Bill Text: AZ HB2003 | 2024 | Fifty-sixth Legislature 2nd Regular | Engrossed


Bill Title: Replacement lines; structures; commission hearings

Spectrum: Partisan Bill (Republican 1-0)

Status: (Engrossed) 2024-04-17 - Senate Committee of the Whole action: Do Pass [HB2003 Detail]

Download: Arizona-2024-HB2003-Engrossed.html

 

 

House Engrossed

 

replacement lines; structures; commission hearings

 

 

 

 

State of Arizona

House of Representatives

Fifty-sixth Legislature

Second Regular Session

2024

 

 

 

HOUSE BILL 2003

 

 

 

 

An Act

 

amending section 40-360.03, Arizona Revised Statutes; relating to public utilities.

 

 

(TEXT OF BILL BEGINS ON NEXT PAGE)

 


Be it enacted by the Legislature of the State of Arizona:

Section 1. Section 40-360.03, Arizona Revised Statutes, is amended to read:

START_STATUTE40-360.03. Application for certificate of environmental compatibility before construction of facilities; exception

A. Except as provided in subsection B of this section, every utility planning that plans to construct a plant or transmission line, or both, in this state shall first file with the commission an application for a certificate of environmental compatibility. The application shall be in a form prescribed by the commission and shall be accompanied by information with respect to the proposed type of facilities and description of the site, including the areas of jurisdiction affected and the estimated cost of the proposed facilities and site. Also The application shall also be accompanied by a receipt evidencing that evidences payment of the appropriate fee required by section 40-360.09. The commission shall promptly refer the application and accompanying information shall be promptly referred by the commission to the chairman of the committee for the committee's review and decision.

B. A utility may replace a conductor or wire on a transmission line or may replace an existing transmission line structure or structures with a new transmission line structure or structures without seeking a new certificate of environmental compatibility and without holding a hearing under this article if the replacement is on a transmission line that previously received a certificate of environmental compatibility or that was in use or authorized before August 13, 1971. All replacement conductors or structures shall comply with the terms and conditions of the applicable existing certificate of environmental compatibility. END_STATUTE