Bill Text: CA AB2539 | 2019-2020 | Regular Session | Amended


Bill Title: Electrical corporations: deenergization events: elections.

Spectrum: Partisan Bill (Republican 1-0)

Status: (Introduced - Dead) 2020-03-10 - Re-referred to Com. on U. & E. [AB2539 Detail]

Download: California-2019-AB2539-Amended.html

Amended  IN  Assembly  March 09, 2020

CALIFORNIA LEGISLATURE— 2019–2020 REGULAR SESSION

Assembly Bill
No. 2539


Introduced by Assembly Member Bigelow

February 19, 2020


An act to amend Section 8386 of add Section 768.9 to the Public Utilities Code, relating to electricity.


LEGISLATIVE COUNSEL'S DIGEST


AB 2539, as amended, Bigelow. Electrical corporations: wildfire mitigation plans. deenergization events: elections.
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. Existing law requires each electrical corporation to annually prepare a wildfire mitigation plan and to submit its plan to the commission for review and approval, as specified. Existing law requires the wildfire mitigation plan to include, among other things, protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety.
Under existing law, a violation of the Public Utilities Act is a crime.
This bill would require an electrical corporation that initiates a deenergization event, as defined, in the 2 weeks preceding an election or in the month following an election to provide assistance to ensure that the deenergization event does not impair the ability of local elections officials to perform official duties.
Because these provisions would be a part of the Public Utilities Act, the violation of which is a crime, the bill would impose a state-mandated local program.
The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
This bill would provide that no reimbursement is required by this act for a specified reason.

Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations. Existing law requires each electrical corporation to annually prepare and submit a wildfire mitigation plan to the commission for review and approval, as specified.

This bill would make a nonsubstantive change to the provisions relating to wildfire mitigation plans.

Vote: MAJORITY   Appropriation: NO   Fiscal Committee: NOYES   Local Program: NOYES  

The people of the State of California do enact as follows:


SECTION 1.

 Section 768.9 is added to the Public Utilities Code, to read:

768.9.
 (a) If an electrical corporation provides notification of a potential deenergization event in the two weeks preceding an election or in the month following an election, the electrical corporation shall work with local elections officials within its service territory to determine the ability of those officials to conduct their official duties. An electrical corporation shall provide assistance, including, but not limited to, the provision of mobile backup generators, to ensure that the deenergization event does not impair the ability of the local elections official to perform official duties.
(b) For purposes of this section, “deenergization event” means the proactive interruption of electrical service for the purpose of reducing or eliminating the risk of wildfires resulting from the operation of the electrical grid or related facilities.

SEC. 2.

 No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.
SECTION 1.Section 8386 of the Public Utilities Code is amended to read:
8386.

(a)Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.

(b)Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the Wildfire Safety Division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan, but each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.

(c)The wildfire mitigation plan shall include all of the following:

(1)An accounting of the responsibilities of persons responsible for executing the plan.

(2)The objectives of the plan.

(3)A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.

(4)A description of the metrics the electrical corporation plans to use to evaluate the plan’s performance and the assumptions that underlie the use of those metrics.

(5)A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.

(6)Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety. As part of these protocols, each electrical corporation shall include protocols related to mitigating the public safety impacts of disabling reclosers and deenergizing portions of the electrical distribution system that consider the impacts on all of the following:

(A)Critical first responders.

(B)Health and communication infrastructure.

(C)Customers who receive medical baseline allowances pursuant to subdivision (c) of Section 739. The electrical corporation may deploy backup electrical resources or provide financial assistance for backup electrical resources to a customer receiving a medical baseline allowance for a customer who meets all of the following requirements:

(i)The customer relies on life-support equipment that operates on electricity to sustain life.

(ii)The customer demonstrates financial need, including through enrollment in the California Alternate Rates for Energy program created pursuant to Section 739.1.

(iii)The customer is not eligible for backup electrical resources provided through medical services, medical insurance, or community resources.

(D)Subparagraph (C) shall not be construed as preventing an electrical corporation from deploying backup electrical resources or providing financial assistance for backup electrical resources under any other authority.

(7)Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines, including procedures for those customers receiving a medical baseline allowance as described in paragraph (6). The procedures shall direct notification to all public safety offices, critical first responders, health care facilities, and operators of telecommunications infrastructure with premises within the footprint of potential deenergization for a given event.

(8)Plans for vegetation management.

(9)Plans for inspections of the electrical corporation’s electrical infrastructure.

(10)Protocols for the deenergization of the electrical corporation’s transmission infrastructure, for instances when the deenergization may impact customers who, or entities that, are dependent upon the infrastructure.

(11)A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporation’s service territory, including all relevant wildfire risk and risk mitigation information that is part of the Safety Model Assessment Proceeding and the Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:

(A)Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporation’s equipment and facilities.

(B)Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporation’s service territory.

(12)A description of how the plan accounts for the wildfire risk identified in the electrical corporation’s Risk Assessment Mitigation Phase filing.

(13)A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.

(14)A description of where and how the electrical corporation considered undergrounding electrical distribution lines within those areas of its service territory identified to have the highest wildfire risk in a commission fire threat map.

(15)A showing that the electrical corporation has an adequately sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the electrical corporation.

(16)Identification of any geographic area in the electrical corporation’s service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.

(17)A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.

(18)A description of how the plan is consistent with the electrical corporation’s disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:

(A)Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.

(B)Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.

(19)A statement of how the electrical corporation will restore service after a wildfire.

(20)Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to electrical corporation representatives, and emergency communications.

(21)A description of the processes and procedures the electrical corporation will use to do all of the following:

(A)Monitor and audit the implementation of the plan.

(B)Identify any deficiencies in the plan or the plan’s implementation and correct those deficiencies.

(C)Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.

(22)Any other information that the Wildfire Safety Division may require.

(d)The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commission’s internet website for no less than two months before the division’s decision regarding approval of the plan. The division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.

feedback