Bill Text: TX SB1282 | 2021-2022 | 87th Legislature | Introduced
NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Relating to cost recovery for costs arising from the interconnection of certain electric generation facilities with the ERCOT transmission system.
Spectrum: Partisan Bill (Republican 6-0)
Status: (Engrossed - Dead) 2021-05-25 - Postponed 7/4/21 10:00 AM [SB1282 Detail]
Download: Texas-2021-SB1282-Introduced.html
Bill Title: Relating to cost recovery for costs arising from the interconnection of certain electric generation facilities with the ERCOT transmission system.
Spectrum: Partisan Bill (Republican 6-0)
Status: (Engrossed - Dead) 2021-05-25 - Postponed 7/4/21 10:00 AM [SB1282 Detail]
Download: Texas-2021-SB1282-Introduced.html
87R10952 JXC-F | ||
By: Hancock | S.B. No. 1282 |
|
||
|
||
relating to cost recovery for costs arising from the | ||
interconnection of certain electric generation facilities with the | ||
ERCOT transmission system. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 35.004, Utilities Code, is amended by | ||
amending Subsection (d) and adding Subsection (d-1) to read as | ||
follows: | ||
(d) The commission shall price wholesale transmission | ||
services within ERCOT based on the postage stamp method of pricing | ||
under which a transmission-owning utility's rate is based on the | ||
ERCOT utilities' combined annual costs of transmission, other than | ||
costs described in Subsection (d-1), divided by the total demand | ||
placed on the combined transmission systems of all such | ||
transmission-owning utilities within a power region. An electric | ||
utility subject to the freeze period imposed by Section 39.052 may | ||
treat transmission costs in excess of transmission revenues during | ||
the freeze period as an expense for purposes of determining annual | ||
costs in the annual report filed under Section 39.257. | ||
Notwithstanding Section 36.201, the commission may approve | ||
wholesale rates that may be periodically adjusted to ensure timely | ||
recovery of transmission investment. Notwithstanding Section | ||
36.054(a), if the commission determines that conditions warrant the | ||
action, the commission may authorize the inclusion of construction | ||
work in progress in the rate base for transmission investment | ||
required by the commission under Section 39.203(e). | ||
(d-1) Capital costs incurred to interconnect with the ERCOT | ||
transmission system generation resources and electric energy | ||
storage resources described by Section 35.152(a), including costs | ||
of utility interconnection facilities and all necessary system | ||
upgrades, must be directly assigned by the ERCOT independent system | ||
operator to the generation resource or electric energy storage | ||
resource receiving interconnection service through the facilities. | ||
SECTION 2. This Act takes effect September 1, 2021. |