Bill Text: NY S04321 | 2021-2022 | General Assembly | Introduced


Bill Title: Establishes a program to develop microgrids that are capable of providing an uninterrupted supply of power to one or more community outage assets through an extended electric distribution outage.

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced - Dead) 2022-01-05 - REFERRED TO ENERGY AND TELECOMMUNICATIONS [S04321 Detail]

Download: New_York-2021-S04321-Introduced.html



                STATE OF NEW YORK
        ________________________________________________________________________

                                          4321

                               2021-2022 Regular Sessions

                    IN SENATE

                                    February 3, 2021
                                       ___________

        Introduced  by  Sen.  COMRIE -- read twice and ordered printed, and when
          printed to be committed to the Committee on  Energy  and  Telecommuni-
          cations

        AN  ACT  to amend the public service law and the public authorities law,
          in relation to developing microgrids in preparation for extreme weath-
          er events and other risks to public security

          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:

     1    Section  1.  The public service law is amended by adding a new section
     2  66-q to read as follows:
     3    § 66-q. Microgrid development program. 1. Definitions. As used in this
     4  section:
     5    (a) "community outage asset" means a public  or  private  entity  that
     6  provides  critical  services  to  the public during an extended electric
     7  distribution outage. Community outage assets shall include, but are  not
     8  limited  to:    telecommunications  providers, hospitals, nursing homes,
     9  large retail stores, supermarkets, government  agencies,  data  centers,
    10  transportation  systems,  financial  institutions,  gas stations, educa-
    11  tional institutions, large multi-family residential housing,  wastewater
    12  treatment  facilities,  community  centers and other customers deemed by
    13  the commission to provide a critical service to the  public  that  would
    14  promote  or  enhance  health and safety during an outage of the electric
    15  distribution system;
    16    (b) "extended electric distribution outage" means a total  or  partial
    17  outage  of  an electric corporation's distribution system that continues
    18  for a period of twenty-four hours or longer;
    19    (c) "uninterrupted" means that the output of the microgrid  system  is
    20  delivered  to  the  end-use  customer  throughout  an  extended electric
    21  distribution outage, with the exception of momentary interruptions asso-
    22  ciated with transitions to and from  grid  parallel  and  grid  islanded
    23  operations; and

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD08802-01-1

        S. 4321                             2

     1    (d) "microgrid" shall mean a load or group of interconnected loads and
     2  distributed  energy  resources within clearly defined electrical bounda-
     3  ries that acts as a single controllable entity with respect to the elec-
     4  tric grid.  A microgrid can connect and  disconnect  from  the  electric
     5  grid to enable it to operate in both grid-connected or island-mode.
     6    2.  On or within one hundred twenty days of the effective date of this
     7  section, the commission shall, after a hearing held on notice, adopt  an
     8  order  requiring  the  New  York  state  energy research and development
     9  authority to establish a program to support the  development  of  micro-
    10  grids  that are capable of providing an uninterrupted supply of power to
    11  one or  more  community  outage  assets  through  an  extended  electric
    12  distribution  outage.  Such program shall provide overall funding in the
    13  amount of seventy-five million dollars for the years two thousand  twen-
    14  ty-two  through  two thousand twenty-six.   Such program shall include a
    15  preference for those microgrids that:
    16    (a) maximize annual reductions in carbon dioxide equivalent, oxides of
    17  nitrogen, sulfur dioxide and particulate matter emissions achieved rela-
    18  tive to marginal grid emissions for the region in which the  project  is
    19  located.  For  purposes  of  this  section  the  commission shall define
    20  marginal emissions using the same metric or metrics  that  are  used  to
    21  quantify  emissions  reductions  achieved by other New York state energy
    22  research and development authority clean energy programs;
    23    (b) displace or otherwise  reduce  the  operation  of  diesel  back-up
    24  generators; and
    25    (c)  are more capable of being expeditiously permitted, interconnected
    26  and commissioned in preparation for extreme  weather  events  and  other
    27  grid related risks.
    28    §  2.  The  public  authorities law is amended by adding a new section
    29  1020-mm to read as follows:
    30    § 1020-mm. Microgrid development program. 1. Definitions. As  used  in
    31  this section:
    32    (a)  "community  outage  asset"  means a public or private entity that
    33  provides critical services to the public  during  an  extended  electric
    34  distribution  outage. Community outage assets shall include, but are not
    35  limited to:   telecommunications providers,  hospitals,  nursing  homes,
    36  large  retail  stores,  supermarkets, government agencies, data centers,
    37  transportation systems, financial  institutions,  gas  stations,  educa-
    38  tional  institutions, health care providers, large multi-family residen-
    39  tial housing, wastewater treatment  facilities,  community  centers  and
    40  other  customers  deemed by the commission to provide a critical service
    41  to the public that would promote or enhance health and safety during  an
    42  outage of the electric distribution system;
    43    (b)  "extended  electric distribution outage" means a total or partial
    44  outage of the authority's electric distribution  system  that  continues
    45  for a period of twenty-four hours or longer;
    46    (c)  "uninterrupted"  means that the output of the microgrid system is
    47  delivered to  the  end-use  customer  throughout  an  extended  electric
    48  distribution outage, with the exception of momentary interruptions asso-
    49  ciated  with  transitions  to  and  from grid parallel and grid islanded
    50  operations; and
    51    (d) "microgrid" shall mean a load or group of interconnected loads and
    52  distributed energy resources within clearly defined  electrical  bounda-
    53  ries that acts as a single controllable entity with respect to the elec-
    54  tric  grid.    A  microgrid can connect and disconnect from the electric
    55  grid to enable it to operate in both grid-connected or island-mode.

        S. 4321                             3

     1    2. On or within one hundred eighty days of the effective date of  this
     2  section, the authority shall establish a program to support the develop-
     3  ment of microgrids that are capable of providing an uninterrupted supply
     4  of  power  to  one  or  more community outage assets through an extended
     5  electric distribution outage. Such program shall provide overall funding
     6  in  the amount of twenty-five million dollars for the years two thousand
     7  twenty-two through two thousand twenty-six. Such program shall include a
     8  preference for those microgrids that:
     9    (a) maximize annual reductions in carbon dioxide equivalent, oxides of
    10  nitrogen, sulfur dioxide and particulate matter emissions achieved rela-
    11  tive to marginal grid emissions for the authority's  service  territory.
    12  For  purposes  of this section the authority shall define marginal emis-
    13  sions using the same metric or metrics that are used to  quantify  emis-
    14  sions  reductions  achieved  by other New York state energy research and
    15  development authority clean energy programs;
    16    (b) displace or otherwise  reduce  the  operation  of  diesel  back-up
    17  generators; and
    18    (c)  are more capable of being expeditiously permitted, interconnected
    19  and commissioned in preparation for extreme  weather  events  and  other
    20  grid related risks.
    21    § 3. This act shall take effect immediately.
feedback