A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to the consideration for approval by the executive |
|
director of the Texas Commission on Environmental Quality of an |
|
application for an authorization to use a standard permit for a |
|
concrete batch plant. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 382.05199, Health and Safety Code, is |
|
amended by amending Subsection (h) and adding Subsection (h-1) to |
|
read as follows: |
|
(h) Not later than the 35th day after the date the public |
|
hearing is held, the executive director shall approve or deny the |
|
application for authorization to use the standard permit. In |
|
determining whether to approve the application, the [The] executive |
|
director shall base the decision on: |
|
(1) whether the application meets the requirements of |
|
Section 382.05198; and |
|
(2) a consideration of: |
|
(A) [. The executive director shall consider] |
|
all comments received during the public comment period and at the |
|
public hearing; |
|
(B) the potential harm to local property values; |
|
and |
|
(C) the location of the facility relative to |
|
homes, schools, places of worship, parks, and other community |
|
assets [in determining whether to approve the application]. |
|
(h-1) If the executive director denies the application, the |
|
executive director shall state the reasons for the denial and any |
|
modifications to the application that are necessary for the |
|
proposed plant to qualify for the authorization. |
|
SECTION 2. Section 382.05199, Health and Safety Code, as |
|
amended by this Act, applies only to an application for an |
|
authorization to use a permit that is filed with the Texas |
|
Commission on Environmental Quality on or after the effective date |
|
of this Act. An application for an authorization to use a permit |
|
filed before the effective date of this Act is governed by the law |
|
in effect on the date of filing, and that law is continued in effect |
|
for that purpose. |
|