Bill Text: IL SB1636 | 2019-2020 | 101st General Assembly | Engrossed
NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Amends the Contractor Prompt Payment Act. Provides that a retainage of 10% of the payment may be withheld from a payment under a construction contract prior to the completion of 50% of the contract. Provides that after 50% of the contract is completed, the amount of retainage for any subsequent payment may not exceed 5%. Effective immediately.
Spectrum: Moderate Partisan Bill (Democrat 11-2)
Status: (Passed) 2019-08-20 - Public Act . . . . . . . . . 101-0432 [SB1636 Detail]
Download: Illinois-2019-SB1636-Engrossed.html
Bill Title: Amends the Contractor Prompt Payment Act. Provides that a retainage of 10% of the payment may be withheld from a payment under a construction contract prior to the completion of 50% of the contract. Provides that after 50% of the contract is completed, the amount of retainage for any subsequent payment may not exceed 5%. Effective immediately.
Spectrum: Moderate Partisan Bill (Democrat 11-2)
Status: (Passed) 2019-08-20 - Public Act . . . . . . . . . 101-0432 [SB1636 Detail]
Download: Illinois-2019-SB1636-Engrossed.html
| |||||||
| |||||||
| |||||||
1 | AN ACT concerning business.
| ||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||
3 | represented in the General Assembly:
| ||||||
4 | Section 5. The Contractor Prompt Payment Act is amended by | ||||||
5 | adding Section 20 as follows:
| ||||||
6 | (815 ILCS 603/20 new) | ||||||
7 | Sec. 20. Retainage. No construction contract may permit | ||||||
8 | the withholding of retainage from any payment in excess of the | ||||||
9 | amounts permitted in this Section. A construction contract may | ||||||
10 | provide for the withholding of retainage of up to 10% of any | ||||||
11 | payment made prior to the completion of 50% of the contract. | ||||||
12 | When a contract is 50% complete, retainage withheld shall be | ||||||
13 | reduced so that no more than 5% is held. After the contract is | ||||||
14 | 50% complete, no more than 5% of the amount of any subsequent | ||||||
15 | payments made under the contract may be held as retainage.
| ||||||
16 | Section 99. Effective date. This Act takes effect upon | ||||||
17 | becoming law.
|