Bill Title: Relating to use of electric energy storage facilities in the ERCOT power region.
Spectrum: Partisan Bill (Republican 2-0)
Status: (Engrossed - Dead) 2019-05-21 - Placed on General State Calendar [SB1941 Detail]
Download: Texas-2019-SB1941-Engrossed.html
Bill Title: Relating to use of electric energy storage facilities in the ERCOT power region.
Spectrum: Partisan Bill (Republican 2-0)
Status: (Engrossed - Dead) 2019-05-21 - Placed on General State Calendar [SB1941 Detail]
Download: Texas-2019-SB1941-Engrossed.html
By: Hancock | S.B. No. 1941 |
|
||
|
||
relating to use of electric energy storage facilities in the ERCOT | ||
power region. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 35.151, Utilities Code, is amended to | ||
read as follows: | ||
Sec. 35.151. ELECTRIC ENERGY STORAGE. This subchapter | ||
applies only to the ownership or operation of electric energy | ||
storage equipment or facilities in the ERCOT power region that are | ||
intended to: | ||
(1) provide energy or ancillary services at wholesale, | ||
including electric energy storage equipment or facilities listed on | ||
a power generation company's registration with the commission or, | ||
for an exempt wholesale generator, on the generator's registration | ||
with the Federal Energy Regulatory Commission; or | ||
(2) provide reliable delivery of electric energy to | ||
retail customers. | ||
SECTION 2. Subchapter E, Chapter 35, Utilities Code, is | ||
amended by adding Section 35.153 to read as follows: | ||
Sec. 35.153. CONTRACTS FOR ELECTRIC ENERGY STORAGE FOR | ||
RELIABILITY SERVICES. (a) A transmission and distribution | ||
utility, with the approval of the commission, may contract with the | ||
owner or operator of an electric energy storage facility to provide | ||
electric energy from an electric energy storage facility to ensure | ||
reliable service to retail customers. | ||
(b) The commission may not authorize ownership of an | ||
electric energy storage facility by a transmission and distribution | ||
utility. | ||
(c) Before entering into a contract under Subsection (a), | ||
the transmission and distribution utility must issue a request for | ||
proposals for use of an electric energy storage facility to meet the | ||
utility's reliability needs. | ||
(d) A transmission and distribution utility may enter into a | ||
contract under Subsection (a) only if use of an electric energy | ||
storage facility is more cost-effective than construction or | ||
modification of traditional distribution facilities. | ||
(e) A transmission and distribution utility may not enter | ||
into a contract under Subsection (a) that reserves an amount of | ||
capacity exceeding the amount of capacity required to ensure | ||
reliable service to the utility's retail customers. | ||
(f) An owner or operator of an electric energy storage | ||
facility subject to a contract under Subsection (a) may sell | ||
electric energy or ancillary services through use of the facility | ||
only to the extent that the owner or operator reserves capacity as | ||
required by the contract. | ||
(g) An owner or operator of an electric energy storage | ||
facility subject to a contract under Subsection (a) may not | ||
discharge the facility for reliability purposes unless directed by | ||
the transmission and distribution utility. | ||
(h) A contract under Subsection (a) must require an owner or | ||
operator of an electric energy storage facility to reimburse a | ||
transportation and distribution utility for the cost of | ||
administrative penalties assessed against the utility for a | ||
violation caused by the facility's failure to meet the requirements | ||
of the agreement. | ||
(i) In establishing the rates of a transmission and | ||
distribution utility, a regulatory authority shall review a | ||
contract between the utility and an owner or operator of an electric | ||
energy storage facility under Subsection (a). The utility has the | ||
burden of proof to establish that the costs of the contract are | ||
reasonable and necessary. The regulatory authority may authorize a | ||
transmission and distribution utility to earn a reasonable return | ||
on the present value of future payments required under the | ||
contract. | ||
(j) The total amount of electric energy storage capacity | ||
reserved by contracts under Subsection (a) may not exceed 40 | ||
megawatts. The commission shall by rule establish the maximum | ||
amount of electric energy storage capacity allotted to each | ||
transmission and distribution utility. | ||
(k) The commission shall adopt rules as necessary to | ||
implement this section and establish criteria for approving | ||
contracts under Subsection (a). | ||
SECTION 3. The Public Utility Commission of Texas shall | ||
adopt rules required by Section 35.153, Utilities Code, as added by | ||
this Act, as soon as practicable after the effective date of this | ||
Act. | ||
SECTION 4. This Act takes effect September 1, 2019. |