S T A T E   O F   N E W   Y O R K
       ________________________________________________________________________
                                          796
                              2015-2016 Regular Sessions
                                 I N  A S S E M B L Y
                                    January 7, 2015
                                      ___________
       Introduced  by  M.  of A. BRAUNSTEIN, TENNEY, NOJAY, SCHIMEL, MONTESANO,
         HEVESI, RUSSELL -- Multi-Sponsored by -- M. of A. STECK --  read  once
         and referred to the Committee on Governmental Operations
       AN  ACT to amend the state finance law and the general municipal law, in
         relation to requiring full payment for delivered and accepted  materi-
         als pertaining to public work projects; and to amend the general busi-
         ness  law, in relation to prohibiting the retention of any payment due
         and owing a material supplier for a construction project
         THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND  ASSEM-
       BLY, DO ENACT AS FOLLOWS:
    1    Section  1. Subdivisions 1 and 2 of section 139-f of the state finance
    2  law, subdivision 1 as added by chapter 769  of  the  laws  of  1978  and
    3  subdivision  2  as amended by section 16 of part MM of chapter 57 of the
    4  laws of 2008, are amended to read as follows:
    5    1. Payment by public owners to contractors. The contractor shall peri-
    6  odically, in accordance with the terms of the contract,  submit  to  the
    7  public owner and/or [his] ITS agent a requisition for a progress payment
    8  for  the  work  performed  and/or materials furnished to the date of the
    9  requisition, less any amount previously  paid  to  the  contractor.  The
   10  public  owner shall in accordance with the terms of the contract approve
   11  and promptly pay the requisition for the progress payment less an amount
   12  necessary to satisfy any claims, liens or judgments against the contrac-
   13  tor which have not been suitably discharged and less any retained amount
   14  as hereafter described. The public owner shall retain not more than five
   15  per centum of each progress payment, NOT INCLUDING ANY PAYMENT FOR MATE-
   16  RIALS PERTINENT TO THE PROJECT WHICH HAVE BEEN DELIVERED,  ACCEPTED  AND
   17  ARE  COVERED  BY  A  MANUFACTURER'S  WARRANTY, AND/OR ARE GRADED TO MEET
   18  INDUSTRY STANDARDS, to the contractor except that the public  owner  may
   19  retain  in excess of five per centum but not more than ten per centum of
   20  each progress payment, NOT INCLUDING ANY PAYMENT FOR MATERIALS PERTINENT
   21  TO THE PROJECT WHICH HAVE BEEN DELIVERED, ACCEPTED AND ARE COVERED BY  A
        EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
                             [ ] is old law to be omitted.
                                                                  LBD02317-01-5
       A. 796                              2
    1  MANUFACTURER'S  WARRANTY,  AND/OR ARE GRADED TO MEET INDUSTRY STANDARDS,
    2  to the contractor provided that there are no requirements by the  public
    3  owner  for  the contractor to provide a performance bond and a labor and
    4  material  bond both in the full amount of the contract. The public owner
    5  shall pay IN FULL, upon requisition from the contractor, for ALL materi-
    6  als pertinent to the project which have been delivered to  the  site  or
    7  off-site  by the contractor and/or subcontractor and suitably stored and
    8  secured as required by the public owner and  the  contractor  [provided,
    9  the  public  owner  may  limit such payment to materials in short and/or
   10  critical supply and materials specially fabricated for the project  each
   11  as  defined in the contract]. When the work or major portions thereof as
   12  contemplated by the terms of the contract are  substantially  completed,
   13  the contractor shall submit to the public owner and/or [his] ITS agent a
   14  requisition for payment of the remaining amount of the contract balance.
   15  Upon  receipt  of  such  requisition  the public owner shall approve and
   16  promptly pay the remaining amount of the contract balance less two times
   17  the value of any remaining items to be completed and an amount necessary
   18  to satisfy any claims, liens or judgments against the  contractor  which
   19  have  not  been  suitably discharged. As the remaining items of work are
   20  satisfactorily completed or corrected, the public owner  shall  promptly
   21  pay,  upon  receipt  of a requisition, for these remaining items less an
   22  amount necessary to satisfy any claims, liens or judgments  against  the
   23  contractor  which  have  not been suitably discharged. Any claims, liens
   24  and judgments referred to in this section shall pertain to  the  project
   25  and  shall  be  filed  in  accordance  with  the terms of the applicable
   26  contract and/or applicable laws.
   27    2. Payment by contractors to  subcontractors.  Within  seven  calendar
   28  days of the receipt of any payment from the public owner, the contractor
   29  shall  pay each of [his] ITS subcontractors and materialmen the proceeds
   30  from the payment representing the value of  the  work  performed  and/or
   31  materials furnished by the subcontractor and/or materialman and reflect-
   32  ing  the  percentage  of  the  subcontractor's  work  completed  or  the
   33  materialman's material supplied in the requisition approved by the owner
   34  and based upon the actual value of the  subcontract  or  purchase  order
   35  less  an  amount  necessary  to  satisfy  any claims, liens or judgments
   36  against the subcontractor or materialman which have  not  been  suitably
   37  discharged  and, WITH REGARD TO SUBCONTRACTORS, less any retained amount
   38  as hereafter described. Failure by the contractor to pay any subcontrac-
   39  tor or materialman within seven calendar days  of  the  receipt  of  any
   40  payment  from  the  public  owner  shall  result in the commencement and
   41  accrual of interest on amounts due to such subcontractor or  materialman
   42  for the period beginning on the day immediately following the expiration
   43  of  such  seven  calendar  day  period  and  ending on the date on which
   44  payment is made by the contractor to such subcontractor or  materialman.
   45  Such  interest  payment shall be the sole responsibility of the contrac-
   46  tor, and shall be paid at the rate of interest in  effect  on  the  date
   47  payment  is made by the contractor.  Notwithstanding any other provision
   48  of law to the contrary, interest shall be computed at  the  rate  estab-
   49  lished  in  paragraph  (b)  of  subdivision one of section seven hundred
   50  fifty-six-b of the general business law. The contractor shall retain not
   51  more than five per centum of each payment to the  subcontractor  [and/or
   52  materialman] except that the contractor may retain in excess of five per
   53  centum  but  not more than ten per centum of each payment to the subcon-
   54  tractor provided that prior to entering  into  a  subcontract  with  the
   55  contractor,  the  subcontractor  is  unable  or  unwilling  to provide a
   56  performance bond and a labor and material bond, both in the full  amount
       A. 796                              3
    1  of  the  subcontract,  at the request of the contractor.  THE CONTRACTOR
    2  SHALL PAY IN FULL, UPON PAYMENT BY THE PUBLIC OWNER, FOR  ALL  MATERIALS
    3  PERTINENT  TO  THE  PROJECT WHICH HAVE BEEN DELIVERED TO AND ACCEPTED AT
    4  THE  SITE  OR OFF-SITE BY A MATERIALMAN AND ARE COVERED BY A MANUFACTUR-
    5  ER'S WARRANTY, AND/OR ARE GRADED TO MEET  INDUSTRY  STANDARDS.  However,
    6  EXCEPT  IN THE CASE OF A MATERIALMAN WHO IS ALSO CONTRACTED TO INSTALL A
    7  PRODUCT HE/SHE DELIVERED, the contractor shall retain nothing from those
    8  payments representing proceeds owed the subcontractor and/or materialman
    9  from the public owner's payments to the  contractor  for  the  remaining
   10  amounts  of  the contract balance as provided in subdivision one of this
   11  section. If the contractor  has  failed  to  submit  a  requisition  for
   12  payment  of  the remaining amounts of the contract balance within ninety
   13  days of substantial completion as provided in subdivision  one  of  this
   14  section,  then  any clause in the subcontract between the contractor and
   15  the subcontractor or  materialman  which  states  that  payment  by  the
   16  contractor  to  such  subcontractor  or  materialman  is contingent upon
   17  payment by the owner to the contractor shall be deemed  invalid.  Within
   18  seven  calendar  days of the receipt of payment from the contractor, the
   19  subcontractor and/or materialman shall pay each of [his] ITS subcontrac-
   20  tors and materialmen in the same manner as the contractor has  paid  the
   21  subcontractor,  including  interest  as  herein  provided above. Nothing
   22  provided herein shall create any obligation on the part  of  the  public
   23  owner to pay or to see to the payment of any moneys to any subcontractor
   24  or  materialman  from  any contractor nor shall anything provided herein
   25  serve to create any relationship in contract or  otherwise,  implied  or
   26  expressed,  between  the  subcontractor  or  materialman  and the public
   27  owner.
   28    S 2. Paragraph (a) of subdivision 1 and subdivision 2 of section 106-b
   29  of the general municipal law, paragraph (a) of subdivision 1 as  amended
   30  by  chapter  98  of  the  laws  of  1995 and subdivision 2 as amended by
   31  section 15 of part MM of chapter 57 of the laws of 2008, are amended  to
   32  read as follows:
   33    (a) The contractor shall periodically, in accordance with the terms of
   34  the contract, submit to the public owner and/or [his] ITS agent a requi-
   35  sition  for  a  progress payment for the work performed and/or materials
   36  furnished to the date of the requisition less any amount previously paid
   37  to the contractor. The public owner shall in accordance with  the  terms
   38  of  the  contract  approve  and  promptly  pay  the  requisition for the
   39  progress payment less an amount necessary to satisfy any  claims,  liens
   40  or  judgments  against  the  contractor  which  have  not  been suitably
   41  discharged and less any retained  amount  as  hereafter  described.  The
   42  public owner shall retain not more than five per centum of each progress
   43  payment,  NOT  INCLUDING  ANY  PAYMENT  FOR  MATERIALS  PERTINENT TO THE
   44  PROJECT WHICH HAVE  BEEN  DELIVERED,  ACCEPTED  AND  ARE  COVERED  BY  A
   45  MANUFACTURER'S  WARRANTY,  AND/OR ARE GRADED TO MEET INDUSTRY STANDARDS,
   46  to the contractor except that the public owner may retain in  excess  of
   47  five  per  centum  but  not  more  than  ten per centum of each progress
   48  payment, NOT INCLUDING  ANY  PAYMENT  FOR  MATERIALS  PERTINENT  TO  THE
   49  PROJECT  WHICH  HAVE  BEEN  DELIVERED,  ACCEPTED  AND  ARE  COVERED BY A
   50  MANUFACTURER'S WARRANTY, AND/OR ARE GRADED TO MEET  INDUSTRY  STANDARDS,
   51  to  the contractor provided that there are no requirements by the public
   52  owner for the contractor to provide a performance bond and a  labor  and
   53  material  bond both in the full amount of the contract. The public owner
   54  shall pay IN FULL, upon requisition from the contractor, for ALL materi-
   55  als pertinent to the project which have been delivered to  the  site  or
   56  off-site  by the contractor and/or subcontractor and suitably stored and
       A. 796                              4
    1  secured as required by the public owner and  the  contractor  [provided,
    2  the  public  owner  may  limit such payment to materials in short and/or
    3  critical supply and materials specially fabricated for the project  each
    4  as  defined in the contract]. When the work or major portions thereof as
    5  contemplated by the terms of the contract are  substantially  completed,
    6  the contractor shall submit to the public owner and/or [his] ITS agent a
    7  requisition for payment of the remaining amount of the contract balance.
    8  Upon  receipt  of  such  requisition  the public owner shall approve and
    9  promptly pay the remaining amount of the contract balance less two times
   10  the value of any remaining items to be completed and an amount necessary
   11  to satisfy any claims, liens or judgments against the  contractor  which
   12  have  not  been  suitably discharged. As the remaining items of work are
   13  satisfactorily completed or corrected, the public owner  shall  promptly
   14  pay,  upon  receipt  of  a  requisition,  for these items less an amount
   15  necessary to satisfy any claims, liens or judgments against the contrac-
   16  tor which have not been suitably discharged. Any claims, liens and judg-
   17  ments referred to in this section shall pertain to the project and shall
   18  be filed in accordance with the terms of the applicable contract  and/or
   19  applicable  laws.  Where  the public owner is other than the city of New
   20  York, the term "promptly pay" shall mean  payment  within  thirty  days,
   21  excluding  legal  holidays,  of  receipt  of the requisition unless such
   22  requisition is not approvable  in  accordance  with  the  terms  of  the
   23  contract. Notwithstanding the foregoing, where the public owner is other
   24  than  the city of New York and is a municipal corporation which requires
   25  an elected official to approve progress payments, "promptly  pay"  shall
   26  mean  payment  within  forty-five  days,  excluding  legal  holidays, of
   27  receipt of the requisition unless such requisition is not approvable  in
   28  accordance with the terms of the contract.
   29    2.  Payment  by  contractors  to subcontractors. Within seven calendar
   30  days of the receipt of any payment from the public owner, the contractor
   31  shall pay each of [his] ITS subcontractors and materialmen the  proceeds
   32  from  the  payment  representing  the value of the work performed and/or
   33  materials furnished by the subcontractor and/or materialman and reflect-
   34  ing  the  percentage  of  the  subcontractor's  work  completed  or  the
   35  materialman's material supplied in the requisition approved by the owner
   36  and  based  upon  the  actual value of the subcontract or purchase order
   37  less an amount necessary to  satisfy  any  claims,  liens  or  judgments
   38  against  the  subcontractor  or materialman which have not been suitably
   39  discharged and, WITH REGARD TO SUBCONTRACTORS, less any retained  amount
   40  as  hereafter  described. Failure by the contractor to make any payment,
   41  including any remaining amounts of the contract balance  as  hereinafter
   42  described,  to  any  subcontractor  or materialman within seven calendar
   43  days of the receipt of any payment from the public owner shall result in
   44  the commencement and accrual of interest on amounts due to such  subcon-
   45  tractor  or  materialman for the period beginning on the day immediately
   46  following the expiration of such seven calendar day period and ending on
   47  the date on which payment is made by the contractor to such  subcontrac-
   48  tor  or  materialman.  Such interest shall be the sole responsibility of
   49  the contractor, and shall be paid at the rate of interest in  effect  on
   50  the  date  payment  is made by the contractor. Notwithstanding any other
   51  provision of law to the contrary, interest shall be computed at the rate
   52  established in paragraph (b) of subdivision one of section seven hundred
   53  fifty-six-b of the general business law. The contractor shall retain not
   54  more than five per centum of each payment to the  subcontractor  [and/or
   55  materialman] except that the contractor may retain in excess of five per
   56  centum  but  not more than ten per centum of each payment to the subcon-
       A. 796                              5
    1  tractor provided that prior to entering  into  a  subcontract  with  the
    2  contractor,  the  subcontractor  is  unable  or  unwilling  to provide a
    3  performance bond and a labor and material bond both in the  full  amount
    4  of  the  subcontract  at  the  request of the contractor. THE CONTRACTOR
    5  SHALL PAY IN FULL, UPON PAYMENT BY THE PUBLIC OWNER, FOR  ALL  MATERIALS
    6  PERTINENT  TO  THE  PROJECT WHICH HAVE BEEN DELIVERED TO AND ACCEPTED AT
    7  THE SITE OR OFF-SITE BY A MATERIALMAN AND ARE COVERED BY  A  MANUFACTUR-
    8  ER'S  WARRANTY,  AND/OR  ARE GRADED TO MEET INDUSTRY STANDARDS. However,
    9  EXCEPT IN THE CASE OF A MATERIALMAN WHO IS ALSO CONTRACTED TO INSTALL  A
   10  PRODUCT HE/SHE DELIVERED, the contractor shall retain nothing from those
   11  payments representing proceeds owed the subcontractor and/or materialman
   12  from  the  public  owner's  payments to the contractor for the remaining
   13  amounts of the contract balance as provided in subdivision one  of  this
   14  section.  If  the  contractor  has  failed  to  submit a requisition for
   15  payment of the remaining amounts of the contract balance  within  ninety
   16  days  of  substantial  completion as provided in subdivision one of this
   17  section, then any clause in the subcontract between the  contractor  and
   18  the  subcontractor  or  materialman  which  states  that  payment by the
   19  contractor to such  subcontractor  or  materialman  is  contingent  upon
   20  payment  by  the owner to the contractor shall be deemed invalid. Within
   21  seven calendar days of the receipt of payment from the  contractor,  the
   22  subcontractor and/or materialman shall pay each of [his] ITS subcontrac-
   23  tors  and  materialmen in the same manner as the contractor has paid the
   24  subcontractor, including interest as herein  provided  above.    Nothing
   25  provided  herein  shall  create any obligation on the part of the public
   26  owner to pay or to see to the payment of any moneys to any subcontractor
   27  or materialman from any contractor nor shall  anything  provided  herein
   28  serve  to  create  any relationship in contract or otherwise, implied or
   29  expressed, between the  subcontractor  or  materialman  and  the  public
   30  owner.
   31    S  3.  Section  756-c of the general business law, as added by chapter
   32  127 of the laws of 2002, is amended to read as follows:
   33    S 756-c. Retention. 1. By mutual agreement of the relevant parties  an
   34  owner may retain a reasonable amount of the contract sum as retainage. A
   35  contractor  or  subcontractor  may  also  retain a reasonable amount for
   36  retainage so long as the amount does not exceed  the  actual  percentage
   37  retained  by  the owner. Retainage shall be released by the owner to the
   38  contractor no later than thirty days after the  final  approval  of  the
   39  work  under a construction contract. In the event that an owner fails to
   40  release retainage as required by this  article,  or  the  contractor  or
   41  subcontractor  fails  to  release a proportionate amount of retainage to
   42  the relevant parties after receipt of  retainage  from  the  owner,  the
   43  owner,  contractor,  or  subcontractor,  as  the  case  may be, shall be
   44  subject to the payment of interest at the rate of one percent per  month
   45  on the date retention was due and owing.
   46    2.  NOTWITHSTANDING THE PROVISIONS OF SUBDIVISION ONE OF THIS SECTION,
   47  NO PORTION OF ANY PAYMENT DUE AND OWING TO A MATERIAL SUPPLIER FOR MATE-
   48  RIALS WHICH HAVE BEEN DELIVERED, ACCEPTED AND ARE COVERED BY A  MANUFAC-
   49  TURER'S  WARRANTY,  AND/OR  GRADED  TO  MEET INDUSTRY STANDARDS SHALL BE
   50  RETAINED BY AN OWNER, CONTRACTOR OR SUBCONTRACTOR.
   51    S 4. This act shall take effect on the thirtieth day  after  it  shall
   52  have become a law and shall apply to materials delivered and accepted on
   53  or after such effective date.