||||||
| 7 | Section 5. Definitions. As used in this Section: | ||||||
| 8 | "Agency" means the Department of Transportation or the | ||||||
| 9 | Illinois State Toll Highway Authority, depending on which | ||||||
| 10 | entity a public utility is seeking a right-of-way from. | ||||||
| 11 | "Authority" means the Illinois State Toll Highway | ||||||
| 12 | Authority. | ||||||
| 13 | "Department" means the Illinois Department of | ||||||
| 14 | Transportation. | ||||||
| 15 | "Highway" has the meaning given to that term in Section | ||||||
| 16 | 2-202 of the Illinois Highway Code. | ||||||
| |||||||
| |||||||
| 1 | "High-voltage electric service line" has the meaning given | ||||||
| 2 | to that term in Section 8-406 of the Public Utilities Act. | ||||||
| 3 | "High-voltage transmission infrastructure" means poles, | ||||||
| 4 | wires, cable, or any physical infrastructure associated with a | ||||||
| 5 | high-voltage electric service line. | ||||||
| 6 | "Public utility" has the meaning given to that term in | ||||||
| 7 | Section 3-105 of the Public Utilities Act. | ||||||
| 8 | "Secretary" means the Secretary of Transportation. | ||||||
| 9 | Section 10. High-voltage transmission line colocation | ||||||
| 10 | requests. | ||||||
| 11 | (a) A public utility may construct, place, or maintain a | ||||||
| 12 | high-voltage electric service line on a public right-of-way or | ||||||
| 13 | along a highway if (i) the public utility submits to the | ||||||
| 14 | Secretary or the Authority a colocation request for the | ||||||
| 15 | high-voltage electric service line, (ii) the Secretary or the | ||||||
| 16 | Authority reviews and approves the colocation request, and | ||||||
| 17 | (iii) the Federal Highway Administration does not express | ||||||
| 18 | objection to the request. | ||||||
| 19 | (b) The Secretary or the Authority may deny a colocation | ||||||
| 20 | request under this Section if the Secretary or the Authority | ||||||
| 21 | determines that the construction, placement, or maintenance of | ||||||
| 22 | a high-voltage electric service line on a public right-of-way | ||||||
| 23 | or along a highway would endanger public safety, would | ||||||
| 24 | decrease the efficacy or efficiency of the State's | ||||||
| 25 | transportation network, would prevent possible system | ||||||
| |||||||
| |||||||
| 1 | expansion, would interfere with other public assets, would | ||||||
| 2 | interfere with the optimal function of the highway, or would | ||||||
| 3 | interfere with any current or future Agency project. | ||||||
| 4 | (c) If the Secretary or the Authority denies a colocation | ||||||
| 5 | request under this Section, the Secretary or the Authority | ||||||
| 6 | shall submit the reasons for the denial to the Director of the | ||||||
| 7 | Environmental Protection Agency, the Executive Director of the | ||||||
| 8 | Commission, and the Director of Commerce and Economic | ||||||
| 9 | Opportunity within 90 days after the issuance of the denial. | ||||||
| 10 | Section 15. Consultation and constructability report. | ||||||
| 11 | (a) A public utility may submit a written request, signed | ||||||
| 12 | by a professional engineer who is qualified to perform | ||||||
| 13 | engineering design with the Agency, to the Department or the | ||||||
| 14 | Authority for an evaluation of corridors for possible | ||||||
| 15 | locations for a high-voltage electric service line. The Agency | ||||||
| 16 | shall evaluate each request and respond to the applicable | ||||||
| 17 | public utility. | ||||||
| 18 | (b) The Department or the Authority shall inform a public | ||||||
| 19 | utility about any of the Department's or the Authority's | ||||||
| 20 | current plans or projects that could impact the public | ||||||
| 21 | utility's potential construction or placement of a | ||||||
| 22 | high-voltage electric service line within a corridor. | ||||||
| 23 | (c) After an evaluation under subsection (a) identifies an | ||||||
| 24 | acceptable location within a corridor, a public utility, in | ||||||
| 25 | consultation with the Department or the Authority, shall | ||||||
| |||||||
| |||||||
| 1 | develop a constructability report. The public utility shall be | ||||||
| 2 | assisted by a professional engineer who is qualified to | ||||||
| 3 | perform engineering design with the Agency. The | ||||||
| 4 | constructability report shall include (i) the terms and | ||||||
| 5 | conditions for the siting of the high-voltage electric service | ||||||
| 6 | line to account for the safety, operability, and maintenance | ||||||
| 7 | of highways operated by the Department and the Authority, (ii) | ||||||
| 8 | a plan for addressing and mitigating the impacts of induced | ||||||
| 9 | voltage, and (iii) a plan for the maintenance of the | ||||||
| 10 | high-voltage transmission infrastructure, including access, | ||||||
| 11 | traffic control, vegetation control, and restoration of the | ||||||
| 12 | right-of-way. The Department or the Authority shall issue a | ||||||
| 13 | permit to the public utility for the use of a public | ||||||
| 14 | right-of-way within the corridor for the siting of a | ||||||
| 15 | high-voltage electric service line only after a | ||||||
| 16 | constructability report is approved by the Department or the | ||||||
| 17 | Authority and the public utility. | ||||||
| 18 | (d) A public utility and the Agency shall follow the terms | ||||||
| 19 | and conditions of the approved constructability report during | ||||||
| 20 | the planning and approval process for the siting of a | ||||||
| 21 | high-voltage electric service line. | ||||||
| 22 | Section 20. Relocation and removal. If at any point the | ||||||
| 23 | Agency finds that a public utility is not meeting prescribed | ||||||
| 24 | standards set out in a constructability report, the public | ||||||
| 25 | utility must take corrective action within a timely manner, as | ||||||
| |||||||
| |||||||
| 1 | set out in the constructability report. If the Agency is not | ||||||
| 2 | satisfied with the public utility's corrective action and | ||||||
| 3 | progress, the Agency may revoke the permit provided to the | ||||||
| 4 | public utility and any operation of the high-voltage | ||||||
| 5 | transmission infrastructure must cease. | ||||||
| 6 | Section 25. Project labor agreements. High-voltage | ||||||
| 7 | electric service lines and related facilities constructed or | ||||||
| 8 | placed on a public right-of-way or along a highway in | ||||||
| 9 | accordance with this Act shall be built by general contractors | ||||||
| 10 | who have entered into a project labor agreement prior to | ||||||
| 11 | construction. | ||||||
| 12 | Section 30. Rules. The Department and the Authority may | ||||||
| 13 | adopt rules for the implementation of this Act. | ||||||
| 14 | Section 35. The Public Utilities Act is amended by | ||||||
| 15 | changing Sections 8-406 and 8-406.1 as follows: | ||||||
| 16 | (220 ILCS 5/8-406) (from Ch. 111 2/3, par. 8-406) | ||||||
| 17 | (Text of Section before amendment by P.A. 104-458) | ||||||
| 18 | Sec. 8-406. Certificate of public convenience and | ||||||
| 19 | necessity. | ||||||
| 20 | (a) No public utility not owning any city or village | ||||||
| 21 | franchise nor engaged in performing any public service or in | ||||||
| 22 | furnishing any product or commodity within this State as of | ||||||
| |||||||
| |||||||
| 1 | July 1, 1921 and not possessing a certificate of public | ||||||
| 2 | convenience and necessity from the Illinois Commerce | ||||||
| 3 | Commission, the State Public Utilities Commission, or the | ||||||
| 4 | Public Utilities Commission, at the time Public Act 84-617 | ||||||
| 5 | goes into effect (January 1, 1986), shall transact any | ||||||
| 6 | business in this State until it shall have obtained a | ||||||
| 7 | certificate from the Commission that public convenience and | ||||||
| 8 | necessity require the transaction of such business. A | ||||||
| 9 | certificate of public convenience and necessity requiring the | ||||||
| 10 | transaction of public utility business in any area of this | ||||||
| 11 | State shall include authorization to the public utility | ||||||
| 12 | receiving the certificate of public convenience and necessity | ||||||
| 13 | to construct such plant, equipment, property, or facility as | ||||||
| 14 | is provided for under the terms and conditions of its tariff | ||||||
| 15 | and as is necessary to provide utility service and carry out | ||||||
| 16 | the transaction of public utility business by the public | ||||||
| 17 | utility in the designated area. | ||||||
| 18 | (b) No public utility shall begin the construction of any | ||||||
| 19 | new plant, equipment, property, or facility which is not in | ||||||
| 20 | substitution of any existing plant, equipment, property, or | ||||||
| 21 | facility, or any extension or alteration thereof or in | ||||||
| 22 | addition thereto, unless and until it shall have obtained from | ||||||
| 23 | the Commission a certificate that public convenience and | ||||||
| 24 | necessity require such construction. Whenever after a hearing | ||||||
| 25 | the Commission determines that any new construction or the | ||||||
| 26 | transaction of any business by a public utility will promote | ||||||
| |||||||
| |||||||
| 1 | the public convenience and is necessary thereto, it shall have | ||||||
| 2 | the power to issue certificates of public convenience and | ||||||
| 3 | necessity. The Commission shall determine that proposed | ||||||
| 4 | construction will promote the public convenience and necessity | ||||||
| 5 | only if the utility demonstrates: (1) that the proposed | ||||||
| 6 | construction is necessary to provide adequate, reliable, and | ||||||
| 7 | efficient service to its customers and is the least-cost means | ||||||
| 8 | of satisfying the service needs of its customers or that the | ||||||
| 9 | proposed construction will promote the development of an | ||||||
| 10 | effectively competitive electricity market that operates | ||||||
| 11 | efficiently, is equitable to all customers, and is the least | ||||||
| 12 | cost means of satisfying those objectives; (2) that the | ||||||
| 13 | utility is capable of efficiently managing and supervising the | ||||||
| 14 | construction process and has taken sufficient action to ensure | ||||||
| 15 | adequate and efficient construction and supervision thereof; | ||||||
| 16 | and (3) that the utility is capable of financing the proposed | ||||||
| 17 | construction without significant adverse financial | ||||||
| 18 | consequences for the utility or its customers. | ||||||
| 19 | (b-5) As used in this subsection (b-5): | ||||||
| 20 | "Qualifying direct current applicant" means an entity that | ||||||
| 21 | seeks to provide direct current bulk transmission service for | ||||||
| 22 | the purpose of transporting electric energy in interstate | ||||||
| 23 | commerce. | ||||||
| 24 | "Qualifying direct current project" means a high voltage | ||||||
| 25 | direct current electric service line that crosses at least one | ||||||
| 26 | Illinois border, the Illinois portion of which is physically | ||||||
| |||||||
| |||||||
| 1 | located within the region of the Midcontinent Independent | ||||||
| 2 | System Operator, Inc., or its successor organization, and runs | ||||||
| 3 | through the counties of Pike, Scott, Greene, Macoupin, | ||||||
| 4 | Montgomery, Christian, Shelby, Cumberland, and Clark, is | ||||||
| 5 | capable of transmitting electricity at voltages of 345 | ||||||
| 6 | kilovolts or above, and may also include associated | ||||||
| 7 | interconnected alternating current interconnection facilities | ||||||
| 8 | in this State that are part of the proposed project and | ||||||
| 9 | reasonably necessary to connect the project with other | ||||||
| 10 | portions of the grid. | ||||||
| 11 | Notwithstanding any other provision of this Act, a | ||||||
| 12 | qualifying direct current applicant that does not own, | ||||||
| 13 | control, operate, or manage, within this State, any plant, | ||||||
| 14 | equipment, or property used or to be used for the transmission | ||||||
| 15 | of electricity at the time of its application or of the | ||||||
| 16 | Commission's order may file an application on or before | ||||||
| 17 | December 31, 2023 with the Commission pursuant to this Section | ||||||
| 18 | or Section 8-406.1 for, and the Commission may grant, a | ||||||
| 19 | certificate of public convenience and necessity to construct, | ||||||
| 20 | operate, and maintain a qualifying direct current project. The | ||||||
| 21 | qualifying direct current applicant may also include in the | ||||||
| 22 | application requests for authority under Section 8-503. The | ||||||
| 23 | Commission shall grant the application for a certificate of | ||||||
| 24 | public convenience and necessity and requests for authority | ||||||
| 25 | under Section 8-503 if it finds that the qualifying direct | ||||||
| 26 | current applicant and the proposed qualifying direct current | ||||||
| |||||||
| |||||||
| 1 | project satisfy the requirements of this subsection and | ||||||
| 2 | otherwise satisfy the criteria of this Section or Section | ||||||
| 3 | 8-406.1 and the criteria of Section 8-503, as applicable to | ||||||
| 4 | the application and to the extent such criteria are not | ||||||
| 5 | superseded by the provisions of this subsection. The | ||||||
| 6 | Commission's order on the application for the certificate of | ||||||
| 7 | public convenience and necessity shall also include the | ||||||
| 8 | Commission's findings and determinations on the request or | ||||||
| 9 | requests for authority pursuant to Section 8-503. Prior to | ||||||
| 10 | filing its application under either this Section or Section | ||||||
| 11 | 8-406.1, the qualifying direct current applicant shall conduct | ||||||
| 12 | 3 public meetings in accordance with subsection (h) of this | ||||||
| 13 | Section. If the qualifying direct current applicant | ||||||
| 14 | demonstrates in its application that the proposed qualifying | ||||||
| 15 | direct current project is designed to deliver electricity to a | ||||||
| 16 | point or points on the electric transmission grid in either or | ||||||
| 17 | both the PJM Interconnection, LLC or the Midcontinent | ||||||
| 18 | Independent System Operator, Inc., or their respective | ||||||
| 19 | successor organizations, the proposed qualifying direct | ||||||
| 20 | current project shall be deemed to be, and the Commission | ||||||
| 21 | shall find it to be, for public use. If the qualifying direct | ||||||
| 22 | current applicant further demonstrates in its application that | ||||||
| 23 | the proposed transmission project has a capacity of 1,000 | ||||||
| 24 | megawatts or larger and a voltage level of 345 kilovolts or | ||||||
| 25 | greater, the proposed transmission project shall be deemed to | ||||||
| 26 | satisfy, and the Commission shall find that it satisfies, the | ||||||
| |||||||
| |||||||
| 1 | criteria stated in item (1) of subsection (b) of this Section | ||||||
| 2 | or in paragraph (1) of subsection (f) of Section 8-406.1, as | ||||||
| 3 | applicable to the application, without the taking of | ||||||
| 4 | additional evidence on these criteria. Prior to the transfer | ||||||
| 5 | of functional control of any transmission assets to a regional | ||||||
| 6 | transmission organization, a qualifying direct current | ||||||
| 7 | applicant shall request Commission approval to join a regional | ||||||
| 8 | transmission organization in an application filed pursuant to | ||||||
| 9 | this subsection (b-5) or separately pursuant to Section 7-102 | ||||||
| 10 | of this Act. The Commission may grant permission to a | ||||||
| 11 | qualifying direct current applicant to join a regional | ||||||
| 12 | transmission organization if it finds that the membership, and | ||||||
| 13 | associated transfer of functional control of transmission | ||||||
| 14 | assets, benefits Illinois customers in light of the attendant | ||||||
| 15 | costs and is otherwise in the public interest. Nothing in this | ||||||
| 16 | subsection (b-5) requires a qualifying direct current | ||||||
| 17 | applicant to join a regional transmission organization. | ||||||
| 18 | Nothing in this subsection (b-5) requires the owner or | ||||||
| 19 | operator of a high voltage direct current transmission line | ||||||
| 20 | that is not a qualifying direct current project to obtain a | ||||||
| 21 | certificate of public convenience and necessity to the extent | ||||||
| 22 | it is not otherwise required by this Section 8-406 or any other | ||||||
| 23 | provision of this Act. | ||||||
| 24 | (c) As used in this subsection (c): | ||||||
| 25 | "Decommissioning" has the meaning given to that term in | ||||||
| 26 | subsection (a) of Section 8-508.1. | ||||||
| |||||||
| |||||||
| 1 | "Nuclear power reactor" has the meaning given to that term | ||||||
| 2 | in Section 8 of the Nuclear Safety Law of 2004. | ||||||
| 3 | After the effective date of this amendatory Act of the | ||||||
| 4 | 103rd General Assembly, no construction shall commence on any | ||||||
| 5 | new nuclear power reactor with a nameplate capacity of more | ||||||
| 6 | than 300 megawatts of electricity to be located within this | ||||||
| 7 | State, and no certificate of public convenience and necessity | ||||||
| 8 | or other authorization shall be issued therefor by the | ||||||
| 9 | Commission, until the Illinois Emergency Management Agency and | ||||||
| 10 | Office of Homeland Security, in consultation with the Illinois | ||||||
| 11 | Environmental Protection Agency and the Illinois Department of | ||||||
| 12 | Natural Resources, finds that the United States Government, | ||||||
| 13 | through its authorized agency, has identified and approved a | ||||||
| 14 | demonstrable technology or means for the disposal of high | ||||||
| 15 | level nuclear waste, or until such construction has been | ||||||
| 16 | specifically approved by a statute enacted by the General | ||||||
| 17 | Assembly. Beginning January 1, 2026, construction may commence | ||||||
| 18 | on a new nuclear power reactor with a nameplate capacity of 300 | ||||||
| 19 | megawatts of electricity or less within this State if the | ||||||
| 20 | entity constructing the new nuclear power reactor has obtained | ||||||
| 21 | all permits, licenses, permissions, or approvals governing the | ||||||
| 22 | construction, operation, and funding of decommissioning of | ||||||
| 23 | such nuclear power reactors required by: (1) this Act; (2) any | ||||||
| 24 | rules adopted by the Illinois Emergency Management Agency and | ||||||
| 25 | Office of Homeland Security under the authority of this Act; | ||||||
| 26 | (3) any applicable federal statutes, including, but not | ||||||
| |||||||
| |||||||
| 1 | limited to, the Atomic Energy Act of 1954, the Energy | ||||||
| 2 | Reorganization Act of 1974, the Low-Level Radioactive Waste | ||||||
| 3 | Policy Amendments Act of 1985, and the Energy Policy Act of | ||||||
| 4 | 1992; (4) any regulations promulgated or enforced by the U.S. | ||||||
| 5 | Nuclear Regulatory Commission, including, but not limited to, | ||||||
| 6 | those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of | ||||||
| 7 | the Code of Federal Regulations, as from time to time amended; | ||||||
| 8 | and (5) any other federal or State statute, rule, or | ||||||
| 9 | regulation governing the permitting, licensing, operation, or | ||||||
| 10 | decommissioning of such nuclear power reactors. None of the | ||||||
| 11 | rules developed by the Illinois Emergency Management Agency | ||||||
| 12 | and Office of Homeland Security or any other State agency, | ||||||
| 13 | board, or commission pursuant to this Act shall be construed | ||||||
| 14 | to supersede the authority of the U.S. Nuclear Regulatory | ||||||
| 15 | Commission. The changes made by this amendatory Act of the | ||||||
| 16 | 103rd General Assembly shall not apply to the uprate, renewal, | ||||||
| 17 | or subsequent renewal of any license for an existing nuclear | ||||||
| 18 | power reactor that began operation prior to the effective date | ||||||
| 19 | of this amendatory Act of the 103rd General Assembly. | ||||||
| 20 | None of the changes made in this amendatory Act of the | ||||||
| 21 | 103rd General Assembly are intended to authorize the | ||||||
| 22 | construction of nuclear power plants powered by nuclear power | ||||||
| 23 | reactors that are not either: (1) small modular nuclear | ||||||
| 24 | reactors; or (2) nuclear power reactors licensed by the U.S. | ||||||
| 25 | Nuclear Regulatory Commission to operate in this State prior | ||||||
| 26 | to the effective date of this amendatory Act of the 103rd | ||||||
| |||||||
| |||||||
| 1 | General Assembly. | ||||||
| 2 | (d) In making its determination under subsection (b) of | ||||||
| 3 | this Section, the Commission shall attach primary weight to | ||||||
| 4 | the cost or cost savings to the customers of the utility. The | ||||||
| 5 | Commission may consider any or all factors which will or may | ||||||
| 6 | affect such cost or cost savings, including the public | ||||||
| 7 | utility's engineering judgment regarding the materials used | ||||||
| 8 | for construction. | ||||||
| 9 | (e) The Commission may issue a temporary certificate which | ||||||
| 10 | shall remain in force not to exceed one year in cases of | ||||||
| 11 | emergency, to assure maintenance of adequate service or to | ||||||
| 12 | serve particular customers, without notice or hearing, pending | ||||||
| 13 | the determination of an application for a certificate, and may | ||||||
| 14 | by regulation exempt from the requirements of this Section | ||||||
| 15 | temporary acts or operations for which the issuance of a | ||||||
| 16 | certificate will not be required in the public interest. | ||||||
| 17 | A public utility shall not be required to obtain but may | ||||||
| 18 | apply for and obtain a certificate of public convenience and | ||||||
| 19 | necessity pursuant to this Section with respect to any matter | ||||||
| 20 | as to which it has received the authorization or order of the | ||||||
| 21 | Commission under the Electric Supplier Act, and any such | ||||||
| 22 | authorization or order granted a public utility by the | ||||||
| 23 | Commission under that Act shall as between public utilities be | ||||||
| 24 | deemed to be, and shall have except as provided in that Act the | ||||||
| 25 | same force and effect as, a certificate of public convenience | ||||||
| 26 | and necessity issued pursuant to this Section. | ||||||
| |||||||
| |||||||
| 1 | No electric cooperative shall be made or shall become a | ||||||
| 2 | party to or shall be entitled to be heard or to otherwise | ||||||
| 3 | appear or participate in any proceeding initiated under this | ||||||
| 4 | Section for authorization of power plant construction and as | ||||||
| 5 | to matters as to which a remedy is available under the Electric | ||||||
| 6 | Supplier Act. | ||||||
| 7 | (f) Such certificates may be altered or modified by the | ||||||
| 8 | Commission, upon its own motion or upon application by the | ||||||
| 9 | person or corporation affected. Unless exercised within a | ||||||
| 10 | period of 2 years from the grant thereof, authority conferred | ||||||
| 11 | by a certificate of convenience and necessity issued by the | ||||||
| 12 | Commission shall be null and void. | ||||||
| 13 | No certificate of public convenience and necessity shall | ||||||
| 14 | be construed as granting a monopoly or an exclusive privilege, | ||||||
| 15 | immunity or franchise. | ||||||
| 16 | (g) A public utility that undertakes any of the actions | ||||||
| 17 | described in items (1) through (3) of this subsection (g) or | ||||||
| 18 | that has obtained approval pursuant to Section 8-406.1 of this | ||||||
| 19 | Act shall not be required to comply with the requirements of | ||||||
| 20 | this Section to the extent such requirements otherwise would | ||||||
| 21 | apply. For purposes of this Section and Section 8-406.1 of | ||||||
| 22 | this Act, "high voltage electric service line" means an | ||||||
| 23 | electric line having a design voltage of 100,000 or more. For | ||||||
| 24 | purposes of this subsection (g), a public utility may do any of | ||||||
| 25 | the following: | ||||||
| 26 | (1) replace or upgrade any existing high voltage | ||||||
| |||||||
| |||||||
| 1 | electric service line and related facilities, | ||||||
| 2 | notwithstanding its length; | ||||||
| 3 | (2) relocate any existing high voltage electric | ||||||
| 4 | service line and related facilities, notwithstanding its | ||||||
| 5 | length, to accommodate construction or expansion of a | ||||||
| 6 | roadway or other transportation infrastructure; or | ||||||
| 7 | (3) construct a high voltage electric service line and | ||||||
| 8 | related facilities that is constructed solely to serve a | ||||||
| 9 | single customer's premises or to provide a generator | ||||||
| 10 | interconnection to the public utility's transmission | ||||||
| 11 | system and that will pass under or over the premises owned | ||||||
| 12 | by the customer or generator to be served or under or over | ||||||
| 13 | premises for which the customer or generator has secured | ||||||
| 14 | the necessary right of way. | ||||||
| 15 | (h) A public utility seeking to construct a high-voltage | ||||||
| 16 | electric service line and related facilities (Project) must | ||||||
| 17 | show that the utility has held a minimum of 2 pre-filing public | ||||||
| 18 | meetings to receive public comment concerning the Project in | ||||||
| 19 | each county where the Project is to be located, no earlier than | ||||||
| 20 | 6 months prior to filing an application for a certificate of | ||||||
| 21 | public convenience and necessity from the Commission. Notice | ||||||
| 22 | of the public meeting shall be published in a newspaper of | ||||||
| 23 | general circulation within the affected county once a week for | ||||||
| 24 | 3 consecutive weeks, beginning no earlier than one month prior | ||||||
| 25 | to the first public meeting. If the Project traverses 2 | ||||||
| 26 | contiguous counties and where in one county the transmission | ||||||
| |||||||
| |||||||
| 1 | line mileage and number of landowners over whose property the | ||||||
| 2 | proposed route traverses is one-fifth or less of the | ||||||
| 3 | transmission line mileage and number of such landowners of the | ||||||
| 4 | other county, then the utility may combine the 2 pre-filing | ||||||
| 5 | meetings in the county with the greater transmission line | ||||||
| 6 | mileage and affected landowners. All other requirements | ||||||
| 7 | regarding pre-filing meetings shall apply in both counties. | ||||||
| 8 | Notice of the public meeting, including a description of the | ||||||
| 9 | Project, must be provided in writing to the clerk of each | ||||||
| 10 | county where the Project is to be located. A representative of | ||||||
| 11 | the Commission shall be invited to each pre-filing public | ||||||
| 12 | meeting. | ||||||
| 13 | (h-5) A public utility seeking to construct a high-voltage | ||||||
| 14 | electric service line and related facilities must also show | ||||||
| 15 | that the Project has complied with training and competence | ||||||
| 16 | requirements under subsection (b) of Section 15 of the | ||||||
| 17 | Electric Transmission Systems Construction Standards Act. | ||||||
| 18 | (h-10) A public utility may be permitted to use highway | ||||||
| 19 | corridors for the purposes of constructing a high-voltage | ||||||
| 20 | electric service line and related facilities. | ||||||
| 21 | (h-15) A public utility seeking to construct a | ||||||
| 22 | high-voltage electric service line and related facilities must | ||||||
| 23 | consider corridors of development in the following order of | ||||||
| 24 | priority: | ||||||
| 25 | (1) existing utility corridors, where adding new lines | ||||||
| 26 | or making improvements to existing lines can achieve | ||||||
| |||||||
| |||||||
| 1 | expanded electric capacity at the lowest possible cost; | ||||||
| 2 | (2) highway corridors; and | ||||||
| 3 | (3) new utility corridors. | ||||||
| 4 | Consideration of corridors shall be done, to the greatest | ||||||
| 5 | extent possible, in a manner that accounts for economic and | ||||||
| 6 | engineering considerations, the reliability of the electric | ||||||
| 7 | system, and the protection of the environment. | ||||||
| 8 | (i) For applications filed after August 18, 2015 (the | ||||||
| 9 | effective date of Public Act 99-399), the Commission shall, by | ||||||
| 10 | certified mail, notify each owner of record of land, as | ||||||
| 11 | identified in the records of the relevant county tax assessor, | ||||||
| 12 | included in the right-of-way over which the utility seeks in | ||||||
| 13 | its application to construct a high-voltage electric line of | ||||||
| 14 | the time and place scheduled for the initial hearing on the | ||||||
| 15 | public utility's application. The utility shall reimburse the | ||||||
| 16 | Commission for the cost of the postage and supplies incurred | ||||||
| 17 | for mailing the notice. | ||||||
| 18 | (Source: P.A. 102-609, eff. 8-27-21; 102-662, eff. 9-15-21; | ||||||
| 19 | 102-813, eff. 5-13-22; 102-931, eff. 5-27-22; 103-569, eff. | ||||||
| 20 | 6-1-24; 103-1066, eff. 2-20-25.) | ||||||
| 21 | (Text of Section after amendment by P.A. 104-458) | ||||||
| 22 | Sec. 8-406. Certificate of public convenience and | ||||||
| 23 | necessity. | ||||||
| 24 | (a) No public utility not owning any city or village | ||||||
| 25 | franchise nor engaged in performing any public service or in | ||||||
| |||||||
| |||||||
| 1 | furnishing any product or commodity within this State as of | ||||||
| 2 | July 1, 1921 and not possessing a certificate of public | ||||||
| 3 | convenience and necessity from the Illinois Commerce | ||||||
| 4 | Commission, the State Public Utilities Commission, or the | ||||||
| 5 | Public Utilities Commission, at the time Public Act 84-617 | ||||||
| 6 | goes into effect (January 1, 1986), shall transact any | ||||||
| 7 | business in this State until it shall have obtained a | ||||||
| 8 | certificate from the Commission that public convenience and | ||||||
| 9 | necessity require the transaction of such business. A | ||||||
| 10 | certificate of public convenience and necessity requiring the | ||||||
| 11 | transaction of public utility business in any area of this | ||||||
| 12 | State shall include authorization to the public utility | ||||||
| 13 | receiving the certificate of public convenience and necessity | ||||||
| 14 | to construct such plant, equipment, property, or facility as | ||||||
| 15 | is provided for under the terms and conditions of its tariff | ||||||
| 16 | and as is necessary to provide utility service and carry out | ||||||
| 17 | the transaction of public utility business by the public | ||||||
| 18 | utility in the designated area. | ||||||
| 19 | (b) No public utility shall begin the construction of any | ||||||
| 20 | new plant, equipment, property, or facility which is not in | ||||||
| 21 | substitution of any existing plant, equipment, property, or | ||||||
| 22 | facility, or any extension or alteration thereof or in | ||||||
| 23 | addition thereto, unless and until it shall have obtained from | ||||||
| 24 | the Commission a certificate that public convenience and | ||||||
| 25 | necessity require such construction. Whenever after a hearing | ||||||
| 26 | the Commission determines that any new construction or the | ||||||
| |||||||
| |||||||
| 1 | transaction of any business by a public utility will promote | ||||||
| 2 | the public convenience and is necessary thereto, it shall have | ||||||
| 3 | the power to issue certificates of public convenience and | ||||||
| 4 | necessity. The Commission shall determine that proposed | ||||||
| 5 | construction will promote the public convenience and necessity | ||||||
| 6 | only if the utility demonstrates: (1) that the proposed | ||||||
| 7 | construction is necessary to provide adequate, reliable, and | ||||||
| 8 | efficient service to its customers and is the least-cost means | ||||||
| 9 | of satisfying the service needs of its customers or that the | ||||||
| 10 | proposed construction will promote the development of an | ||||||
| 11 | effectively competitive electricity market that operates | ||||||
| 12 | efficiently, is equitable to all customers, and is the | ||||||
| 13 | least-cost means of satisfying those objectives; (2) that the | ||||||
| 14 | utility is capable of efficiently managing and supervising the | ||||||
| 15 | construction process and has taken sufficient action to ensure | ||||||
| 16 | adequate and efficient construction and supervision thereof; | ||||||
| 17 | and (3) that the utility is capable of financing the proposed | ||||||
| 18 | construction without significant adverse financial | ||||||
| 19 | consequences for the utility or its customers. | ||||||
| 20 | (b-5) As used in this subsection (b-5): | ||||||
| 21 | "Qualifying direct current applicant" means an entity that | ||||||
| 22 | seeks to provide direct current bulk transmission service for | ||||||
| 23 | the purpose of transporting electric energy in interstate | ||||||
| 24 | commerce. | ||||||
| 25 | "Qualifying direct current project" means a high voltage | ||||||
| 26 | direct current electric service line that crosses at least one | ||||||
| |||||||
| |||||||
| 1 | Illinois border, the Illinois portion of which is physically | ||||||
| 2 | located within the region of the Midcontinent Independent | ||||||
| 3 | System Operator, Inc., or its successor organization, and runs | ||||||
| 4 | through the counties of Pike, Scott, Greene, Macoupin, | ||||||
| 5 | Montgomery, Christian, Shelby, Cumberland, and Clark, is | ||||||
| 6 | capable of transmitting electricity at voltages of 345 | ||||||
| 7 | kilovolts or above, and may also include associated | ||||||
| 8 | interconnected alternating current interconnection facilities | ||||||
| 9 | in this State that are part of the proposed project and | ||||||
| 10 | reasonably necessary to connect the project with other | ||||||
| 11 | portions of the grid. | ||||||
| 12 | Notwithstanding any other provision of this Act, a | ||||||
| 13 | qualifying direct current applicant that does not own, | ||||||
| 14 | control, operate, or manage, within this State, any plant, | ||||||
| 15 | equipment, or property used or to be used for the transmission | ||||||
| 16 | of electricity at the time of its application or of the | ||||||
| 17 | Commission's order may file an application on or before | ||||||
| 18 | December 31, 2023 with the Commission pursuant to this Section | ||||||
| 19 | or Section 8-406.1 for, and the Commission may grant, a | ||||||
| 20 | certificate of public convenience and necessity to construct, | ||||||
| 21 | operate, and maintain a qualifying direct current project. The | ||||||
| 22 | qualifying direct current applicant may also include in the | ||||||
| 23 | application requests for authority under Section 8-503. The | ||||||
| 24 | Commission shall grant the application for a certificate of | ||||||
| 25 | public convenience and necessity and requests for authority | ||||||
| 26 | under Section 8-503 if it finds that the qualifying direct | ||||||
| |||||||
| |||||||
| 1 | current applicant and the proposed qualifying direct current | ||||||
| 2 | project satisfy the requirements of this subsection and | ||||||
| 3 | otherwise satisfy the criteria of this Section or Section | ||||||
| 4 | 8-406.1 and the criteria of Section 8-503, as applicable to | ||||||
| 5 | the application and to the extent such criteria are not | ||||||
| 6 | superseded by the provisions of this subsection. The | ||||||
| 7 | Commission's order on the application for the certificate of | ||||||
| 8 | public convenience and necessity shall also include the | ||||||
| 9 | Commission's findings and determinations on the request or | ||||||
| 10 | requests for authority pursuant to Section 8-503. Prior to | ||||||
| 11 | filing its application under either this Section or Section | ||||||
| 12 | 8-406.1, the qualifying direct current applicant shall conduct | ||||||
| 13 | 3 public meetings in accordance with subsection (h) of this | ||||||
| 14 | Section. If the qualifying direct current applicant | ||||||
| 15 | demonstrates in its application that the proposed qualifying | ||||||
| 16 | direct current project is designed to deliver electricity to a | ||||||
| 17 | point or points on the electric transmission grid in either or | ||||||
| 18 | both the PJM Interconnection, LLC or the Midcontinent | ||||||
| 19 | Independent System Operator, Inc., or their respective | ||||||
| 20 | successor organizations, the proposed qualifying direct | ||||||
| 21 | current project shall be deemed to be, and the Commission | ||||||
| 22 | shall find it to be, for public use. If the qualifying direct | ||||||
| 23 | current applicant further demonstrates in its application that | ||||||
| 24 | the proposed transmission project has a capacity of 1,000 | ||||||
| 25 | megawatts or larger and a voltage level of 345 kilovolts or | ||||||
| 26 | greater, the proposed transmission project shall be deemed to | ||||||
| |||||||
| |||||||
| 1 | satisfy, and the Commission shall find that it satisfies, the | ||||||
| 2 | criteria stated in item (1) of subsection (b) of this Section | ||||||
| 3 | or in paragraph (1) of subsection (f) of Section 8-406.1, as | ||||||
| 4 | applicable to the application, without the taking of | ||||||
| 5 | additional evidence on these criteria. Prior to the transfer | ||||||
| 6 | of functional control of any transmission assets to a regional | ||||||
| 7 | transmission organization, a qualifying direct current | ||||||
| 8 | applicant shall request Commission approval to join a regional | ||||||
| 9 | transmission organization in an application filed pursuant to | ||||||
| 10 | this subsection (b-5) or separately pursuant to Section 7-102 | ||||||
| 11 | of this Act. The Commission may grant permission to a | ||||||
| 12 | qualifying direct current applicant to join a regional | ||||||
| 13 | transmission organization if it finds that the membership, and | ||||||
| 14 | associated transfer of functional control of transmission | ||||||
| 15 | assets, benefits Illinois customers in light of the attendant | ||||||
| 16 | costs and is otherwise in the public interest. Nothing in this | ||||||
| 17 | subsection (b-5) requires a qualifying direct current | ||||||
| 18 | applicant to join a regional transmission organization. | ||||||
| 19 | Nothing in this subsection (b-5) requires the owner or | ||||||
| 20 | operator of a high voltage direct current transmission line | ||||||
| 21 | that is not a qualifying direct current project to obtain a | ||||||
| 22 | certificate of public convenience and necessity to the extent | ||||||
| 23 | it is not otherwise required by this Section 8-406 or any other | ||||||
| 24 | provision of this Act. | ||||||
| 25 | (c) As used in this subsection (c): | ||||||
| 26 | "Decommissioning" has the meaning given to that term in | ||||||
| |||||||
| |||||||
| 1 | subsection (a) of Section 8-508.1. | ||||||
| 2 | "Nuclear power reactor" has the meaning given to that term | ||||||
| 3 | in Section 8 of the Nuclear Safety Law of 2004. | ||||||
| 4 | Beginning January 1, 2026, construction may commence on a | ||||||
| 5 | new nuclear power reactor within this State if the entity | ||||||
| 6 | constructing the new nuclear power reactor has obtained all | ||||||
| 7 | permits, licenses, permissions, or approvals governing the | ||||||
| 8 | construction, operation, and funding of decommissioning of | ||||||
| 9 | such nuclear power reactors required by: (1) this Act; (2) any | ||||||
| 10 | rules adopted by the Illinois Emergency Management Agency and | ||||||
| 11 | Office of Homeland Security under the authority of this Act; | ||||||
| 12 | (3) any applicable federal statutes, including, but not | ||||||
| 13 | limited to, the Atomic Energy Act of 1954, the Energy | ||||||
| 14 | Reorganization Act of 1974, the Low-Level Radioactive Waste | ||||||
| 15 | Policy Amendments Act of 1985, and the Energy Policy Act of | ||||||
| 16 | 1992; (4) any regulations promulgated or enforced by the U.S. | ||||||
| 17 | Nuclear Regulatory Commission, including, but not limited to, | ||||||
| 18 | those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of | ||||||
| 19 | the Code of Federal Regulations, as from time to time amended; | ||||||
| 20 | and (5) any other federal or State statute, rule, or | ||||||
| 21 | regulation governing the permitting, licensing, operation, or | ||||||
| 22 | decommissioning of such nuclear power reactors. None of the | ||||||
| 23 | rules developed by the Illinois Emergency Management Agency | ||||||
| 24 | and Office of Homeland Security or any other State agency, | ||||||
| 25 | board, or commission pursuant to this Act shall be construed | ||||||
| 26 | to supersede the authority of the U.S. Nuclear Regulatory | ||||||
| |||||||
| |||||||
| 1 | Commission. The changes made by this amendatory Act of the | ||||||
| 2 | 103rd General Assembly shall not apply to the uprate, renewal, | ||||||
| 3 | or subsequent renewal of any license for an existing nuclear | ||||||
| 4 | power reactor that began operation prior to the effective date | ||||||
| 5 | of this amendatory Act of the 103rd General Assembly. | ||||||
| 6 | None of the changes made in this amendatory Act of the | ||||||
| 7 | 104th General Assembly are intended to authorize the | ||||||
| 8 | construction of nuclear power plants powered by nuclear power | ||||||
| 9 | reactors that are not nuclear power reactors licensed by the | ||||||
| 10 | U.S. Nuclear Regulatory Commission to operate in this State. | ||||||
| 11 | (d) In making its determination under subsection (b) of | ||||||
| 12 | this Section, the Commission shall attach primary weight to | ||||||
| 13 | the cost or cost savings to the customers of the utility. The | ||||||
| 14 | Commission may consider any or all factors which will or may | ||||||
| 15 | affect such cost or cost savings, including the public | ||||||
| 16 | utility's engineering judgment regarding the materials used | ||||||
| 17 | for construction. | ||||||
| 18 | (e) The Commission may issue a temporary certificate which | ||||||
| 19 | shall remain in force not to exceed one year in cases of | ||||||
| 20 | emergency, to assure maintenance of adequate service or to | ||||||
| 21 | serve particular customers, without notice or hearing, pending | ||||||
| 22 | the determination of an application for a certificate, and may | ||||||
| 23 | by regulation exempt from the requirements of this Section | ||||||
| 24 | temporary acts or operations for which the issuance of a | ||||||
| 25 | certificate will not be required in the public interest. | ||||||
| 26 | A public utility shall not be required to obtain but may | ||||||
| |||||||
| |||||||
| 1 | apply for and obtain a certificate of public convenience and | ||||||
| 2 | necessity pursuant to this Section with respect to any matter | ||||||
| 3 | as to which it has received the authorization or order of the | ||||||
| 4 | Commission under the Electric Supplier Act, and any such | ||||||
| 5 | authorization or order granted a public utility by the | ||||||
| 6 | Commission under that Act shall as between public utilities be | ||||||
| 7 | deemed to be, and shall have except as provided in that Act the | ||||||
| 8 | same force and effect as, a certificate of public convenience | ||||||
| 9 | and necessity issued pursuant to this Section. | ||||||
| 10 | No electric cooperative shall be made or shall become a | ||||||
| 11 | party to or shall be entitled to be heard or to otherwise | ||||||
| 12 | appear or participate in any proceeding initiated under this | ||||||
| 13 | Section for authorization of power plant construction and as | ||||||
| 14 | to matters as to which a remedy is available under the Electric | ||||||
| 15 | Supplier Act. | ||||||
| 16 | (f) Such certificates may be altered or modified by the | ||||||
| 17 | Commission, upon its own motion or upon application by the | ||||||
| 18 | person or corporation affected. Unless exercised within a | ||||||
| 19 | period of 2 years from the grant thereof, authority conferred | ||||||
| 20 | by a certificate of convenience and necessity issued by the | ||||||
| 21 | Commission shall be null and void. | ||||||
| 22 | No certificate of public convenience and necessity shall | ||||||
| 23 | be construed as granting a monopoly or an exclusive privilege, | ||||||
| 24 | immunity or franchise. | ||||||
| 25 | (g) A public utility that undertakes any of the actions | ||||||
| 26 | described in items (1) through (3) of this subsection (g) or | ||||||
| |||||||
| |||||||
| 1 | that has obtained approval pursuant to Section 8-406.1 of this | ||||||
| 2 | Act shall not be required to comply with the requirements of | ||||||
| 3 | this Section to the extent such requirements otherwise would | ||||||
| 4 | apply. For purposes of this Section and Section 8-406.1 of | ||||||
| 5 | this Act, "high voltage electric service line" means an | ||||||
| 6 | electric line having a design voltage of 69,000 or more. For | ||||||
| 7 | purposes of this subsection (g), a public utility may do any of | ||||||
| 8 | the following: | ||||||
| 9 | (1) replace or upgrade any existing high voltage | ||||||
| 10 | electric service line and related facilities, | ||||||
| 11 | notwithstanding its length or, subject to applicable | ||||||
| 12 | Article VII requirements, ownership; | ||||||
| 13 | (2) relocate any existing high voltage electric | ||||||
| 14 | service line and related facilities, notwithstanding its | ||||||
| 15 | length, to accommodate construction or expansion of a | ||||||
| 16 | roadway or other transportation infrastructure; or | ||||||
| 17 | (3) construct a high voltage electric service line and | ||||||
| 18 | related facilities that is constructed solely to serve a | ||||||
| 19 | single customer's premises or to provide a generator | ||||||
| 20 | interconnection to the public utility's transmission | ||||||
| 21 | system and that will (i) pass under or over the premises | ||||||
| 22 | owned by the customer or generator to be served; (ii) pass | ||||||
| 23 | under or over premises for which the customer or generator | ||||||
| 24 | has secured the necessary right-of-way; or (iii) be | ||||||
| 25 | multi-circuited with the facilities of the public utility. | ||||||
| 26 | (h) A public utility seeking to construct a high-voltage | ||||||
| |||||||
| |||||||
| 1 | electric service line and related facilities (Project) must | ||||||
| 2 | show that the utility has held a minimum of 2 pre-filing public | ||||||
| 3 | meetings to receive public comment concerning the Project in | ||||||
| 4 | each county where the Project is to be located, no earlier than | ||||||
| 5 | 6 months prior to filing an application for a certificate of | ||||||
| 6 | public convenience and necessity from the Commission. Notice | ||||||
| 7 | of the public meeting shall be published in a newspaper of | ||||||
| 8 | general circulation within the affected county once a week for | ||||||
| 9 | 3 consecutive weeks, beginning no earlier than one month prior | ||||||
| 10 | to the first public meeting. If the Project traverses 2 | ||||||
| 11 | contiguous counties and where in one county the transmission | ||||||
| 12 | line mileage and number of landowners over whose property the | ||||||
| 13 | proposed route traverses is one-fifth or less of the | ||||||
| 14 | transmission line mileage and number of such landowners of the | ||||||
| 15 | other county, then the utility may combine the 2 pre-filing | ||||||
| 16 | meetings in the county with the greater transmission line | ||||||
| 17 | mileage and affected landowners. All other requirements | ||||||
| 18 | regarding pre-filing meetings shall apply in both counties. | ||||||
| 19 | Notice of the public meeting, including a description of the | ||||||
| 20 | Project, must be provided in writing to the clerk of each | ||||||
| 21 | county where the Project is to be located. A representative of | ||||||
| 22 | the Commission shall be invited to each pre-filing public | ||||||
| 23 | meeting. | ||||||
| 24 | (h-5) A public utility seeking to construct a high-voltage | ||||||
| 25 | electric service line and related facilities must also show | ||||||
| 26 | that the Project has complied with training and competence | ||||||
| |||||||
| |||||||
| 1 | requirements under subsection (b) of Section 15 of the | ||||||
| 2 | Electric Transmission Systems Construction Standards Act. | ||||||
| 3 | (h-10) A public utility may be permitted to use highway | ||||||
| 4 | corridors for the purposes of constructing a high-voltage | ||||||
| 5 | electric service line and related facilities. | ||||||
| 6 | (h-15) A public utility seeking to construct a | ||||||
| 7 | high-voltage electric service line and related facilities must | ||||||
| 8 | consider corridors of development in the following order of | ||||||
| 9 | priority: | ||||||
| 10 | (1) existing utility corridors, where adding new lines | ||||||
| 11 | or making improvements to existing lines can achieve | ||||||
| 12 | expanded electric capacity at the lowest possible cost; | ||||||
| 13 | (2) highway corridors; and | ||||||
| 14 | (3) new utility corridors. | ||||||
| 15 | Consideration of corridors shall be done, to the greatest | ||||||
| 16 | extent possible, in a manner that accounts for economic and | ||||||
| 17 | engineering considerations, the reliability of the electric | ||||||
| 18 | system, and the protection of the environment. | ||||||
| 19 | (i) For applications filed after August 18, 2015 (the | ||||||
| 20 | effective date of Public Act 99-399), the Commission shall, by | ||||||
| 21 | certified mail, notify each owner of record of land, as | ||||||
| 22 | identified in the records of the relevant county tax assessor, | ||||||
| 23 | included in the right-of-way over which the utility seeks in | ||||||
| 24 | its application to construct a high-voltage electric line of | ||||||
| 25 | the time and place scheduled for the initial hearing on the | ||||||
| 26 | public utility's application. The utility shall reimburse the | ||||||
| |||||||
| |||||||
| 1 | Commission for the cost of the postage and supplies incurred | ||||||
| 2 | for mailing the notice. | ||||||
| 3 | (j) In determining whether to issue a certificate of | ||||||
| 4 | public convenience for a new electric generation facility to a | ||||||
| 5 | municipal power agency that is required to obtain such a | ||||||
| 6 | certificate to exercise its power of eminent domain pursuant | ||||||
| 7 | to Section 11-119.1-10 of the Illinois Municipal Code, the | ||||||
| 8 | Commission shall give due consideration to whether a | ||||||
| 9 | generation unit of similar size and type is part of the | ||||||
| 10 | municipal power agency's preferred portfolio or least-cost | ||||||
| 11 | plan for achieving renewable energy goals in its most recent | ||||||
| 12 | integrated resource plan, as described in subsection (d) of | ||||||
| 13 | Section 1-15 of the Municipal and Cooperative Electric Utility | ||||||
| 14 | Transparent Planning Act. | ||||||
| 15 | (Source: P.A. 103-569, eff. 6-1-24; 103-1066, eff. 2-20-25; | ||||||
| 16 | 104-458, eff. 6-1-26.) | ||||||
| 17 | (220 ILCS 5/8-406.1) | ||||||
| 18 | Sec. 8-406.1. Certificate of public convenience and | ||||||
| 19 | necessity; expedited procedure. | ||||||
| 20 | (a) A public utility may apply for a certificate of public | ||||||
| 21 | convenience and necessity pursuant to this Section for the | ||||||
| 22 | construction of any new high voltage electric service line and | ||||||
| 23 | related facilities (Project). To facilitate the expedited | ||||||
| 24 | review process of an application filed pursuant to this | ||||||
| 25 | Section, an application shall include all of the following: | ||||||
| |||||||
| |||||||
| 1 | (1) Information in support of the application that | ||||||
| 2 | shall include the following: | ||||||
| 3 | (A) A detailed description of the Project, | ||||||
| 4 | including location maps and plot plans to scale | ||||||
| 5 | showing all major components. | ||||||
| 6 | (B) The following engineering data: | ||||||
| 7 | (i) a detailed Project description including: | ||||||
| 8 | (I) name and destination of the Project; | ||||||
| 9 | (II) design voltage rating (kV); | ||||||
| 10 | (III) operating voltage rating (kV); and | ||||||
| 11 | (IV) normal peak operating current rating; | ||||||
| 12 | (ii) a conductor, structures, and substations | ||||||
| 13 | description including: | ||||||
| 14 | (I) conductor size and type; | ||||||
| 15 | (II) type of structures; | ||||||
| 16 | (III) height of typical structures; | ||||||
| 17 | (IV) an explanation why these structures | ||||||
| 18 | were selected; | ||||||
| 19 | (V) dimensional drawings of the typical | ||||||
| 20 | structures to be used in the Project; and | ||||||
| 21 | (VI) a list of the names of all new (and | ||||||
| 22 | existing if applicable) substations or | ||||||
| 23 | switching stations that will be associated | ||||||
| 24 | with the proposed new high voltage electric | ||||||
| 25 | service line; | ||||||
| 26 | (iii) the location of the site and | ||||||
| |||||||
| |||||||
| 1 | right-of-way including: | ||||||
| 2 | (I) miles of right-of-way; | ||||||
| 3 | (II) miles of circuit; | ||||||
| 4 | (III) width of the right-of-way; and | ||||||
| 5 | (IV) a brief description of the area | ||||||
| 6 | traversed by the proposed high voltage | ||||||
| 7 | electric service line, including a description | ||||||
| 8 | of the general land uses in the area and the | ||||||
| 9 | type of terrain crossed by the proposed line; | ||||||
| 10 | (iv) assumptions, bases, formulae, and methods | ||||||
| 11 | used in the development and preparation of the | ||||||
| 12 | diagrams and accompanying data, and a technical | ||||||
| 13 | description providing the following information: | ||||||
| 14 | (I) number of circuits, with | ||||||
| 15 | identification as to whether the circuit is | ||||||
| 16 | overhead or underground; | ||||||
| 17 | (II) the operating voltage and frequency; | ||||||
| 18 | and | ||||||
| 19 | (III) conductor size and type and number | ||||||
| 20 | of conductors per phase; | ||||||
| 21 | (v) if the proposed interconnection is an | ||||||
| 22 | overhead line, the following additional | ||||||
| 23 | information also must be provided: | ||||||
| 24 | (I) the wind and ice loading design | ||||||
| 25 | parameters; | ||||||
| 26 | (II) a full description and drawing of a | ||||||
| |||||||
| |||||||
| 1 | typical supporting structure, including | ||||||
| 2 | strength specifications; | ||||||
| 3 | (III) structure spacing with typical | ||||||
| 4 | ruling and maximum spans; | ||||||
| 5 | (IV) conductor (phase) spacing; and | ||||||
| 6 | (V) the designed line-to-ground and | ||||||
| 7 | conductor-side clearances; | ||||||
| 8 | (vi) if an underground or underwater | ||||||
| 9 | interconnection is proposed, the following | ||||||
| 10 | additional information also must be provided: | ||||||
| 11 | (I) burial depth; | ||||||
| 12 | (II) type of cable and a description of | ||||||
| 13 | any required supporting equipment, such as | ||||||
| 14 | insulation medium pressurizing or forced | ||||||
| 15 | cooling; | ||||||
| 16 | (III) cathodic protection scheme; and | ||||||
| 17 | (IV) type of dielectric fluid and | ||||||
| 18 | safeguards used to limit potential spills in | ||||||
| 19 | waterways; | ||||||
| 20 | (vii) technical diagrams that provide | ||||||
| 21 | clarification of any item under this item (1) | ||||||
| 22 | should be included; and | ||||||
| 23 | (viii) applicant shall provide and identify a | ||||||
| 24 | primary right-of-way and one or more alternate | ||||||
| 25 | rights-of-way for the Project as part of the | ||||||
| 26 | filing. To the extent applicable, for each | ||||||
| |||||||
| |||||||
| 1 | right-of-way, an applicant shall provide the | ||||||
| 2 | information described in this subsection (a). Upon | ||||||
| 3 | a showing of good cause in its filing, an | ||||||
| 4 | applicant may be excused from providing and | ||||||
| 5 | identifying alternate rights-of-way. | ||||||
| 6 | (2) An application fee of $100,000, which shall be | ||||||
| 7 | paid into the Public Utility Fund at the time the Chief | ||||||
| 8 | Clerk of the Commission deems it complete and accepts the | ||||||
| 9 | filing. | ||||||
| 10 | (3) Information showing that the utility has held a | ||||||
| 11 | minimum of 3 pre-filing public meetings to receive public | ||||||
| 12 | comment concerning the Project in each county where the | ||||||
| 13 | Project is to be located, no earlier than 6 months prior to | ||||||
| 14 | the filing of the application. Notice of the public | ||||||
| 15 | meeting shall be published in a newspaper of general | ||||||
| 16 | circulation within the affected county once a week for 3 | ||||||
| 17 | consecutive weeks, beginning no earlier than one month | ||||||
| 18 | prior to the first public meeting. If the Project | ||||||
| 19 | traverses 2 contiguous counties and where in one county | ||||||
| 20 | the transmission line mileage and number of landowners | ||||||
| 21 | over whose property the proposed route traverses is 1/5 or | ||||||
| 22 | less of the transmission line mileage and number of such | ||||||
| 23 | landowners of the other county, then the utility may | ||||||
| 24 | combine the 3 pre-filing meetings in the county with the | ||||||
| 25 | greater transmission line mileage and affected landowners. | ||||||
| 26 | All other requirements regarding pre-filing meetings shall | ||||||
| |||||||
| |||||||
| 1 | apply in both counties. Notice of the public meeting, | ||||||
| 2 | including a description of the Project, must be provided | ||||||
| 3 | in writing to the clerk of each county where the Project is | ||||||
| 4 | to be located. A representative of the Commission shall be | ||||||
| 5 | invited to each pre-filing public meeting. | ||||||
| 6 | For applications filed after the effective date of this | ||||||
| 7 | amendatory Act of the 99th General Assembly, the Commission | ||||||
| 8 | shall, by certified mail, notify each owner of record of the | ||||||
| 9 | land, as identified in the records of the relevant county tax | ||||||
| 10 | assessor, included in the primary or alternate rights-of-way | ||||||
| 11 | identified in the utility's application of the time and place | ||||||
| 12 | scheduled for the initial hearing upon the public utility's | ||||||
| 13 | application. The utility shall reimburse the Commission for | ||||||
| 14 | the cost of the postage and supplies incurred for mailing the | ||||||
| 15 | notice. | ||||||
| 16 | (b) At the first status hearing the administrative law | ||||||
| 17 | judge shall set a schedule for discovery that shall take into | ||||||
| 18 | consideration the expedited nature of the proceeding. | ||||||
| 19 | (c) Nothing in this Section prohibits a utility from | ||||||
| 20 | requesting, or the Commission from approving, protection of | ||||||
| 21 | confidential or proprietary information under applicable law. | ||||||
| 22 | The public utility may seek confidential protection of any of | ||||||
| 23 | the information provided pursuant to this Section, subject to | ||||||
| 24 | Commission approval. | ||||||
| 25 | (d) The public utility shall publish notice of its | ||||||
| 26 | application in the official State newspaper within 10 days | ||||||
| |||||||
| |||||||
| 1 | following the date of the application's filing. | ||||||
| 2 | (e) The public utility shall establish a dedicated website | ||||||
| 3 | for the Project 3 weeks prior to the first public meeting and | ||||||
| 4 | maintain the website until construction of the Project is | ||||||
| 5 | complete. The website address shall be included in all public | ||||||
| 6 | notices. | ||||||
| 7 | (f) The Commission shall, after notice and hearing, grant | ||||||
| 8 | a certificate of public convenience and necessity filed in | ||||||
| 9 | accordance with the requirements of this Section if, based | ||||||
| 10 | upon the application filed with the Commission and the | ||||||
| 11 | evidentiary record, it finds the Project will promote the | ||||||
| 12 | public convenience and necessity and that all of the following | ||||||
| 13 | criteria are satisfied: | ||||||
| 14 | (1) That the Project is necessary to provide adequate, | ||||||
| 15 | reliable, and efficient service to the public utility's | ||||||
| 16 | customers and is the least-cost means of satisfying the | ||||||
| 17 | service needs of the public utility's customers or that | ||||||
| 18 | the Project will promote the development of an effectively | ||||||
| 19 | competitive electricity market that operates efficiently, | ||||||
| 20 | is equitable to all customers, and is the least cost means | ||||||
| 21 | of satisfying those objectives. | ||||||
| 22 | (2) That the public utility is capable of efficiently | ||||||
| 23 | managing and supervising the construction process and has | ||||||
| 24 | taken sufficient action to ensure adequate and efficient | ||||||
| 25 | construction and supervision of the construction. | ||||||
| 26 | (3) That the public utility is capable of financing | ||||||
| |||||||
| |||||||
| 1 | the proposed construction without significant adverse | ||||||
| 2 | financial consequences for the utility or its customers. | ||||||
| 3 | (4) That the Project has complied with training and | ||||||
| 4 | competence and Diversity Plan requirements under | ||||||
| 5 | subsections (b) and (d) of Section 15 of the Electric | ||||||
| 6 | Transmission Systems Construction Standards Act. | ||||||
| 7 | (g) The Commission shall issue its decision with findings | ||||||
| 8 | of fact and conclusions of law granting or denying the | ||||||
| 9 | application no later than 150 days after the application is | ||||||
| 10 | filed. The Commission may extend the 150-day deadline upon | ||||||
| 11 | notice by an additional 75 days if, on or before the 30th day | ||||||
| 12 | after the filing of the application, the Commission finds that | ||||||
| 13 | good cause exists to extend the 150-day period. | ||||||
| 14 | (h) In the event the Commission grants a public utility's | ||||||
| 15 | application for a certificate pursuant to this Section, the | ||||||
| 16 | public utility shall pay a one-time construction fee to each | ||||||
| 17 | county in which the Project is constructed within 30 days | ||||||
| 18 | after the completion of construction. The construction fee | ||||||
| 19 | shall be $20,000 per mile of high voltage electric service | ||||||
| 20 | line constructed in that county, or a proportionate fraction | ||||||
| 21 | of that fee. The fee shall be in lieu of any permitting fees | ||||||
| 22 | that otherwise would be imposed by a county. Counties | ||||||
| 23 | receiving a payment under this subsection (h) may distribute | ||||||
| 24 | all or portions of the fee to local taxing districts in that | ||||||
| 25 | county. | ||||||
| 26 | (i) Notwithstanding any other provisions of this Act, a | ||||||
| |||||||
| |||||||
| 1 | decision granting a certificate under this Section shall | ||||||
| 2 | include an order pursuant to Section 8-503 of this Act | ||||||
| 3 | authorizing or directing the construction of the high voltage | ||||||
| 4 | electric service line and related facilities as approved by | ||||||
| 5 | the Commission, in the manner and within the time specified in | ||||||
| 6 | said order. | ||||||
| 7 | (j) A public utility may be permitted to use highway | ||||||
| 8 | corridors for the purposes of constructing a high-voltage | ||||||
| 9 | electric service line and related facilities for the purposes | ||||||
| 10 | of this Section. | ||||||
| 11 | (j-5) A public utility seeking to construct a high-voltage | ||||||
| 12 | electric service line and related facilities must consider | ||||||
| 13 | corridors of development in the following order of priority: | ||||||
| 14 | (1) existing utility corridors, where adding new lines | ||||||
| 15 | or making improvements to existing lines can achieve | ||||||
| 16 | expanded electric capacity at the lowest possible cost; | ||||||
| 17 | (2) highway corridors; and | ||||||
| 18 | (3) new utility corridors. | ||||||
| 19 | Consideration of corridors shall be done, to the greatest | ||||||
| 20 | extent possible, in a manner that accounts for economic and | ||||||
| 21 | engineering considerations, the reliability of the electric | ||||||
| 22 | system, and the protection of the environment. | ||||||
| 23 | (Source: P.A. 102-931, eff. 5-27-22; 103-1066, eff. 2-20-25.) | ||||||
| 24 | Section 95. No acceleration or delay. Where this Act makes | ||||||
| 25 | changes in a statute that is represented in this Act by text | ||||||
| |||||||
| |||||||
| 1 | that is not yet or no longer in effect (for example, a Section | ||||||
| 2 | represented by multiple versions), the use of that text does | ||||||
| 3 | not accelerate or delay the taking effect of (i) the changes | ||||||
| 4 | made by this Act or (ii) provisions derived from any other | ||||||
| 5 | Public Act. | ||||||
| 6 | Section 99. Effective date. This Act takes effect upon | ||||||
| 7 | becoming law.". | ||||||
