Bill Text: CA AB759 | 2017-2018 | Regular Session | Introduced

NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Electricity: electrical cooperatives: integrated resource plan.

Spectrum: Partisan Bill (Republican 5-0)

Status: (Passed) 2017-07-31 - Chaptered by Secretary of State - Chapter 140, Statutes of 2017. [AB759 Detail]

Download: California-2017-AB759-Introduced.html


CALIFORNIA LEGISLATURE— 2017–2018 REGULAR SESSION

Assembly Bill No. 759


Introduced by Assembly Member Dahle

February 15, 2017


An act to amend Section 454.52 of the Public Utilities Code, relating to electricity.


LEGISLATIVE COUNSEL'S DIGEST


AB 759, as introduced, Dahle. Electricity: electrical cooperatives: integrated resource plan.
Existing law requires the Public Utilities Commission to adopt a process for each load-serving entity to file an integrated resource plan, and a schedule for periodic updates to the plan to ensure that load-serving entities meet specified requirements. Existing law requires each load-serving entity to prepare and file an integrated resource plan consistent with certain requirements on a time schedule directed by the commission and subject to commission review.
This bill would provide that, for a load-serving entity that is electrical cooperative, the above requirements only apply if the electrical cooperative has an annual electrical demand exceeding 700 gigawatthours, as determined on a 3-year average commencing January 1, 2013.
Vote: MAJORITY   Appropriation: NO   Fiscal Committee: YES   Local Program: NO  

The people of the State of California do enact as follows:


SECTION 1.

 Section 454.52 of the Public Utilities Code is amended to read:

454.52.
 (a) (1) Commencing in 2017, and to be updated regularly thereafter, the commission shall adopt a process for each load-serving entity, as defined in Section 380, to file an integrated resource plan, and a schedule for periodic updates to the plan, to ensure that load-serving entities do the following:
(A) Meet the greenhouse gas emissions reduction targets established by the State Air Resources Board, in coordination with the commission and the Energy Commission, for the electricity sector and each load-serving entity that reflect the electricity sector’s percentage in achieving the economywide greenhouse gas emissions reductions of 40 percent from 1990 levels by 2030.
(B) Procure at least 50 percent eligible renewable energy resources by December 31, 2030, consistent with Article 16 (commencing with Section 399.11) of Chapter 2.3.
(C) Enable each electrical corporation to fulfill its obligation to serve its customers at just and reasonable rates.
(D) Minimize impacts on ratepayers’ bills.
(E) Ensure system and local reliability.
(F) Strengthen the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities.
(G) Enhance distribution systems and demand-side energy management.
(H) Minimize localized air pollutants and other greenhouse gas emissions, with early priority on disadvantaged communities identified pursuant to Section 39711 of the Health and Safety Code.
(2) (A) The commission may authorize all source procurement for electrical corporations that includes various resource types including demand-side resources, supply side resources, and resources that may be either demand-side resources or supply side resources, taking into account the differing electrical corporations’ geographic service areas, to ensure that each load-serving entity meets the goals set forth in paragraph (1).
(B) The commission may approve procurement of resource types that will reduce overall greenhouse gas emissions from the electricity sector and meet the other goals specified in paragraph (1), but due to the nature of the technology or fuel source may not compete favorably in price against other resources over the time period of the integrated resource plan.
(b) (1) Each load-serving entity shall prepare and file an integrated resource plan consistent with paragraph (2) of subdivision (a) on a time schedule directed by the commission and subject to commission review.
(2) Each electrical corporation’s plan shall follow the provisions of Section 454.5.
(3) The plan of a community choice aggregator shall be submitted to its governing board for approval and provided to the commission for certification, consistent with paragraph (5) of subdivision (a) of Section 366.2, and shall achieve the following:
(A) Economic, reliability, environmental, security, and other benefits and performance characteristics that are consistent with the goals set forth in paragraph (1) of subdivision (a).
(B) A diversified procurement portfolio consisting of both short-term and long-term electricity and electricity-related and demand reduction products.
(C) The resource adequacy requirements established pursuant to Section 380.
(4) The plan of an electric service provider shall achieve the goals set forth in paragraph (1) of subdivision (a) through a diversified portfolio consisting of both short-term and long-term electricity, electricity-related, and demand reduction products.
(c) To the extent that additional procurement is authorized for the electrical corporation in the integrated resource plan or the procurement process authorized pursuant to Section 454.5, the commission shall ensure that the costs are allocated in a fair and equitable manner to all customers consistent with 454.51, that there is no cost-shifting among customers of load-serving entities, and that community choice aggregators may self-provide renewable integration resources consistent with Section 454.51.
(d) In order to eliminate redundancy and increase efficiency, the process adopted pursuant to subdivision (a) shall incorporate, and not duplicate, any other planning processes of the commission.
(e) This section applies to an electrical cooperative, as defined in Section 2776, only if the electrical cooperative has an annual electrical demand exceeding 700 gigawatthours, as determined on a three-year average commencing with January 1, 2013.

feedback