Bill Text: HI HB1315 | 2021 | Regular Session | Introduced


Bill Title: Relating To Capital Improvement Projects For The Benefit Of The Sixth Representative District.

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced - Dead) 2021-02-01 - Referred to FIN, referral sheet 3 [HB1315 Detail]

Download: Hawaii-2021-HB1315-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

1315

THIRTY-FIRST LEGISLATURE, 2021

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Sixth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $298,751,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2021-2022 for the purpose of capital improvement projects for the sixth representative district, as follows:

1.   Holualoa elementary school, Hawaii

     Plans, design, and construction to complete the master plan project and for phase 1 campus improvements.

     Plans                          $200,000

     Design                       $3,000,000

     Construction                $23,000,000

          Total funding                    $26,200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Kahakai elementary school, Hawaii

     Plans, design, and construction of a concrete bridge connecting buildings A and B to meet with Americans with Disabilities Act requirements.

     Plans                           $10,000

     Design                          $15,000

     Construction                   $950,000

          Total funding                       $975,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Kahakai elementary school, Hawaii

     Plans, design, and construction of a covered play court.

     Plans                           $15,000

     Design                          $10,000

     Construction                   $675,000

          Total funding                       $700,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Kealakehe high school, Hawaii

     Design and construction for a performing arts center.

     Design                       $3,500,000

     Construction                $35,000,000

          Total funding                    $38,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Kealakehe high school, Hawaii

     Design, construction, and equipment for synthetic turf for field and strength and conditioning facility for athletic training.

     Design                         $900,000

     Construction                 $4,500,000

     Equipment                      $200,000

          Total funding                     $5,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Kealakehe intermediate school, Hawaii

     Design and construction for an air conditioning system in classroom buildings F, G, and H.

     Design                         $200,000

     Construction                 $1,000,000

          Total funding                     $1,200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Kealakehe intermediate school, Hawaii

     Design and construction for resurfacing of the basketball and volleyball play court and installation of a roof cover.

     Design                         $200,000

     Construction                 $1,000,000

          Total funding                     $1,200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Kealakehe elementary school, Hawaii

     Design and construction for completion of air conditioning system installation for the cafeteria dining room.

     Design                         $500,000

     Construction                 $2,500,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Kealakehe elementary school, Hawaii

     Design and construction for a covered play court in F-Field.

     Design                         $600,000

     Construction                 $3,000,000

          Total funding                     $3,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  West Hawaii veterans' cemetary, Hawaii

     Plans, design, and construction for expansion and improvements needed to qualify for federal aid financing and reimbursement.

     Plans                           $50,000

     Design                         $580,000

     Construction                 $1,070,000

          Total funding                     $1,700,000

     The sum appropriated for this capital improvement project shall be expended by the department of defense.

11.  Holualoa water source development, Hawaii

     Plans, land, design, and construction to develop an exploratory and production well water source.

     Plans                        $1,650,000

     Land                             $5,000

     Design                       $1,505,000

     Construction                $11,825,000

          Total funding                    $14,985,000

     The sum appropriated for this capital improvement project shall be expended by the department of Hawaiian home lands.

12.  Division of forestry and wildlife and Hawaii community college at Palamanui

     Plans and construction to protect the dry forest ecosystem that will serve as a learning lab for community college students to learn about natural resource management, conservation, natural history, biology, and threats to Hawaii's native ecosystem.

     Plans                           $75,000

     Construction                   $525,000

          Total funding                       $600,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

13.  Honokohau harbor, Hawaii

     Design and construction for electrical system improvements.

     Design                         $500,000

     Construction                 $4,500,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

14.  Honokohau harbor, Hawaii

     Design and construction for ground and site improvements to complete phase 3 that includes asphalt paving, striping, and drainage improvements.

     Design                         $300,000

     Construction                 $2,500,000

          Total funding                     $2,800,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

15.  Honokohau harbor, Hawaii

     Design and construction for small boat harbor fender repairs.

     Design                         $300,000

     Construction                 $3,000,000

          Total funding                     $3,300,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

16.  Honokohau harbor, Hawaii

     Design and construction for wastewater system improvements.

     Design                         $300,000

     Construction                 $4,000,000

          Total funding                     $4,300,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

17.  Honokohau harbor, Hawaii

     Design and construction for removal of existing irrigation system and installation of new irrigation system capable of using reuse water from county of Hawaii.

     Design                         $300,000

     Construction                 $2,500,000

          Total funding                     $2,800,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

18.  Hulihee palace, Hawaii

     Construction for ground and site improvements.

     Construction                 $2,000,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

19.  Kekaha Kai state park, Hawaii

     Plans, design, and construction for renovation and rehabilitation of the historic Kaelemakule-Magoon house complex and Mahaiula and Maniniowali improvements.

     Plans                           $50,000

     Design                         $250,000

     Construction                 $1,500,000

          Total funding                     $1,800,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

20.  State parks west Hawaii baseyard, Hawaii

     Plans, design, and construction for a new baseyard complex for state parks west Hawaii staff.

     Plans                           $50,000

     Design                         $300,000

     Construction                 $2,200,000

          Total funding                     $2,550,000

     The sum appropriated for this capital improvement project shall be expended by the department of land and natural resources.

21.  Daniel K. Inouye highway, Hawaii

     Plans, design, and construction to extend Mamalahoa highway to Queen Kaahumanu highway; ground and site improvements; and equipment and appurtenances.

     Plans                        $1,000,000

     Design                       $1,000,000

     Construction                $87,000,000

          Total funding                    $89,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

22.  Ellison Onizuka Kona international airport at Keahole, Hawaii

     Construction for improvements to various facilities.

     Construction                 $2,420,000

          Total funding                     $2,420,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

23.  Ellison Onizuka Kona international airport at Keahole, Hawaii

     Construction for terminal improvements for increased capacity, safety, comfort, and efficiency.

     Construction                $15,721,000

          Total funding                    $15,721,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

24.  Kona community hospital, Hawaii

     Design and equipment to replace current electronic medical record system that sunsets in June 2023.

     Design                       $1,000,000

     Equipment                   $19,000,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii health systems corporation.

25.  Kona community hospital, Hawaii

     Design, construction, and equipment to replace the existing cancer center building and chemo processing room in Kona.

     Design                       $1,000,000

     Construction                 $4,000,000

     Equipment                    $1,000,000

          Total funding                     $6,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii health systems corporation.

26.  Kona community hospital, Hawaii

     Design and construction for emergency room department renovations.

     Design                         $500,000

     Construction                 $3,000,000

          Total funding                     $3,500,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii health systems corporation.

27.  Kona community hospital, Hawaii

     Design and construction for wastewater treatment plant upgrades.

     Design                         $500,000

     Construction                 $1,500,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii health systems corporation.

28.  Kona community hospital, Hawaii

     Design and construction to repaint, reseal, and reroof the entire hospital.

     Design                         $500,000

     Construction                 $2,000,000

          Total funding                     $2,500,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii health systems corporation.

29.  Hawaii community college at Palamanui, Hawaii

     Plans, design, and construction for a portable structure for the health and sciences program; ground and site improvements; and equipment and appurtenances.

     Plans                            $1,000

     Design                           $1,000

     Construction                 $3,998,000

          Total funding                     $4,000,000

     The sum appropriated for this capital improvement project shall be expended by the University of Hawaii.

30.  Hawaii community college at Palamanui, Hawaii

     Plans and construction for the Allied Health Building to relocate the nursing program to the Palamanui campus.

     Plans                          $800,000

     Construction                $30,000,000

          Total funding                    $30,800,000

     The sum appropriated for this capital improvement project shall be expended by the University of Hawaii.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2021.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Sixth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the sixth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

feedback